160 Mo. App. 347 | Mo. Ct. App. | 1911
This suit is on a builder’s bond executed by defendant, a surety company, as a surety for hire. A jury was waived by agreement and, after hearing the evidence, the court made and filed findings of fact and conclusions of law on which it rendered judgment for the defendants. Plaintiffs appealed.
The facts of the case thus may be stated. Plaintiffs are husband and wife and in August, 1904, acting for himself and as the agent of his wife, the husband entered into a contract with defendant Anderson by the terms of which Anderson, who is a contractor, agreed to do the carpenter work and provide the materials therefor for an apartment building to be erected on lots in Kansas City owned by Mrs. Rule. The work was to be done according to plans and specifications in the office of the architect employed by plaintiffs and the contractor was to be paid $4,102.25 for the work at stated times and on the architect’s certificates. November 20, 1904, was fixed as the date for the completion of the work.
Among other provisions of the contract, which was in writing, were the following: ‘ ‘ Should the proprietor, at any time during the progress of the said works, require any alterations of, deviations from, additions to, or omissions in the said contract, specifications or plans, he shall have the right and power to
“No new work of any description done on the premises, or any work of any kind whatsoever shall be considered as extra unless' a separate estimate in writing for the same, before its commencement, shall have been submitted by the contractor to the superintendent and the proprietor, and their signatures obtained thereto, and the contractor shall demand payment for such work immediately it is done. In case of day’s work, statement of the same must be delivered to the proprietor at latest during the week following that in which the work may have been done, and only such day’s work and extra work will be paid for, as such, as agreed on and authorized in writing. ’ ’
Defendant, the National Surety Company, is a New York corporation engaged in the business of guaranteeing the fidelity of employees and contractors and authorized to transact business in this state. It maintains an office in Kansas City in charge of a district manager, and on October 4, 1904, at the request of Anderson, executed a bond at that office by the hand of the manager by which, in consideration of a premium paid by Anderson, it undertook to guarantee the performance of Anderson’s contract with plaintiffs. The building contract was referred to and made a part of the bond.
Among the stipulations of the bond were the fol lowing:
“If said principal shall in any manner default in the performance of any' matter or thing in said contract specified to be by said principal performed, or in the event of said principal abandoning the wort provided by said contract to be done by said principal, the obligee shall immediately so notify the company, and thereafter the company shall have the right' at its Option to assume and sublet said contract and to proceed thereunder as if no default or abandonment had occurred; and if the company elect to assume said contract, all moneys agreed therein to be paid said principal and which at the time of the default be due the principal shall thereupon become payable to the company, and shall be paid to it, anything to the contrary in said contract notwithstanding . . .
“If any changes or alterations by the principal and obligee be made in the terms of said contract or in the plans or specifications for the work mentioned in. said contract, the obligee shall immediately so notify the company of such changes or alterations giving a description thereof and stating the amount of money involved by such changes or alterations. . . .
“None of the conditions or provisions contained - in this instrument shall be deemed waived by the company unless the written consent to such waiver be duly executed by its president or vice-president and its seal be thereto affixed and duly attested; nor shall this instrument or any rights thereunder be assignable unless with like consent duly executed and attested as aforesaid . . k
The work was not completed until January, 1905, and plaintiff failed to give written notice of this default of Anderson until January 21, 1905. In answer to this notice, defendant’s vice-president in New York wrote plaintiffs as follows:
“Referring to your communication of the 21st inst., concerning your contract with'" Mr. R. II. Anderson of Kansas City, the contract required the completion of the work on or before November 20th, 1904. It appears from your letter that the work was not. completed at that date, but in fact was being continued up to about the date of your letter. It is assumed that Mr. Anderson was given an extension of time within which to complete; a careful examination of our papers fails to disclose any assent on our part to any such extension — if one has been granted, without our assent, all liability on our part to you ceased under the bond at the time such extension was granted. If no extension was granted, then you have not complied with the conditions of the bond on your part to be performed, in that you knew on November 20th, 1904, and previously to that date, that Mr. Anderson had not completed the work and did not intend to complete it by that date, and under the conditions of the bond it was your duty to forward in the manner and at the time required by the bond, written notice to us to that effect. This was not done, and for your omission so to do, under another condition of the bond, it was agreed that all liability should cease.
“We regret that you are placed in the position of being without security for that portion of the work which you say remains uncompleted, but the responsibility for this condition does not rest with us.”
November 10, 1904, plaintiffs paid Anderson the fifth architect’s certificate for $200 and on December 3, 1904, they paid him ninety dollars “on the next certificate.”
On or about December 1, 1904, plaintiff Charles D. Rule visited the surety company’s office again and inquired of Mr. Stewart what arrangements should be made about the pay roll of the carpenters. Mr. Stewart requested said plaintiff to pay the carpenters himself. On December 10,1904, plaintiffs paid Anderson “on next certificate” $134.40, on December 17, 1904, $118.60, on December 24, 1904, $131.40 and on December 31, 1904, $45.20.
We quote further from the findings of fact:
“The court finds that ‘2 inch’ lumber in this vicinity is under the universal custom 1% or 1 7-8
“The court finds that the following- requirements of the specifications have been omitted from the construction of the building- by agreement between plaintiff’s architect and defendant Anderson, without the knowledge of the surety company.
