114 Mo. App. 488 | Mo. Ct. App. | 1905
On July 21, 1903, defendant, a common carrier, received at Council Bluffs, Iowa, two cars of oats which it undertook, for a consideration, to transport to Kansas City and there deliver to R. J. Thresher, the consignee named in the bill of lading. On the morning of the 28th inst. defendant notified consignee, who was in the grain business at Kansas City, of the arrival of the cars. Following usual custom defendant had placed them, on arrival, upon a side track in its yards in Harlem across the river, awaiting inspection by the grain inspector, and orders for disposition by the consignee.
Delivery of grain billed to Kansas City was customarily made either by turning the cars over to a connecting carrier at the yards in Kansas City, or by placing them upon a “team track” in said yards, for unloading into wagons. After the inspection of the oats the consignee was furnished by the inspector with a sample from each car, and on the same day, July 28th, sold both carloads, by sample, to plaintiff, another grain dealer in Kansas City. Shortly after the sale was consummated Thresher and plaintiff both telephoned defendant’s agent in charge of its Kansas City freight office, notifying him of the sale and instructing him to have the cars switched upon the team track as soon as possible, for unloading. This he agreed to do without objection or question of any kind. Plaintiff states that the agent agreed to have the cars on the team track by ten o’clock the following morning (the 29th inst.), but the latter, though admitting his unconditional promise to deliver them as requested, denied that he agreed to have them switched in the time stated by plaintiff. Although repeatedly urged by plaintiff to switch the cars sooner, they were not placed upon the team track until August
Plaintiff recovered judgment and defendant appealed.
The first error assigned relates to the sufficiency of the allegations in the petition to constitute a cause of action. In the first count it is charged “that the defendant is and was, at all such times, a common carrier of goods for hire, owning and operating a line of railroad extending in and from the city of Kansas City, Jackson county, Missouri, and elsewhere, and that as such common carrier of goods for hire, it is and was the duty of said defendant to safely convey, transport and deliver, within a reasonable time, any and all goods accepted for shipment. Plaintiff says that it is and was the further duty and custom of this defendant to maintain a place in Kansas City, Missouri, where all consignees and this plaintiff in particular might unload freight or goods Avith some degree of convenience and that such place is usually designated a team track. Plaintiff further says, that on or about July 28, 1903, the said defendant at Kansas City, Missouri, was in possession of 47,680 pounds of oats contained in car No. 61463 N. Y. C. (as a common carrier of goods for hire), belonging to plaintiff. Plaintiff further says that on or about July 28, 1903, plaintiff instructed this defendant to deliver said oats to defendant’s team track but that said oats were not delivered until on or about August 10, 1903.” The
Defendant says the statement alone that it was in possession, as a common carrier of goods for hire, of a car of oats belonging to plaintiff, is not the affirmation of a fact but a conclusion of law. Every fact constitutive of the cause of action must he pleaded to entitle the plaintiff to adduce proof thereof. A conclusion of law cannot take the place of constitutive facts for the reason that it is a mere consequence following the existence of predicative facts, and therefore cannot even tend to establish that which is necessary to call it into action. But defendant evidently has fallen into the common error of mistaking an inference of fact for a conclusion of law. That an ultimate fact upon which may rest the whole fabric of the cause of action pleaded is not susceptible of direct proof, but must result as a corollary from other facts, does not make of it anything but a fact and certainly does not call for the statement in the petition of the means by which its existence is to be established. Its incorporation into the statement of elemental facts apprises the defendant of the nature of the relation it bears to the cause of action asserted, and the character of the proof necessary to sustain or overthrow it, and this complies with the requirements of good pleading. It follows that the averments under consideration must be held to be the statement of constitutive facts and not conclusions of law.
Nor do we think the petition is deficient in the allegations relating to the obligation of the defendant to deliver the oats upon the team track. Reasonably construed, the language employed means that defendant unreasonably delayed putting the cars in the proper place for unloading after they had reached their destination. It is the duty of the common carrier not only to safely carry property to its destination, but to take it to the
Defendant insists that under the facts in evidence it was under no duty to plaintiff to take cars from the Harlem yards to the team track, for the reason that plaintiff had no contract with it. A sale of the oats by the consignee to the plaintiff, while they were in the yards at Harlem, carried with it, as an incident, the rig'hts the former had under the contract of affreightment. To say otherwise would be to take a property right from the consignee and give it to the. carrier. It is conceded that had Thresher remained the owner of the-oats, defendant was under duty to place the cars upon the team track at his direction, without additional charge. No reason is apparent for releasing the carrier from the performance of this or any other duty under its contract by the fact of the sale of the property while in transit.
Nor is any merit to be found in the suggestion that plaintiff’s right to require the defendant to carry out its contract is affected by the failure to prove an assignment of the bill of lading by the consignee to plaintiff. The possession of this instrument, by plaintiff, duly assigned would have been an evidence of plaintiff’s ownership and right to possession of the property, and of its right to be substituted as consignee, but it was not indispensable to the transfer of any or all of the rights mentioned. Such transfer could have been otherwise evidenced. Whatever may have been the right of the defendant to require the production and surrender of the bill of lading before delivering the oats, it is not now in a position to base any claim upon such right. From the time of the announcement of the sale it recognized plaintiff as the rightful owner of the property, and made delivery to him without requiring further proof of the transfer of title than a verbal statement of the vendor and vendee, and without asking for the production and
The court instructed the jury on behalf of the plaintiff as follows: “You are instructed that it was the duty of the defendant railway company to transfer and deliver the property in question, to the place designated by the plaintiff, within a reasonable time and without unnecessary delay, and if you find from the evidence that the defendant did not so transport and deliver plaintiff’s property to the team track, designated by plaintiff, within a reasonable time and without unnecessary delay, then your verdict must be for the plaintiff for the difference in the market value in the property when it should have been delivered, and the market value of the property when it actually was delivered.” This instruction is criticized upon the ground that it ignores a substantial defense offered by the defendant. The defense referred to is pleaded in the answer and is supported by evidence. It is in substance this: On June 1, 1903, and for some days thereafter, a flood of unusual and extraordinary violence swept over the bottoms of the Missouri and Kansas rivers. Defendant’s yards at Kansas Oity and Harlem were inundated and so injured that it was impossible to operate them at all until after the 18th of June, and from then on for a period of several months, partly on account of the demoralized physical condition of the tracks and other facilities, and partly because of the congestion of business resulting from this abnormal condition defendant was greatly impeded and delayed in making deliveries of freight to its patrons. It is shown quite conclusively that the delay suffered by plaintiff in the moving of his cars of oats from Harlem to the team track was no more than that endured by every other shipper, and was not unreasonable under the conditions then prevailing.
The burden of proof is upon the owner of the goods to show their delivery to the carrier for delivery at a certain point, and the failure of the latter to deliver them in a reasonable time, under ordinary circumstances. The burden then devolves upon the carrier to show that the delay was caused either by some fortuitous happening that excuses delay, or that the shipper was informed, before delivery to the carrier, of the fact that prompt delivery could not be made. It was not shown that any notice of this kind was given to the shipper in this case, but to the contrary it appears that the shipment was accepted for delivery in the ordinary course of business. Defendant failed in its proof, and the fact of the demoralization of its yards at Kansas City, known by defendant to be at its height when the shipment was received, is no excuse for the delay. The instruction under consideration will be sustained because of this failure of proof. Other points are made but we deem none