OPINION
We granted this petition for review, brought by Sunland Drywall, Inc. (Sun-land), to determine whether a subcontractor’s mechanic’s lien filed on a multi-building condominium project is timely, under A.R.S. § 33-993(A), when filed within sixty days of completion of the last work done on any building in the project. Rule 23, Ariz. R.Civ.App.P., 17B A.R.S. We have jurisdiction pursuant to article 6, § 5(3) of the Arizona Constitution and A.R.S. § 12-120.-24.
FACTS AND PROCEDURAL HISTORY
The facts in this case are undisputed and are set forth in detail in the court of appeals’ opinion.
S.K. Drywall, Inc. v. Developers Financial Group, Inc.,
DFG hired Drongo, Inc. (Drongo), a general contractor, to construct the eleven buildings and other improvements. In a contract dated October 30, 1985, Drongo agreed to complete the work on the eleven buildings for a total sum of $3,241,320. Article 3 of the contract states that the total sum was determined from a schedule of values, which was attached to the contract, that categorized the work to be performed and its price.
Drongo subcontracted with Sunland for drywall and stucco work on the project. Sunland agreed to do the drywall work on all eleven buildings for a total sum of $211,100 and the stucco work for a total sum of $172,000. In both cases, the contract price was determined by a breakdown of the price per building, in recognition of the fact that some buildings contained more units than others.
The terms of Sunland’s drywall and stucco contracts (Sunland contract) are similar to those of DFG’s contract with Drongo (DFG contract). Sunland was to receive monthly progress payments based on ninety percent of the current month’s completed labor, materials, and equipment costs. In both the DFG and Sunland contracts, billing applications for the monthly progress payments were to be submitted with lien waivers for the previous month’s payments. The ten percent retention on each building was payable within thirty days of occupancy of any unit in the building and not more than ninety days after acceptance of the building by the owner. Sunland provided drywall labor and materi
In January 1987, Drongo quit work on the project and filed for bankruptcy. Sun-land then ceased work on the project. Sun-land properly recorded and served an amended notice and claim of lien for work done on the project. Pursuant to A.R.S. § 33-1004, DFG procured a lien discharge bond from Fidelity & Deposit Co. of Maryland in the amount of $38,591.33. 1 In the trial court, the parties stipulated to the following schedule of completion dates and charges for Sunland’s drywall and stucco labor and materials:
BUILDING DATE COMPLETED AMOUNT
Building 7 May 5, 1986 3.448.73
Ramada May 15, 1986 212.70
Building 8 July 1, 1986 2.089.73
Building 9 July 18, 1986 2.089.73
Building 5 November 4, 1986 6,990.63
Building 6 January 9, 1987 8,032.84
Sunland’s lien was filed March 4, 1987, fifty-four days after completion of work on building 6. DFG argued that the lien was invalid as to all of the buildings, and that it was untimely as to all of the buildings except building 6. On cross-motions for summary judgment, the trial court granted judgment to Sunland.
On appeal, the court of appeals held the lien valid, but a majority held that the lien was time-barred as to all buildings except building 6 under A.R.S. § 33-993, which provides that a lien is timely if filed “within sixty days after the completion of a building, structure or improvement.” The court stated:
Although we do not rule out the possibility that a multi-building project could be deemed an “improvement” within the meaning of A.R.S. § 33-993 on appropriate facts, no such facts are present here. The contractual arrangements between the parties in this case, and the manner in which the buildings in DFG’s condominium development were actually constructed, require the conclusion that each constituted a separate “building” within A.R.S. § 33-993. Accordingly, building 6 was the only one as to which Sunland’s notice and claim of lien was timely filed.
[t]his was a single project, the subject of a single contract to be executed in phases, and Sunland Drywall was entitled to protect itself through a single lien over all of the buildings on which it did work.
Id.
at 603,
We granted Sunland’s petition for review to decide whether the subcontractor’s mechanic’s lien on this multi-building condominium project was timely when filed within sixty days of the last work performed on the project.
DISCUSSION
Mechanics’ liens are creatures of the governing statutes. 53 Am.Jur.2d
Mechanics’ Liens
§ 2 (1970 & Supp.1991). We must first determine, therefore, whether the Arizona statute permits a single lien to be filed on a multi-building condominium development. If the statute permits such a lien, the next question is whether the development was built as a single project or whether different phases of construction were contemplated as distinct and separate projects.
See Northwest Fed. Sav. & Loan v. Tiffany Constr. Co.,
A. Can a multi-building development be an “improvement” under the statute?
The mechanic’s lien statutes, A.R.S. § 33-981
et seq.,
give those who furnish labor or materials to enhance the value of another’s property the right to place a lien on the property for the value of the improvements.
Wahl v. Southwest Sav. & Loan Ass’n,
Other states that have considered this issue have held that condominium developments constitute a single work of improvement.
