85 Iowa 203 | Iowa | 1892
I. The contract between the appellant and McArthur Bros, contains this clause: “Second. The work shall be executed under the direction
II. We next inquire, whether the estimates were wrongfully, falsely, or fraudulently made in either of the respects claimed. “The.plaintiff complains of the estimates in the following particulars: First. Classification of his work, whereby he was estimated and allowed seven and one-half cents per yard as for earthwork, when a large amount of it was, under the contract and specifications, loose rock, to be paid for at thirty-five cents per yard. Second. He was estimated, allowed and paid for work by the monthly estimates, which was afterwards wrongfully deducted and taken from him. Third. ’That he was underestimated in haul provided by the contract. Fourth. That he was underestimated in grubbing done by him under the contract. Fifth. That finishing stakes were not furnished him, and that he was, in consequence, required to go over' his work, and bring it up to grade a second time after it had settled, when five to seven per cent, of all the banks had been deducted for shrinkage, the amount it cost him being shown by the bills for such work proved by the evidence. Sixth. That he was damaged by delay in being furnished right of way in the largest cut on his work, so that it cost him one thousand five hundred dollars more to do it than if it had been furnished on time as he needed to work on it.”
The evidence touching these items is quite voluminous, and cannot be noticed in detail within the limits of
Estimates were made from time to time as the work progressed, and payment made thereon ,by the railroad company to McArthur Bros., and by them to their sub-contractors, including the appellant. In making these estimates it was the purpose to keep within the limit of work done, so that there would be no overpayment to the contractor, leaving any deficiencies to be covered by the final estimate. These estimates were made in part, at least, according to the following instructions: “As to classification, use your best judgment. Where the material is so hard that six horses can only plow half the time, allow a fair portion of loose rock, say twenty-five per cent. Where eight horses would be required, call about fifty per cent, loose rock, and about in that ratio, until in the very hard material, the hardpan of the specifications would be reached, which should all be classified as loose rock.” During the progress of this work, the appellant and other sub-contractors complained of the classification, and upon the completion of the work McArthur Bros, had a conference with their sub-contractors, including the appellant, at which the classification of the work
It is evident from - the nature of the materials named, and the manner in which they are often found blended in the earth, that a classification must be to some extent a matter of judgment; and it was no doubt in view of this fact that the parties agreed that the classifications of the engineer should be final and conclusive. The contract fixed, as the rule by which it was to be determined whether the material was earth or loose rock, the force recjuired to remove it. If it could be plowed with a strong ten-inch grading plow, well handled, behind a good six mule or horse team; it was to be classed as loose earth; but if it required greater force than this, and less than solid rock, it was to be classed as loose rock; and if, in the judgment of the engineer, blasting was required, then it was to be classed as solid rock. According to the contract, if the material could be plowed as stated, it was loose earth without regard to the length of time a team could be continuously worked; in other words, if it could be plowed at all in the manner stated, it was loose earth. The instructions quoted above were certainly more favorable to the contractor. If the six-horse team could only plow half time or less, it was loose earth under the contract, and yet the instruction was to “allow a fair portion of loose rock, say twenty-five per cent.”
The only evidence relied upon as tending to show fraud in the making of the estimates is the relation of the engineer to the defendant railroad company ^ The agreement to submit to his classification, measurements and calculations, was made with a full knowledge of that relation, and the evidence fails to satisfy us that Ms classifications, measurements and calculations, were in any substantial respect wrongful, false or fraud-, ulent.
III. As to the other claims of the appellant, it appears that at the time of the conference with Mc-Arthur Bros., and the making of demands by the contractors with a view to the final estimate, the appellant did not make or urge either of these claims., and that he received full payment of the amount found due to him according to the final estimate. While it does appear that other engineers might have estimated differently as to these.items, br classified differently as to earth or loose rock, yet it does not appear that there was any substantial or intentional error in the esti
As the foregoing conclusion fully disposes of the case, we need not consider the issue as to whether the the appellant is estopped from asserting these claims by reason of the payment made to him. Our conclusion upon the whole record is that the judgment of the district court should be abfibmed.