“Wooden beams over bay windows (iron beams supplied by plaintiffs) ........$ 5>.00
No. 2 lumber used on first floor instead . of No.' 1, difference ................ 10.00
False ceilings under front porch omitted 25.00' 10 sq. yds. gravel roof - used instead of
“Carey” difference ................ 9.00 Scotia on rear steps and kitchen moulding
omitted without leave.......•......... 5.00 21 feet of metal corner beams omitted .. 1.05
“The court finds that there were the following- additional .items of material and labor furnished by defendant Anderson at plaintiffs’ request not required by the plans and specifications, and of which the surety company had no knowledge:
“Labor laying extra felt between boards on 2nd and 3rd floors ..................$ 5.00
Picture moulding- on chimney breasts .... 1.00 Casing on transon openings in bathroom
closet on 3rd floor .................. 2.50
Scuttle in hall closet on 3rd floor........ 1.50
Countersinking Escutcheons on sliding-doors .............................. 3.00
Placing boards behind sinks............ 1.50'
Wicket doors in lattice-work .......... 1.75'
$ 16.25”
The declaration of law on which judgment was " rendered for defendants is as follows:
Plaintiffs alleged in the petition and introduced evidence tending to support the averments that Anderson had defaulted in the performance of the building contract in a number of specified particulars and that the total loss to plaintiffs on account of such breaches amounted to $1386.48. Though the manager of the Surety Company at Kansas City had actual knowledge of the breach by the contractor of his obligation to complete the work by November 20, the company did not offer to return the premium paid by plaintiffs, nor disclose its purpose of declaring a forfeiture of the bond but, on the contrary, the manager advised the very course of conduct plaintiffs afterward pursued.
The answer of the Surety Company interposed a number of defenses, including the one sustained by the
The contract for the improvement provided in the third paragraph for the making of changes in the plans and specifications regardless of whether such changes might be substantial or trivial, and in the sixth paragraph a methed was provided by which alone the contractor would be entitled to compensation for extra work done by him. This method was not followed with respect to the seven items of “extras” under consideration and we would be justified by the evidence, as a whole, in saying that these extras were furnished, not under the contract, but pursuant to subsequent independent agreements between plaintiffs and the contractor, but we prefer to base our decision of the questions now before us on other grounds and, for the purposes of our decision, shall assume that the extra work, amounting to sixteen dollars and tweny-five cents, was done under the original contract and pursuant to the provisions of the third and sixth para
But we find no room in the facts of the case for the indulgence of a reasonable conclusion that the few trifling alterations in the plans and specifications which, involved a net diminution of the contract price of about thirty three dollars could have had an appreciable effect on the risk of the surety, and we come to the question of whether or not the surety may invoke the rule-frequently applied in cases of voluntary suretyship, that where changes made without the consent of the surety affect the identity of the building contract, the surety will be discharged, notwithstanding .the fact that such changes did not increase or diminish the risk of the surety. That rule, we are persuaded; should
The deep solicitude of the law for the welfare of voluntary parties who bound themselves from purely disinterested motives never comprehended the protection of pecuniary enterprises organized for the express purpose of engaging in the business of surety-ship for profit. To allow such companies to collect and retain premiums for their services, graded according to the nature and extent of the risk, and then to repudiate their obligations on slight pretexts that have no relation to the risk, would be most unjust and immoral and would be a perversion of the wise and just rules designed for the protection of voluntary sureties. The contracts' of surety companies are contracts of indemnity and, as such, fall under the rules of construction applicable to contracts of insurance. Since they are prepared by the companies and generally abound with conditions and stiplations devised for the restriction of the obligation assumed by the company, such stipulations must not be extended to favor limitations providing for forfeiture of the contract. They must be strictly construed and no unreasonable right of forfeiture should be allowed.
Recently this court, speaking through Broaddus, P. J., in the case of Boppart v. Surety Co., 140 Mo. App. l. c. 683, gave voice to the views just expressed:
“The general rule is that a surety has the right to stand on the strict terms of his contract. This rule
In the light of this wholesome doctrine we are constrained to hold that the true intent and purpose of the provisions for notice in the bond were that the surety company should be given notice of any change or alterations that affected the risk in any degree and that the obligees were not required to give notice where the alterations were not material to the risk.
It is clear from what we have said that the trial court erred in pronouncing the bond forfeited on the ground of changes in the plans and specifications and we pass to other defenses not sustained in the circuit court but pressed upon our attention in the briefs of defendants.
The bond recites on its face thait the.contractor is the principal obligor and the Surety Clompany his surety, and contemplates that the contractor should sign the instrument. When the bond was introduced in evi-' dence it appeared that probably through some over
But manifestly this rule has no application to a contract of indemnity such as we have found the present contract to be. We cannot give our sanction to the idea that the Surety Company may collect and retain the premium charged for the bond; treat the instrument as one properly executed until a loss occurred and then repudiate liability on the ground that the bond was not signed by the contractor.
Finally it is argued by the surety that the failure of plaintiffs to give written notice of the breach of the building* contract by the contractor in respect of the stipulation relating to the time in which the improvement should be completed constituted a forfeiture of the bond. That point is sufficiently answered by the observation that this ground of forfeiture was one the surety could waive, and we hold that the conduct of the manager of the company’s office at Kansas City, as depicted in the evidence of plaintiffs, was a waiver of the right to forfeit the contract on that ground.
The knowledge of the manager of the true situation was the knowledge of the company and his acquiescence in the course pursued by plaintiffs was the acquiescence of the company whose alter ego he was. The company had no right to encourage plaintiffs in