See
9 CONSTRUCTION LIT.REP. 148 (1988) (citing
E.D. McGillicuddy Constr. Co. v. Knoll Recreation Ass’n,
The Texas statute, under which the
Habitat
case was decided, is very similar to ours. The analogous provision for placing the lien provides that the lienor shall, within ninety days, give notice to the owner of the house, building, or
improvement
for which the labor and materials were furnished. Tex.Rev.Civ.Stat.Ann. § 5453 (Vernon 1958 & Supp.1991).
2
Section 5452 defines “improvement” broadly but does not specify that it may include multi-building projects. The court in
Habitat
noted the general rule that “if the improvement is made under an entire contract for the whole and is located on one body of land, it is one improvement, though there are several separate structures.”
Arizona case law supports reading the term “improvement” to encompass a multibuilding project. In Lewis v.
Midway Lumber, Inc.,
the court of appeals defined improvement as a “catch-all” term that refers to the “subject of construction,” specifically, a “valuable addition or betterment to real estate such as a building, clearing, drain, fence, etc.”
Thus, where construction of a multibuilding project constitutes a “single project,” a single mechanic’s lien may be filed on the project and is timely if filed within the statutory period dating from the time the last item of work was performed or the last material was furnished.
3
See Gene McVety, Inc. v. Don Grady Homes, Inc.,
B. The single project theory
We turn, then, to the question of whether Sunland performed the drywall and stucco work on the condominium development as a single project. In Gene McVety, this court considered the single project theory in deciding whether a materialman had timely filed a lien against a subdivision when the lien was filed within sixty days of the project’s completion but more than sixty days after its acceptance. The project in that case consisted of water and sewer improvements to a subdivision. Gene McVety supplied materials for the project as a whole, unaware that the work would be performed under two contracts between the owner and the contractor. This court found that the materialman had supplied materials to a single project, stating:
It is, of course, the rule that two or more contracts cannot be tacked together so as to extend the time within which a lien notice must be filed____ This case is not, however, governed by the foregoing rule. Where work, distinct in nature, is performed at different times, the law supposes that it is performed under distinct contracts. But when work is done or materials furnished, all going to the same general purpose, if the several parts form an entire whole or are so connected together as to show that the parties had it in contemplation that the whole would form but one and not distinct matters of settlement, the whole must be treated as a single contract.
Gene McVety,
Courts examine various factors to determine whether work was performed on a single project. Annotation,
Mechanic’s Lien for Work on or Material for Separate Buildings of One Owner,
Accordingly, most courts hold that where work is performed on several structures under a single contract, a single lien may be filed within the statutory period from the date of the last work performed or last materials supplied.
See, e.g., Cline-Hanson, Inc. v. Esselman,
Sunland argued in its motion for summary judgment that the multi-building project was an improvement for the purposes of A.R.S. § 33-993, and that its lien filed within sixty days of completing work on building 6 was timely as to the project as a whole. The trial court granted Sun-land summary judgment. Minute Entry, March 16, 1988. The court of appeals’ majority, however, conducted an exhaustive analysis of the administrative details of the Sunland contract, and concluded that the contract was in fact a series of separate contracts to complete work on and collect payment for each individual building. Thus, there was not a single improvement, and Sunland’s lien was timely filed only with respect to building 6.
S.K. Drywall,
In examining the contractual relationship between the parties, we look first to the contract between the owner and the general contractor, which forms the basis for Sunland’s mechanic's lien against the project. DFG and Drongo entered into a single contract to construct a multi-building condominium development for a lump sum. The lump sum was determined from a schedule of values detailing each category of the project and the prices assigned for the work and materials involved.
Sunland’s drywall and stucco contracts mirror the structure of the DFG contract. Sunland agreed to do the drywall and stucco work on all of the buildings for lump sums to be paid as the work progressed. The contracts contained schedules detailing the value of the work for each building, as some buildings contained more units than others. The mere fact that a total contract sum is arrived at by assigning a value to each structure does not, in itself, turn a “single contract” into one severable as to each structure.
Will B. Miller Co.,
DFG asserts that because the work was “performed and paid for on a building-by-building basis” and materials were supplied by Sunland to each building separately, Sunland was required to file a lien on each building. Response to Petition for Review at 8. Although billing statements were apparently generated for each building, both the DFG contract and the Sunland contract called for monthly progress payments based on ninety percent of the current month’s completed labor, materials, and equipment costs. DFG admits that certain buildings were under construction simultaneously. Thus, according to the contracts, each month’s progress payment could cover work on more than one building. Only the ten percent retention was tied to each building, payable within thirty days after occupancy of “any
unit
in a given building and not more than ninety (90) days after acceptance of each
building
by the owner.”
S.K. Drywall,
We fail to see how these terms can be construed as representing payment on separate contracts on a per-building basis. Rather, it appears that the payment schedule was structured for administrative efficiency in an ongoing effort to complete the entire development.
Cf. Mathis v. Thunderbird Village, Inc.,
The terms of the DFG and Sunland contracts indicate that the parties believed work on the condominium development would be undertaken as a single project, executed in phases as the buildings were completed, with payment provided on a monthly basis. The development was on one tract of land and had a unified concept of use and design. The DFG contract obligates the developer to proceed with, and the contractor to complete, all eleven buildings in one continuous course of construction, specifying that the “work” required by the contract is “completion of the project” according to the relevant specifications. DFG Contract, Art. 1, Appendix to Response to Petition for Review. The estimated time for completion of the entire eleven-building project was listed as fourteen months. Id., Art. 2.
