284 F. 227 | 3rd Cir. | 1922
This is a proceeding by the plaintiff in error to review the judgment of the District Court based on the verdict of a jury, awarding damages for breach of a contract. By its terms defendant agreed to sell and plaintiff to purchase 50,000 tons of coal, 25,000 tons of two-inch screenings at $2.40 per ton, and 25,000 tons of larger prepared sizes at $3.50 per ton, between May 10, 1920, and April 1, 1921, “in equal monthly installments.” The Contract provided that, since the amount of coal contracted for was about one-third of the production of the Bell Union mines, in case there was “a severe car shortage or other causes” reducing the production of the mines, the amount to be shipped on the contract was to be one-third of the output of the mines. Settlement was to be made on the 15th day of the month for all coal shipped during the preceding month.
The contract was executed April 14, 1920. In May, 1920, the defendant shipped 14 cars of coal, averaging 47 tons per car. This was not paid for on June 15th, but $1,873.48 was paid on June 17th, and the balance of $1,644.20 was paid on June 24th. In June the defendant shipped 41 cars, averaging 42 tons per car, which was valued at $5,318.81. The president of the defendant company testified that, on or about July 8th he told Mr. Pagenkopf, sales manager of the plaintiff company, that instead of paying on the 15th of June, plaintiff paid one part on June 17th and the other part on the 24th; that he did not want that to occur again, and, if it did, “this contract will be canceled automatically. * * * Get this; Í must have my money or the contract is canceled.” The June deliveries, however, were not paid for until July 21st, and then only after defendant wrote on July 17th, saying that it was disappointed in not receiving the check, and asking that it be sent by return mail, and again two days later stating that, “We ,need our money, and we need it on the 15th of the month.” After some contentions between the parties following this payment, the defendant refused to ship any more coal to the plaintiff, on the ground
The plaintiff contends, inter alia, that the defendant had already breached the contract by its failure to ship either the monthly installments from May 10th to1 June 30th, or, since there was a severe car shortage, one-third the output of the mines to which it was entitled under the contract during that time, and therefore defendant itself had no right to breach the contract, even though the plaintiff was in default in monthly payments. It further contends that, in addition to its own breach, defendant waived any default on the part of the plaintiff by accepting the check on July 21st. There are many assignments of error, but this case turns upon who breached the contract.
The failure of the plaintiff to pay on the 15th of June and July was not induced by defendant’s alleged failure to make the required deliveries, for the plaintiff did not know that it had not received one-third of the output of the mines from May 10th to June 30th until some time in the month of August. If the plaintiff did not receive one-third of the output during that time, if it had known that fact, it could have rescinded the contract and sued for damages, or affirmed the contract and deducted the amount it had lost because of short deliveries from what it owed defendant for the coal already delivered, and then paid the difference. In ignorance of the alleged short deliveries, it could do neither, but it could and should have paid for the June deliveries on July 15th. This it deliberately failed or refused to do, though defendant was actually clamoring for its money due on the coal it had delivered. It now seeks to justify its failure to pay in accordance with the contract by the defaults of the defendant of which it was at that time ignorant. In other words, it argues that one breach justifies another, and when both parties to a contract separately breach it, one breach neutralizes the other, and results in the affirmance of the contract; that the second breach, deliberately made in ignorance of the first, cures the first, and the contract stands just as though no breach had been made, in spite of the determination of the party damaged by the second to terminate it. We are unable to 'assent to this proposition. One breach has no neutralizing effect upon the other. The party injured by a breach may disregard it or terminate the contract, but he may not ignore it and plead it as an offset to his own breach.
Payment at the stipulated times was very important to defendant. In conducting its large business it had to know whence it would get money to meet its obligations. Time of payment was of the essence of the contract. Hull Coal & Coke Co. v. Empire Coal & Coke Co., 113 Fed. 256, 51 C. C. A. 213; Grigg v. Landis, 19 N. J. Eq. 350; Shin et al. v. Roberts, 20 N. J. Law, 436, 43 Am. Dec. 636; Owen v. Giles et al., 157 Fed. 825, 85 C. C. A. 189; Meier Dental Mfg. Co. v. Smith et al., 237 Fed. 563, 150 C. C. A. 445; McFarland v. Savannah River Sales Co., 247 Fed. 652, 656, 159 C. C. A. 554. The general rule of law is that, where time is of the essence of the contract, performance after such time is not a performance of the contract, unless assented to by the other party, 13 Corpus Juris, 681, and failure of the plaintiff to pay on July 15th was not assented to.
As an element of damage plaintiff contends that, however the questions of waiver and breach for nonpayment on July 15th may be determined, it is entitled to the difference between the contract price and the market price of coal on that portion of the one-third of the output of the mines which it alleges the defendant failed to deliver to it from May 10, 1920, to June 30, 1920.
As already stated, the evidence establishes, and we take it to be admitted, that the price of coal' was higher during that period or on May 31st and June 30th, the days when plaintiff, according to its contention, had the right to demand that the full one-third of the coal mined that month be shipped, than the contract price, though there is a difference among the witnesses as to exactly how much higher it was. It is admitted that there was a severe car shortage in May and June. The plaintiff, contending that it had been established by undisputed evidence that defendant did not ship to it one-third of the output of the mines from May 10, 1920, to June 30, 1920, requested the trial judge to charge that:
“Under all tlie evidence you must find that plaintiff is entitled to damages for the defendant’s failure to deliver one-third of his admitted output to plaintiff for the period May 10 to May 31, 1920, and for the month of June, 1920.”
The request was refused. The contract provided that the defendant agreed to sell and the plaintiff to purchase 50,000 tons of coal between May 10, 1920, and April 1, 1921, “in equal monthly installments.” The paragraph of the contract containing this provision presumed normal conditions, and the 50,000 tons purchased were doubtless to be shipped “in equal monthly installments” during the contract period. But the contract provided also for abnormal conditions:
“Should there be a severe car shortage or other causea( beyond the control of the Bell Union Coal & Mining Company, by which the production in said mines is reduced, the amount of- coal shipped on this contract shall be one-third of the output.”
It is significant that this paragraph does not contain the provision of “equal monthly installments.” During such abnormal times, the defendant by such omission saw to it that the contract did not obligate it
We have carefully considered' all the other assignments of error, but do not find error in any of them, and therefore the judgment of the District Court is affirmed.