152 Mich. 386 | Mich. | 1908

Grant, 0. J.

(after stating the,facts). The court held that the $20 per day was a penalty, and could not have been considered by the parties in the nature of compensation. This presents the most important question in the case. It is ably and fully discussed by Christiancy, J., in Jaquith v. Hudson, 5 Mich. 123. It was there said that “there is some conflict and more confusion in the cases.” But the principle is there established that courts will “disregard the express stipulation of parties, only in those cases where it is obvious from the contract before them, and the whole subject-matter, that the principle of compensation has been disregarded.” See, also, Ward v. Hudson River Building Co., 125 N. Y. 230; Hennessy v. Metzger, 152 Ill. 505; Wilcus v. Kling, 87 Ill. 107; Western Gas Construction Co. v. Dowagiac Gas & Fuel Co., 146 Mich. 119.

In cases where it is difficult to accurately determine the damages which one party may suffer by the failure of the other to perform his contract, the parties themselves may agree upon such sum as in their judgment will be ample compensation for the breach.

The defendant desired the possession of his house at a specified time. The plaintiff understood and contracted with reference to this. He had not complied with his first contract as to time. Cold weather was approaching. The damages which a householder would naturally suffer under such circumstances cannot be estimated by the amount of the contract or the rental value of the house. The purpose for which- the building is to be used, the necessity for having the work done within the prescribed time and the indirect as well as direct damages to a householder desiring to move into his house before cold weather, are elements which the parties to such a contract take into consideration. It would be difficult under such circumstances to accurately determine the damage which the householder might receive in being compelled to store his goods and to live at a hotel or boarding-house. We cannot therefore hold that the amount is per se excessive *389and a penalty. The use of the word “forfeit” does not necessarily imply a penalty (Western Gas Construction Co. v. Dowagiac Gas & Fuel Co., supra), and the circumstances were not such as to justify the court in holding, as a matter of law, that it was a penalty. For cases holding that the stipulated amount was a penalty rather than a fixed compensation, see Trustees of First Orthodox Congregational Church v. Walrath, 27 Mich. 234; Myer v. Hart, 40 Mich. 517, 523; Daily v. Litchfield, 10 Mich. 29; Davis v. Freeman, 10 Mich. 188; Cochran v. Railway Co., 113 Mo. 359; Condon v. Kemper, 47 Kan. 126 (13 L. R. A. 671).

Where the provision is held to be a penalty the defendant is entitled to recover his actual damages.

A more doubtful question arises out of the stipulation in the contract that “ If work is pushed, a few days of grace will be allowed.” We think it was not for the court to say that 13 days was the few days of grace contracted for. The question depends upon the character of the work to be done, the time necessarily required in doing it, and all the circumstances surrounding the transaction. The question should have been submitted to the jury.

The court also held that this provision for a few days of grace was a waiver of the provision for damages. No reason was given for the holding, and we are unable to suggest any. It was a waiver of damages only if, the work was pushed, and upon this point there is a conflict of evidence.

Two other questions are raised, but the ruling of the court thereon was correct, and they are not of sufficient importance to discuss.

Judgment reversed, and new trial ordered.

Montgomery, Ostrander, Hooker, and Carpenter, JJ., concurred.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.