The parties to this appeal participated in arbitration after disputes arose concerning
In 2005, Royal Palm sued the Lewises, seeking to foreclose on a $72,339 construction lien it had recorded pursuant to chapter 713, Florida Statutes (count I); the establishment of an equitable lien in the amount of $72,339 (count II); and damages under breach of contract and quantum me-ruit theories (counts III and IV, respectively). The Lewises answered and raised a variety of counterclaims. As the parties’ contract contained an arbitration clause, the parties were ordered to arbitration.
Following a five-day hearing, the arbitrator awarded Royal Palm $38,528.88, finding that it was entitled to be paid for the “actual construction that was put in place by them.” The arbitrator rejected Royal Palm’s claim that the Lewises had breached the contract, but found as follows with respect to its lien foreclosure claim:
Claimant[’]s claim of lien was proper in that it was their only means of protecting their interests in the project during the dispute. Florida Statutes are specific as to the time frames required for filing a lien and the time to move to foreclose on a lien. Claimant took those steps as required by law to protect their interests.
The trial court subsequently entered an order confirming the arbitrator’s award.
Thereafter, Royal Palm sought the entry of a judgment foreclosing its construction lien. The trial court refused to enter a judgment of foreclosure, indicating at the hearing that Royal Palm was not entitled to one because the arbitrator’s award was silent on the matter and the basis of the award was unclear. The trial court entered only a judgment for money damages. This was error. In this case, Royal Palm was entitled to the entry of a final judgment of foreclosure as a means of enforcing the arbitrator’s award.
See
§§ 713.08, 713.21, Fla. Stat. (2009);
Mills v. Robert W. Gottfried, Inc.,
Affirmed in part; Reversed in part; and Remanded.
