No. 4468 | 6th Cir. | Feb 12, 1926

MOORMAN, Circuit Judge.

There is a statute of Ohio requiring one about to enter into a contract to construct a public building or other improvement to execute bond, with surety, to pay for all labor performed or material furnished in the construction or improvements to be made. The plaintiff in error was surety on a bond executed to the city of Lima for the construction of an in*502tereepting outfall sewer. The contractor defaulted in the performance of his contract, and this action was brought against the surety to recover.for material furnished on the work.

The bond bound the principal and surety jointly and severally. The contract, which was made a part of the bond by reference, provided that the principal would faithfully perform the work specified conformable to the terms, conditions, and requirements of the plans and specifications. Section 11242 of the General Code of Ohio provides that, if' the contractor forfeits his bond or renders his sureties liable thereon, the person injured thereby who is entitled to the benefits of the security may bring an action thereon in his own name “against the person [contractor] and his sureties to recover the amount to which he is entitled by reason of the delinquency.” It is contended by the surety company that, if a materialman desires to avail himself of this provision, he must sue both the principal and surety, and not the surety alone, as plaintiff has done.

The general rule is that an action may be maintained against either or both of two persons who are jointly and severally bound on a single obligation. Walsh Construction Co. v. City of Cleveland (D. C.) 250 F. 137" court="N.D. Ohio" date_filed="1918-04-04" href="https://app.midpage.ai/document/walsh-const-co-v-city-of-cleveland-8807725?utm_source=webapp" opinion_id="8807725">250 F. 137. This was an Ohio contract, and a statute of the state provides that “one or more of the persons severally liable on an instrument may be included in the same action thereon.” Section 11258, G. C. It is true that in Aucker v. Adams & Ford, 23 Ohio St. 543, it was held that suit could not be maintained against the surety alone on the official bond of a justice of the peace. But there the bond, from the nature of the case, could be nothing more than one of indemnity. The defendant here was more than an indemnitor against official affirmative misconduct. By the terms of the bond it was bound for the full performance of every undertaking of the principal, and carried the full obligation if the principal did nothing. Besides, in Indemnity Co. v. Granite Co., 126 N. E. 405, 100 Ohio St. 373, 12 A. L. R. 378, a recovery was had against the surety alone on a contractor’s bond given to the city 'of Cleveland, and it was pointed out,-in discussing one of the points made in that ease (though the question here presented was not raised), that as to surety engagements, for which compensation wds received, “the earlier rule of strietissimi juris adopted for the protection of sureties should not apply.” In this situation, and in view of the aim of the statute — the protection of those who furnish labor and material for public improvements — the Aucker Case cannot be regarded as controlling. As in U. S. v. Surety Co. (C. C. A.) 5 F.2d 412" court="6th Cir." date_filed="1925-04-06" href="https://app.midpage.ai/document/united-states-v-ætna-casualty--surety-co-6830287?utm_source=webapp" opinion_id="6830287">5 F.(2d) 412, we think it would be too narrow a construction to say that the words “against the person and his sureties” forbid the bringing of an action against the surety alone. The right to sue both is permissive, but not exclusive.

The remaining contention is that plaintiff failed to perform the condition precedent to the maintenance of this action required by section 2365 — 3 of the Ohio Statutes; that is,, having furnished material for use on the work, it failed, “within ninety days after the acceptance thereof by the duly authorized board or officer,” to furnish the surety a statement of the amount due on that account. It clearly appears that no such statement was furnished. But it further appears that the contractor abandoned its contract and the work was never accepted. The plaintiff,, therefore, could not comply with the statute. But it is said that in these circumstances it was the duty of plaintiff to show a legal excuse for not performing the condition. ■ If that be true, a sufficient answer is that the petition alleged and the answer admitted that the contractor abandoned the work before completing it. This was all that was required.

Judgment affirmed.