From 1972 until 1983, Quemetco, Inc. (Quemetco), a subsidiary of RSR Corporation, operated a lead smelter on Harbor Island, near Seattle, Washington. During that time, Harbor Island suffered substantial environmental damage. In December 1982, the Environmental Protection Agency (EPA) announced that it planned to place Harbor Island on its National Priorities List (NPL). 1 In 1986, the EPA determined that Quemetco was a potentially responsible party for the pollution. On May 22, 2000, the EPA filed an action under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) seeking recovery from RSR Corporation for the costs it had expended in cleaning up Harbor Island, as well as for expected future costs.
Meanwhile, on February 2, 2000, International Insurance Company (International) sued RSR Corporation, Quemetco, Quemetco Metals Limited, Inc., and Quemetco Realty, Inc. (collectively, RSR), seeking a declaratory judgment that International had no obligations to RSR under four Environmental Impairment Liability (Environmental) policies which International’s predecessor in interest had sold to RSR in 1981. An initial jury trial was held to resolve certain coverage issues, while other coverage and damages issues were reserved for future resolution. At the conclusion of this initial trial, the district court entered judgment for RSR, holding that International’s Environmental policies obligated it to indemnify RSR for remediation costs incurred by the EPA at Harbor Island, to the extent those costs were not excluded by the policies. We affirmed the district court’s judgment on September 19, 2005.
Int’l Ins. Co. v. RSR Corp.,
RSR and International were realigned on July 12, 2007. 2 Afterwards, International raised additional defenses which had been unavailable to it at the time of the prior judgment or which had been reserved in the initial jury trial. On October 22, 2008, both parties filed motions for summary judgment. The district court granted International’s motion and dismissed RSR’s claims, holding that RSR could not recover from International (1) because an “other insurance” clause in International’s Environmental policies limited RSR’s recovery to sums it had already received from settlement agreements with several other insurance companies and (2) alternatively, because Texas’s “one recovery” rule barred RSR from collecting money from International when it had already been fully compensated for its Harbor Island liability through its settlement agreements with other insurance companies.
RSR now appeals the district court’s grant of summary judgment. For the following reasons, we affirm.
FACTS AND PROCEEDINGS BELOW
In 1981, the North River Insurance Company (North River) issued four Environmental policies to RSR, which provided successive layers of coverage up to $60 million, with a per claim limit of $30 million, subject to certain terms and conditions. The policies provided coverage for multiple locations, including RSR’s facilities on Harbor Island. In 1993, Interna
Under the Environmental policies, North River agreed to:
“[Ijndemnify the Insured against all sums which the Insured shall be obligated to pay for compensatory but not punitive or exemplary damages by reason of the liability imposed upon the Insured by law on account of:—
(a) Personal Injury, including death at any time resulting therefrom;
(b) Property Damage;
(c) Impairment or diminution of or other interference with any other environmental right or amenity protected by law;
... caused by Environmental Impairment in connection with the Business of the Insured ... and in respect of which a claim has been made against or other due notice has been received by the Insured during the Policy Period.”
The policies defined “Environmental Impairment” as:
“(a) the emission, discharge, dispersal, disposal, seepage, release or escape of any liquid, solid, gaseous or thermal irritant, contaminant or pollutant into or upon land, the atmosphere or any watercourse or body of water;
(b) the generation of smell, noises, vibrations, light, electricity, radiation, changes in temperature or any other sensory phenomena but not fire or explosion
arising out of or in the course of the Insured’s operations, installations or premises.... ”
However, Condition 8 of each policy provided that:
“This Policy shall not be called upon in contribution and no liability shall attach hereunder for any injury, loss, damage, costs or expenses recoverable under any other insurance insuring to the benefit of the Insured except as regards any excess over and above the amounts collectible under such other insurance; provided always that this clause shall not apply to any policy that is specifically arranged by the Insured to cover limits in excess of those stated in this Policy.”
Additionally, each Environmental policy excluded coverage for liability resulting from a “sudden and accidental happening” or a “fire or explosion.”
RSR also purchased Comprehensive General Liability (CGL) insurance policies from many other insurance companies that covered multiple sites, including the Harbor Island site. Some of those CGL policies contained exclusions for environmental claims, with exceptions to the exclusions for “sudden and accidental” events. Other CGL policies excluded environmental claims, but had exceptions to those exclusions for hostile fires. And other CGL policies did not exclude environmental claims, but only covered accidents and occurrences.
