40 Mo. App. 213 | Mo. Ct. App. | 1890
This was a suit, brought on a builder’s contract, to enforce a mechanic’s lien for balance claimed to be due thereon. The petition, amongst other allegations, contained the following, to-wit:
Plaintiff complains of defendant, and for his cause of action states, that defendant is and at all times hereinafter mentioned has been the owner of a tract or parcel of land in the city of St. Joseph, county of Buchanan and state of Missouri, known and designated as lots 1, 2, 3 and 4, in block 3, in Wilson’s addition to. the city of St. Joseph aforesaid ; that about the eighth day of August, 1887, the plaintiff and defendant entered into a contract by written articles of agreement, whereby the plaintiff covenanted, promised and agreed to and with the defendant to make, erect and finish, in a good, substantial and workmanlike manner, on the parcel of ground above described, a large two-story, double-brick tenement dwelling house, which has since its erection been known as Dr. Boteler’s flats, by furnishing all the material and doing all the work therefor, except the brick work, brick material, painting and glazing; that
The answer was a general denial, at the trial, the plaintiff introduced in evidence the builder’s contract, which, amongst others, contained the following provisions, to-wit:
First. The said party of the second part does hereby, for himself, his heirs, executors and administrators, covenant, promise and agree to and with the said party of the first part, or his executors, administrators or assigns, that W. R. Roy, the said party of the second part, or his executors or administrators, shall and will, for the consideration hereinafter mentioned, without any unnecessary delay, and as soon as ordered, so make, erect, build and finish in a good, substantial and workmanlike manner, on the vacant lot situate on northeast corner of Thirteenth and Edmond streets in St. Joseph, Missouri, a certain job of carpenters’ and joiners’ work for a new brick building, containing four flats, to be built by the said party of the first part on the place aforesaid, and all to be agreeable
The plaintiff, to show performance, introduced the following statement, to-wit:
“St. Joseph, Mo., January 15, 1888.
“Hr. W. C. Boteler bought of Wm. R. Roy, Contractor and Builder, August 8, 1887:
To contract on flats..........................$3,200.00
To extra on front roof, 6 pieces 2x10-20........................$ 2 50
To 80 feet flooring............... 1 75
To 2} days’ labor, $7.50; nails, 25 cts. 7 75 12 00
To 1 window frame, sash and casing 7 00
To 72 feet inside base.............. 2 88
To 14 pieces 2x4-16, $2.80; 2 pair door casings, $2.50____■........ 5 30
To 4 days’ work, $3.25, ,$13.00; nails, 50 cts......................... 13 50
To 24 lbs. window weights......... 32. 36 00
To extra work — changing front steps To paneling front vestibule, 90 hours work, at 30 cts................$ 27 00 5 00
To nails and moulding............. 1 00
To 200 feet clear poplar lumber, at $3.50.........................1 7 00 35 00
To 2 closets on back porch, 2 days’ work.........................$ 6 00
To 100 feet lumber, -at $3.00; locks and hinges.....:............. 4 00 10 00
To 80 feet flooring No. 2 bds, $1.60; 7 feet flooring $1.90, used in wood work................... 3 50
$3,301 50
Or.
By cash..........................$2,860 96
Amount paid for inside blinds...... 90 00
Amount paid for picture moulding 13 75
Four drain boards left out of house 4 00
Changing sliding door to folding doors......................... 5 00
Difference in width of back porch.. 3 00 2,976 71
“Balance due $324 79”
The defendant objected to this evidence, on the ground, (1) that the contract provided that in every case, when payment was to be made under the contract! including final payment, a certificate should first be obtained by plaintiff, signed by Eckel & Mann, and countersigned by the sureties; and (2) because the statement offered in evidence, under the hand of said architects, was not the certificate of completion required by said contract, which objections were by the court sustained, and the evidence excluded.
The plaintiff then offered to prove that two papers “B” and “0,” offered in evidence, and excluded by the court, related to extra work, etc.; that the defendant refused to pay the balance due on said contract, as shown by the statements of said architects, solely on the ground that there was a charge for extra ■ work which he disputed; that the controversy was referred to arbitrators, to whom defendant stated that the only difference between him and plaintiff was this matter of extra work about the panels in the doors ; that the contract work had been completed to his entire satisfaction; that he had no objection to make to plaintiff or his work; if he had a dozen houses to build he wanted plaintiff to build them, as he liked his way of doing business; that he repeatedly stated the same thing to
The court, on motion of defendant, instructed the jury to find for the defendant, whereupon plaintiff took a non-suit, with leave to move to set the ■ same aside, which was granted, and thereupon judgment was entered accordingly, and, after an unsuccessful motion to set the same aside, the plaintiff took his appeal therefrom here.
I. The procurement by the plaintiff of the certificate of the architect, required by the contract, was a condition precedent. Neenan v. Donoghue, 50 Mo. 495; Yeats v. Ballentine, 56 Mo. 539; Dinsmore v. Livingston Co., 60 Mo. 244; Lloyd’s Law of Building and Buildings, sec. 20. This condition should be pleaded, and its performance alleged and proved. Dinsmore v. Livingston Co., supra; Stout v. St. Louis Tribune Co., 52 Mo. 347; Basye v. Ambrose, 32 Mo. 484; Turner v. Miller, 54 Mo. 535.