The numerous details pointed to by the court of appeals, such as the delivery of building materials to each building rather than a common delivery site, the recording of a plat map for the condominium project, and the issuance of separate building permits and start orders for each building, are certainly not inconsistent with the concept that the contract was entire and nondivisible. Building permits are governed by city code requirements, and the issuance of start orders and the delivery of supplies are, as the dissenting judge in the court of appeals noted, merely “differing administrative details” of the overall contract.
S.K. Drywall,
C. Equitable considerations
In enacting the mechanic’s lien statutes, our legislature “intended that laborers and materialmen, who contribute of their labor and means to enhance the value of the property of another, should be jealously protected.”
Wahl,
The statutory scheme protects the property owner by requiring a person who has
The statute also protects property owners by requiring that mechanics’ liens be filed within a specific period of time following the completion of construction. A.R.S. § 33-993(A). The purpose of the timely filing requirement is “to give the property owner an opportunity to protect himself and time to investigate the claim to determine whether it is a proper charge.” Lewis,
Moreover, DFG entered into a single contract with Drongo for the construction of the entire condominium project. The initial determination of whether the development would be a single project or a series of projects was thus “a matter within the control of the property owner.”
In re Waller Creek, Ltd.,
In contrast, the record reveals nothing that would have put Sunland on notice that work on each building would be furnished under a separate and distinct contract and that the condominium development was not a single project. A “mechanic’s lien can be limited only when the contractor is able to determine which lot will stand as security for its construction efforts.”
Waller Creek,
A contrary result would lead to multiple problems. First, each case would turn on detailed and often unique facts. The court of appeals, for instance, distinguished the twenty-four building apartment complex in
Wahl
from the condominium development in this case by focusing on the differing administrative provisions in the contract, as well as on such ambiguous factors as whether the project had a common laundry facility and whether units would eventually be sold or rented.
S.K. Drywall,
Second, under the court of appeals’ approach, prudent contractors would be forced to file separate liens as each building or unit is completed in order to ensure their timeliness. Aside from the inconvenience to potential lienors, this process would require courts to handle multiple actions on successive phases of the same contract and/or project. In this case, for example, Sunland would have had to record a mechanic’s lien on the first building completed and file an action to foreclose on
Finally, under both the contract and the subcontract, the ten percent retentions on a given building could be withheld for up to ninety days after DFG accepted the building. If, as the court of appeals held, Sun-land was required to record its lien within sixty days of completing a given building, the limitations period for foreclosing the lien could begin to run even before the retention was payable under the contract. We believe such results to be inconsistent with the intent of A.R.S. § 33-993 and the case law interpreting this statute.
CONCLUSION
A multi-building condominium development may constitute a single improvement within the meaning of A.R.S. § 33-993(A). When construction on the development was contemplated as a single project, a contractor is entitled to file a single lien within the statutory period after the last work is performed on the development. The development in question was an improvement within the contemplation of the mechanic’s lien statute and was a single project involving construction of a multi-building condominium complex. Sunland properly filed its mechanic’s lien within sixty days after the last work was performed on the project.
We vacate that portion of the court of appeals’ opinion holding Sunland’s lien untimely with respect to each building except building 6. We affirm the trial court’s judgment that the lien was timely as to all buildings listed in Sunland’s notice and claim of lien.
Notes
. The effect of the bond, when recorded, was to discharge the real property of the lien and provide for recovery, if any, to be satisfied from the bond. See A.R.S. § 33-1004.
. Sections 5452-5456 were repealed in 1983, after the Habitat case was decided, when the Texas property code was enacted. Tex.Rev.Civ.Stat. Ann. §§ 5452-5456 (Vernon 1958 & Supp.1991).
. The parties in this case stipulated to the date of completion.
See
A.R.S. § 33-993(B);
cf. Egan-Ryan Mechanical Co. v. Cardon Meadows Dev. Corp.,
.
See also Shepherd Plumbing & Heating Co. v. Bedford,
.
See also Knauft v. Miller,
In certain circumstances, however, other facts may indicate that the work comprised a single project or transaction despite the existence of separate contracts — for example, where the contracts were with the same owner, the construction was for the same purpose, and the buildings were constructed on the same lot or on contiguous lots.
See generally
53 Am. Jur.2d
Mechanics’Liens
§ 258, at 788 (1970);
cf. Standard Lumber Co. v. Fields,
. Building 7 was completed on May 5, 1986. Under the court of appeals’ holding, Sunland would have had to record its lien on building 7 within sixty days, or by approximately July 5. The mechanic’s lien statute limits the time for foreclosure of a mechanic’s lien to six months from the date of recording. A.R.S. § 33-998. In this case, then, Sunland would have had to foreclose on building 7 by approximately January 5, 1987, but Sunland was working on building 6 until January 9, 1987.