In 1993, RSR sued fifty-three of its CGL insurance providers in the 71st District Court for the Judicial District of Harrison County, Texas. In that action, RSR asserted claims against the CGL insurers for refusing to cover environmental cleanup costs and personal injury claims relating to more than twenty-five sites, including the Harbor Island site. In 2001, several CGL insurers made International a cross-claim defendant in the Harrison County action and sought contribution. RSR also asserted claims against International in the Harrison County action for breach of the Environmental policies, violations of the Texas Insurance Code, and recovery of attorney’s fees.
In the Harrison County action, RSR asserted that the CGL insurers were obligated to reimburse it for environmental costs because the pollution had been acci
Between 1993 and 2005, RSR entered into thirty-six separate settlement agreements with its CGL insurers, from which it received an aggregate payment of $76,006,501.00. It dismissed the rest of its CGL insurers from the Harrison County action. It also dismissed International. Following the execution of the last of the settlements, RSR non-suited the Harrison County action.
In the meantime, International had initiated the present action in federal court in February 2000, seeking a declaratory judgment that it had no obligations to RSR under the Environmental policies in connection with the Harbor Island site or with another site in West Dallas, Texas. In August 2001, RSR and International tried certain coverage issues relating to the Harbor Island claim before a jury, while reserving unripe coverage and damages issues for future resolution. Issues relating to the West Dallas site were severed into a separate trial and were later settled. 3 After the jury returned its verdict on the Harbor Island issues, the district court entered judgment for RSR, declaring that International was:
“contractually obligated to indemnify RSR for any remediation costs and expenses that RSR is or becomes obligated to pay to the United States Environmental Protection Agency (‘EPA’) with respect to the EPA’s remediation activity at the Harbor Island site ... to the extent such remediation costs and expenses are covered by [the] EIL Policies ... and are not otherwise excluded by the terms of the policies.... ”
The district court also determined that the EPA had made a claim against RSR, that RSR had not waived its right to coverage with respect to the Harbor Island site, that RSR’s Harbor Island lawsuit against International was not barred by the statute of limitations, and that RSR should take nothing on its common law bad faith and Texas Insurance Code claims against International. We affirmed this judgment on September 19, 2005.
Int'l Ins. Co.,
In March 2006, RSR moved to reopen the same federal district court case under 28 U.S.C. § 2202. Subsequently, International requested leave to amend its complaint to assert new coverage and damages defenses which had not been ripe at the time of the 2001 trial. In February 2007, the district court granted both motions. International then amended its complaint to assert new defenses, among them that Condition 8 of its policies, an “other insurance” clause, precluded coverage of RSR’s Harbor Island claims because RSR had already been fully compensated for this liability through its settlements with the CGL insurers in the Harrison County state court case. International also asserted that, even if the “other insurance” clause did not encompass the CGL policies, no recovery could be had on the Harbor Island claims, due to the Texas common law “one satisfaction” rule, because the CGL settlements had fully compensated RSR for its losses.
On July 12, 2007, the parties were realigned. RSR filed its original complaint on March 7, 2008, seeking approximately
DISCUSSION
RSR argues that the district court erred by granting summary judgment to International (1) because, as a matter of law, the “other insurance” clause in International’s policy cannot properly be read to bar recovery based on the settlements with the CGL insurers, and (2) because the common law “one satisfaction” rule is inapplicable outside of tort cases in Texas. We need not address the applicability of the “one satisfaction” rule to an insurance contract, because we agree with the district court that International’s “other insurance” clause deprived RSR of any right to recover more than it had already obtained from its settlements with the CGL insurers.
I. Standard of Review
We review a district court’s grant of summary judgment de novo.
Goodman v. Harris County,
We must view all evidence and reasonable inferences therefrom in the light most favorable to the party opposing the motion.
Scott v. Harris,
Our jurisdiction in this case is based on the diversity of the parties. International’s insurance policies are governed by Texas law.
Int’l Ins. Co.,
Texas courts interpret insurance policies according to the rules of contractual construction.
Int’l Ins. Co.,
II. “Other Insurance”
Where a liability covered by the Environmental policies is also covered by “other insurance,” Condition 8 4 prevents recovery unless the other insurance has been exhausted, in which ease the Environmental policies can serve as excess insurance. Condition 8 is triggered where “any injury, loss, damage, costs or expenses [are] recoverable under any other insurance insuring to the benefit of the Insured.” Thus, for Condition 8 to have been applicable in this case, (1) RSR must have had “other insurance” insuring to its benefit, and (2) RSR must have been able to recover under this other insurance for the same “injury, loss, damage, costs or expenses” it sought to recover from International.
