347 Mass. 655 | Mass. | 1964
This is a bill in equity brought by the buyer for the specific performance of a contract to sell land. The judge filed a report of material facts. From a decree granting relief to the plaintiff the defendant has appealed. The evidence is reported.
Lots B and C occupied respectively the southwestern and southeastern corners of a large undivided tract of land (lot 15) owned by Enterprise under a registered land title. Lot 15 ran from the Revere Beach Parkway south to the Mystic River. The parties contemplated that Enterprise would build a road from the Revere Beach Parkway to the Mystic River along the western edge of lot 15. The sale and option of lots B and C were predicated in part upon the filing with and approval by the planning board of Medford (board) of a subdivision plan of lot 15. A private road connecting lot B to the public road system was necessary in order to secure board approval. Such approval was also required in order to record a deed to lot B in the land registration office. Attached to and made a part of the agreement of sale was a drawing entitled “Plan of Land Russo’s Marine Mart” (the attached plan), which showed lots B and C, the remaining portion of lot 15, and the contemplated road designated as a “50' roadway.” The agreement contains the following: ‘ ‘ There is to be excepted from the premises to be conveyed [lot B] so much thereof as may be required by the Seller so as to comply with the requirements of the Planning Board of . . . Medford ... so as to validate the creation of the proposed street running from Revere Beach Parkway substantially as shown on said plan [and] obtain the approval by said Planning Board ... of the plan to be filed with the Planning Board creating said proposed street so that the same may be filed for registration with Middlesex South Registry District so as to permit the Seller to subdivide its remaining land shown on
Enterprise had submitted to the board in 1959 a subdivision plan (the initial plan) drawn for it by one H. J. Nicholson, an experienced civil engineer and a former consultant to the board. On October 15, 1959, the board first informed Enterprise that the proposed roadway would have to be widened from 50 feet to 60 feet. Before submission of the initial plan Nicholson had estimated that an expenditure of between $30,000 and $40,000 would be sufficient to secure board approval of the plan. There is no evidence that such an estimate was ever communicated to Russo. In addition to the 60 foot roadway the board requested that other changes be made in the initial plan involving expense
A board hearing on a revised definitive plan submitted by Enterprise and dated February 5,1960, which embodied the changes as requested, was held on April 27, 1960. Shortly thereafter the board tentatively approved the revised plan. Final approval could not be granted until either a construction bond was posted by Enterprise or the road and other improvements were actually constructed. The bond has never been posted nor the road ever constructed. As a result the application for approval was dismissed by the board without prejudice on September 13,1961.
Extensions of the time of performance of the contract running until January 31,1962, were mutually agreed upon by the parties. Since that date Enterprise has regarded its contractual obligation at an end.
On September 6,1960, the parties agreed that “until September 7, 1961, or until the aforesaid purchase and sale agreement, as amended, is terminated, whichever event occurs first, ’ ’ Russo should have the right to occupy and improve lots B and C. The plaintiff went on the premises, dredged the land, put in fill, made considerable grading of a large area so as to make it usable for his operation . . . built a [mjarina and hot-topped the roadway leading into the same . . He spent some $53,500 on these improvements until March 6, 1962, as indicated by evidence which was properly admitted.
The final decree ordered Enterprise to resubmit the definitive plan dated February 5, 1960, to the board for
1. The judge correctly concluded that Enterprise was obligated by contract to construct “the proposed street running from Revere Beach Parkway substantially as shown on said plan.” While the purchase and sale agreement does not contain an express promise by Enterprise to build the street, such an obligation was clearly intended by the parties. “An omission to express an intention cannot be supplied by conjecture. But if the instrument as a whole produces a conviction that a particular result was fixedly desired although not expressed by formal words, that defect may be supplied by implication and the underlying intention . . . may be effectuated, provided it is sufficiently declared by the entire instrument. ’ ’ Dittemore v. Dickey, 249 Mass. 95,105. Spaulding v. Morse, 322 Mass. 149,152-153. See Proctor v. Union Coal Co. 243 Mass. 428; Eno Sys. Inc. v. Eno, 311 Mass. 334, 338-340.
For this reason we are also of opinion that with respect to the drainage system and other improvements required by the board, Enterprise was obligated to do whatever was necessary to “obtain the approval by . . . [the board] of the plan to be filed with the . . . [board].” We note in this connection: (1) the board notified Enterprise prior to J anuary 11,1960, of the changes to be required in the initial plan before approval; (2) the contract provides that Russo was obligated to pay a percentage “of the cost to the Seller for the installation of water and other utility lines, sewerage and drainage lines”; (3) Enterprise itself acknowledged, again prior to J anuary 11,1960, that these other improvements could cost $75,000; and (4) the $30,000-$40,000
2. We must next decide whether in all the circumstances here presented a street 60 feet wide conforms “substantially” to one of 50 foot width. Enterprise knew before the signing of the contract that the wider road would be required. Thus the question of whether it did conform substantially to that drawn on the attached plan had been posed to the defendant. We must presume that both parties signed the agreement intending in good faith to be bound by it. See Shayeb v. Holland, 321 Mass. 429, 432. In our view, only a belief real or constructive on the part of Enterprise that there was a substantial conformity is consistent with its execution of the contract in good faith. Believing otherwise the defendant would knowingly have been signing an agreement containing a readily available avenue of relief from its contract obligation.
Furthermore, the contract “ except [s] from the premises to be conveyed so much thereof as may be required by the Seller so as to comply with the [board] requirements . . . so as to validate . . . the proposed street” (emphasis supplied), and lot B is described as bounded on its western side by the eastern edge of that street shown on the attached plan as 50 feet wide. Thus the contract itself seems to recognize that there is a range of permissible increase in the street dimension set forth in the attached plan. In this circumstance a 20% increase in width of the road does not seem so large as to make it in its new dimension “substantially” nonconformable with that originally planned.
3. The defendant argues that a line of cases from Old Colony Trust Co. v. Chauncey, 214 Mass. 271, to Barrett v. Carney, 337 Mass. 466, bars specific performance here. These cases construe the provision, “ [i]f the Seller shall be unable to. give title or to make conveyance as herein stipulated, then ... all other obligations of the parties hereto shall cease and this agreement shall be void,” to mean that the seller who is without fault has no duty to make reasonable efforts to remove defects in title prior to the date of performance. The line is inapposite. Here Enterprise
Enterprise contends that the order to construct a roadway of 60 foot width with improvements is defective because compliance with it is contingent upon the consent of third party abutting landowners not before this court. The factual basis for this contention does not appear in the record.
4. The defendant’s counterclaim based upon a wrongful occupancy after the expiration of the September 6, 1960, license was properly dismissed. Enterprise may not capitalize on the result of its own breach of contract.
5. In summary, the plaintiff seeks only to compel Enterprise to do that which it contracted to do, and in the light of the foregoing the order must be
Decree affirmed with costs of appeal.
By a supplementary document the buyer’s 20% share was amended to 10% and Enterprise later wrote to Busso: “It is understood and agreed that your 10% share ... is to be based on the cost of such installation up to $75,000.”