The long and well-established rule, that a pleading should be construed most strongly against the pleader,
II. It is contended by the plaintiff, that the trial court erred in excluding from the consideration of the jury the statement of the architects, which was introduced to show compliance with that part of the contract which required the procurement of the architect’s certificate. If this statement was sufficient to meet the requirements of the contract, it was conclusive in favor of the plaintiff’s right of recovery, until impeached for fraud. No other proof was necessary to enable him to recover on the contract. His whole case, the contract being admitted, was made by it. The rule that the architect’s certificate, in such cases, must comply with the requirements of the contract, otherwise no action
“I hereby certify that the work of J. B. has been completed to my entire satisfaction, and in conformity to the specifications and drawings, and in a substantial and efficient manner. I further certify that there is a balance of $-due him under said contract.
“A. L., Architect.”
Any other words conveying a similar meaning will answer. This writer 'further remarks that, when the contract provides that the architect’s certificate shall be in writing, that a want of such certificate will bar the contractor’s claim. In Wycoff v. Meyers, 44 N. Y. 144, the certificate read:
“This is to certify that the last payment of eighteen hundred dollars is due W. & W. on your buildings, corner of Gf. and B. streets, as per contract.
“[Signed] E. W. & Sow.”
It was claimed that the certificate was not in proper form, because it did not in terms certify that “the work was completely finished.” “If there .was no other answer to this,” said the court, “it would be a sufficient answer that the defendant did not place his objection to pay on this ground.” But the certificate was in substance all the contract required.''' In Snell v. Herf, 84 Ill. 225, the contract required that the architect’ s certificate should be signed by two architects, who were partners, when it was only signed by one. The certificate was presented to the plaintiff, who declined to -pay because of the delay in the completion of the job. It was held that inasmuch as plaintiff did not, when the certificate was presented, object to it because signed by only one of the architects, so that the objection might be removed, that it was conclusive. In Downing v.
The contract in this case required the certificate should be under the hand of the architects and to show, (1) that the whole job had been completed and accepted by the architects, (2) the final estimate by the architects of the amount due on the contract, and (8) that the work had been performed agreeable to the drawings and specifications, under the direction and to the satisfaction of the architect. It will be observed that the statement is. wan ting in those essentials which the contract required it should contain. It shows the balance due by plaintiff but nothing more.- It was sought to supply the omissions by extrinsic evidence. These conditions were imposed by the terms of the contract. They were fundamental. They were by the agreement of the parties made conditions precedent. Their performance was exacted before the plaintiff was entitled to the contract price of any of the work. This was the law governing the relation of the parties, and made so by the terms of the agreement. The statement was not in substance the certificate required by the contract. The most liberal construction that can be placed upon it cannot make it so. The plaintiff sued on the contract, and before he could recover on it he must show compliance, or an excuse for non-compliance. He has endeavored to show compliance by the production of a
III. The plaintiff’s further contention is that, even if the production of the architects’ certificate was a condition precedent, the defendant could waive it, and that the proof of waiver sustains the allegation of performance. It seems that this construction finds some support in the cases of Ins. Co. v. Kyle, 11 Mo. 278; Okey v. Ins. Co., 29 Mo. App. 110; Travis v. Ins. Co., 32 Mo. App. 101. The cases cited by plaintiff, and others which might have been cited, assert the doctrine for which he contends only in insurance cases. Why the rules of pleading and practice should be different in actions in insurance contracts from other actions is quite difficult to understand. The rule invoked by plaintiff seems to have so far been only made applicable to actions arising on insurance policies. Why so limited is nowhere made to appear. However this may all be, the cases cited by plaintiff can have no application to a case of this kind, or, if so, then the same aré not in harmony with the last utterance of the supreme court, by which we must be governed in thig case. Lanitz v. King, 93 Mo. 518; Nichols, Shepard & Co. v. Larkin, 79 Mo. 271; First Nat. Bank v. Hatch, 78 Mo. 24; Peer v. Hunch, 52 Mo. 33; Mohney v. Reed, ante, p. 99, decided at present term, are cases which assert a contrary view. It is not pretended that the plaintiff has pleaded a waiver by defendant of the performance of any of the conditions precedent. If the plaintiff ’ s offer of evidence tended to show a waiver of a condition precedent of the contract, or an excuse on his part for nonperformance, it was inadmissible, and properly rejected, unless the petition had alleged such waiver or excuse for non-performance, of which there is no pretense. In view of the rule as declared in Lanitz v. King and Mohney v. Reed, and the other cases to the same effect which we have cited, it is quite clear that, under the
It is contended further that as the statement which was introduced in evidence was made in that form by the architect to meet the request of defendant, it was for that reason not open to the objection made to it. This may be true: still if it was intended to prove a modification or alteration in the condition of the contract, or a waiver or estoppel, it was indispensably necessary for the plaintiff to have framed his pleading with that view so that an intelligent issue could have been made in that respect, then the proposed evidence would have no doubt been admissible. Under the state of the pleadings, the evidence offered was properly rejected, and the action of the court was unexceptionable. The judgment of the circuit court will be affirmed.