The district court held that RSR’s CGL policies were “other insurance” under which RSR successfully recovered for the full amount of its Harbor Island liabilities pursuant to its settlement agreements with the CGL insurers. Therefore, it concluded that Condition 8 of International’s Environmental policies barred any further recovery. RSR argues that the district court erred because its CGL policies were not “other insurance” within the meaning of Condition 8 for two major reasons. First, RSR argues that a payment pursuant to a settlement agreement is not “insurance” and therefore does not qualify as “other insurance” under the plain language of the policy. Second, it argues that, even if a settlement payment could be considered insurance, Condition 8 would only apply if the Environmental policies issued by International covered the same liabilities as the CGL policies. RSR contends that the Environmental policies and the CGL policies covered different liabilities. The district court held that RSR was judicially estopped from making this argument, because RSR had argued successfully in the Harrison County action that the CGL and Environmental policies covered the same liabilities. RSR argues that the district court abused its discretion by finding that judicial estoppel was appropriate.
A. Settlement Payments as “Other Insurance”
RSR contends that the district court erred by holding that a payment pursuant to a settlement agreement could be “other insurance” within the meaning of Condi
There is no dispute that RSR’s CGL policies were insurance. Thus, the relevant question for the purposes of determining Condition 8’s applicability in this case is not whether RSR’s settlements were “insurance.” The relevant question is whether RSR sought to recover for liabilities under its Environmental policies that were also “recoverable” under its CGL policies.
B. “Recoverable” Under Other Insurance
RSR also argues that the district court erred by finding that Condition 8 barred recovery under the Environmental policies, because it asserts that the CGL and Environmental policies covered different liabilities. If this assertion were correct, Condition 8 would be inapplicable, since one of its triggering requirements is that “other insurance” cover the same “injury, loss, damage, costs or expenses” for which recovery is sought under the Environmental policies. However, the district court held that RSR was judicially estopped from asserting that the CGL and Environmental policies covered different liabilities, because it had argued successfully in the Harrison County action that the CGL and Environmental policies covered the same liabilities at Harbor Island. RSR argues that this application of judicial estoppel was an abuse of discretion.
“The doctrine of judicial estoppel prevents a party from asserting a position in a legal proceeding that is contrary to a position previously taken in the same or some earlier proceeding.”
Ergo Science, Inc. v. Martin,
Some of RSR’s CGL policies excluded coverage for environmental liabilities, with the exception of environmental liabilities resulting from “sudden and accidental” events or “hostile fires,” while the other CGL policies did not exclude environmental liability claims, but only covered aeci
However, in the Harrison County action, RSR took a very different position. There, RSR argued that the CGL policies’ exception for “sudden and accidental” occurrences could be satisfied by an occurrence that was not sudden, so long as it was accidental. RSR argued that the CGL policies covered “all forms of emissions causing pollution liabilities, except for those resulting from intentional pollution.” (Emphasis in original.) It urged the Harrison County district court to hold that the CGL policies covered “all damages from unexpected and unintended releases, discharges, dispersals, and/or escapes of pollution.” In a letter ruling dated March 19, 2003, the Harrison County district court granted RSR’s request and held that “the ‘sudden and accidental’ exception provides coverage for all unexpected and unintended pollution.”
In the present case, RSR attempted to avoid judicial estoppel by arguing that the Environmental policies covered “routine” environmental pollution, while the CGL policies covered “non-routine” pollution. The district court rejected this argument for two reasons. The first was that the terms “routine” and “non-routine” do not appear in either set of policies. The second reason was that RSR has never alleged that the pollution at Harbor Island was expected or intended.
We decline to find an abuse of discretion in the district court’s holding for the same reasons. The Environmental policies have nothing to do with whether or not the pollution in question can be characterized as “routine.” Their exclusions are triggered only where pollution occurred in a manner that was both sudden and accidental.
See Primrose Operating Co. v. Nat’l Am. Ins. Co.,
RSR clearly alleged in state court that its CGL policies covered all accidental pollution, whether or not it was sudden. RSR has not alleged that any of its pollution at Harbor Island was intentional.
5
Therefore, by implication, all of the pollution at Harbor Island was alleged to be accidental. Because RSR’s original interpretation of the CGL and Environmental policies allowed accidental pollution to be covered under both policies, and because the only pollution alleged to have occurred
C. Possible Excess
If RSR’s Harbor Island liabilities were only partially covered by its CGL settlements, Condition 8 would allow the Environmental policies to serve as excess insurance for the uncovered portion. Thus, the final issue we must confront in our analysis of the district court’s dismissal under Condition 8 is whether or not the CGL settlements compensated RSR fully for its Harbor Island liabilities. RSR argues that it was not fully compensated for these liabilities by the CGL settlements. International responds that, even if this were true, it was RSR’s burden under Texas law to allocate the settlement proceeds. Because RSR failed to do this, International argues that Texas law presumes that the full amount of the CGL settlements must be allocated to liabilities that would also be covered under the Environmental policies. International collected over $76 million from its settlements with the CGL insurers. It only seeks $13.1 million from International for its Harbor Island liabilities. Therefore, if International is correct about Texas’s presumptive allocation, then there is no excess to be covered under Condition 8, and we must affirm the district court’s take-nothing judgment.
