From the assessment of alleged benefits to its property by the Rudersdorf Drainage District, hereinafter called
On the part of the company, on appeal to this court, the objections are substantially these:
(a) The district wаs not organized according'to law, nor (b) was a lawful estimate made of the required work, (c) The proposed assessment against the company is in еxcess of any actual benefits and is therefore void, (d) That by reason of the construction of the proposed ditch through an existing pile trestle bridge of the railroad and the same appropriated by the .district for a new waterway, the. .objector has suffered damages in the sum. of $5,000, and is entitled to an offset. ■ (e) That the .purported levy is irregular and void because an election was not called by the district on three weeks’ notice, as section 1862, Cоmp. St. 1922, requires for a vote on the adoption of the improvement and. proceeding with the work. The estimate of the cost of the project exceeds 20 per cent, of .the assessed value of the lands benefited by the improvement, which assessed value, under section 1862, is based upon one-fifth оf the actual value.
' Counsel for the district make this observation: “Can the appellant declare the assessment void and in the same breath declare it valid by its appeal from the apportionment?” In Baker v. Morrill Drainage District,
In respect of the merits it may be observed, on the рart of the district, that Mr. Gavenman, the district engineer, testified that the drainage district ditch was. installed to
The secretary of thе district board of directors testified that frequently, after a heavy rainfall, he had seen three feet of water on the north side of the right of way adjacent to the railroad tracks and that the volume of water looked like a small lake. He testified too that, at times, he heard section men working on the tracks during the nighttime to overcome the flood of water and prevent damage to the company’s property.
Four or five disinterested witnesses testified in respect of the heavy rainfalls and the consequent inundation of the roadbed, and also to the fact that, at some points, the floodwater came up to a foot or a foot and a half of the tracks. And some of these averred that sediment was deposited, by reason of the excessive rainfall, in the immediate vicinity, to such extent that it almost covered the top оf the fence posts. From their evidence it appears that, at the time, the roadbed of the company was gradually being submerged.
The division engineer testified that the trestle bridge was constructed by the company at an expense of. more than $3,200 to relieve the overflow of the flood-waters. And it mаy be observed that the right of way is nearly 12 feet high where it crosses the ditch. He also testified that the district engineer asked permission of him to run the ditch through the bridge, but that he had no power to give such permission and that he had never heard from higher authority granting permission. In respect of a culvert in the vicinity in question, оwned by the company, this witness testified: “Q. Wasn’t it (the culvert) built large enough to carry off the water that flowed there? A. No, sir.”
County of Blaine v. Brewster,
When it is determined by competent authority that either an individual or a business enterprise, in the present case a common carrier, is the recipient of a substantial benefit from imрrovements installed by the public, such enterprise should bear a reasonable part of the expenses of the construction. That the right of way of thе company is enhanced in value by the construction of the drainage system under discussion is apparent. Only a few of these benefits need be here enumerated, and among these are relief from numerous floods extending up to the ties and rails, and decreasing the hazards of passenger and freight traffiс, and lessened expense of maintaining the right of way.
So far as applicable here, we adhere to the rule announced in Drainage District v. Chicago, B. & Q. R. Co.,
From the record before us, and in view of the decisions, we conclude that the judgment of the trial court in fixing the amount of the assessment at $1,000 is reasonable and should .be sustained. The judgment is therefore
Affirmed.