While the Supreme Court of Texas has not confronted the precise issue before us, we conclude that its opinion in
Mobil Oil Corp. v. Ellender,
The court began its analysis of the issue by noting that “settling plaintiffs are in a better position than nonsettling defendants to insure that the settlement award is allocated between actual and punitive damages.” Id. at 928. It expressed concern that “[wjithout an allocation, Mobil, who was not a party to the settlement, had almost no ability to prove which part of the settlement amount represented actual damages. Nonsettling parties should not be penalized for events over which they have no control.” Id. It then examined the hazards inherent in the opposite rule:
“When the settlement agreement does not allocate between actual and punitive damages, requiring a nonsettling party to prove the agreement’s allocation before receiving a settlement credit not only unfairly penalizes the nonsettling party but also allows settling parties to abrogate the one satisfaction rule.... Settling parties could prevent nonsettling parties from receiving settlement credit by refusing to allocate between actual and punitive damages in settlement agreements.... The better rule is to require a settling party to tender to the trial court, before judgment, a settlement agreement allocating between actual and punitive damages as a condition precedent to limiting dollar-for-dollar settlement credits to settlement amounts representing actual damages.” Id.
The court concluded that, where a settling party failed to allocate its settlement, the nonsettling party was entitled to a credit equaling the entire settlement amount. Id.
In our view, the situation in this case is analogous to the situation in Ellender. Just as Mobil was not a party to any of the plaintiffs’ settlements in Ellender, here International was not a party to any of RSR’s settlement agreements or negotiations with its CGL insurers. Just as the lack of an allocation could have led to a double recovery in Ellender, the lack of allocation could lead to a double recovery respecting the Harbor Island liabilities in this case. International was unable to request, let alone require, that the CGL settlement agreements allocate the proceeds amongst RSR’s various liabilities. International should not be penalized for the fact that no allocations were made. Nor should RSR be rewarded for failing to track each of its liabilities diligently through to the end of its negotiations. Therefore, just as the Supreme Court of Texas placed the burden of uncertainty on the party to the settlement agreements in Ellender, so will we place it on the party to the settlements in this case.
RSR argues that
Ellender
is inapplicable to this case because its logic relies on the vindication of the one satisfaction rule, which RSR argues is inapplicable outside of tort cases.
See CTTI Priesmeyer v. K & O Ltd. Partnership,
The solution the Supreme Court of Texas reached on this issue was far from novel.
See, e.g., McCormick on Evidence
950 (3d ed., Edward W. Cleary ed.,1984) (stating that a party often must carry the burden of proof on an issue when the facts with regard to the issue lie peculiarly within the knowledge of that party). As the court noted in
Ellender,
it is a result we have reached under similar circumstances.
CONCLUSION
For the foregoing reasons, we affirm the take-nothing judgment of the district court.
AFFIRMED.
Notes
. Placement of a site on the NPL indicates that the EPA plans to clean up a site and serves as notice to potentially responsible parties that the EPA may seek to recoup its remediation costs from them.
. So that RSR became plaintiff and International defendant.
. The Harbor Island and West Dallas sites are the only sites on which RSR has made unsatisfied claims on International on the Environmental policies.
. The entire text of Condition 8 is:
“This Policy shall not be called upon in contribution and no liability shall attach hereunder for any injury, loss, damage, costs or expenses recoverable under any other insurance insuring to the benefit of the Insured except as regards any excess over and above the amounts collectible under such other insurance; provided always that this clause shall not apply to any policy that is specifically arranged by the Insured to cover limits in excess of those stated in this Policy. Nothing herein shall be construed to make this Policy subject to the terms, conditions and limitations of any other insurance.”
. This is not surprising, since intentional pollution at Harbor Island would likely be excluded from the Environmental policies under Exclusion 4 ("Liability for Environmental Impairment, arising out of the Insured's noncompliance with any valid and applicable statute, regulation or written instruction relating to Environmental Impairment issued by competent authority or Exclusion 13 ("Liability arising from the deliberate and intentional dumping or disposal of toxic or radioactive substances in the open sea.”). An admission by RSR that its pollution at Harbor Island was intentional also might have led to new difficulties with the EPA.
. This allocation was important because a defendant cannot receive credit for settlement amounts representing punitive damages.
Ellender,
