550 S.E.2d 698 | Ga. Ct. App. | 2001
ROSENHEIMER et. al.
v.
TIDAL CONSTRUCTION COMPANY.
Court of Appeals of Georgia.
*699 Eugene C. Brooks IV, Christopher M. Kessinger, Savannah, for appellants.
Brannen, Searcy & Smith, Daniel C. Cohen, Ashlee L. Vaught, Savannah, for appellee.
RUFFIN, Judge.
Robert Rosenheimer and Victoria Soland (the plaintiffs) purchased a new home built by Tidal Construction Company (Tidal). After discovering an alleged moisture problem with the synthetic stucco exterior of the house, the plaintiffs sued Tidal and Colormatch Exteriors, Inc. (Colormatch), the company that manufactured the synthetic stucco. The defendants moved for summary judgment, asserting that all of plaintiffs' claims were barred by the statute of limitation. The trial court granted defendants' motions, and this appeal ensued. For reasons that follow, we reverse.
To prevail on a motion for summary judgment, a defendant must demonstrate that there are no genuine issues of material facts and that the facts, viewed most favorably to the plaintiff, warrant judgment as a matter of law.[1] "We review a grant of summary judgment de novo."[2]
Viewed in this light, the evidence shows that Tidal obtained a building permit in June 1994 to build a house in Bryan County. The exterior of the house was finished using an exterior insulation and finish system, also referred to as synthetic stucco, that was allegedly manufactured by Colormatch. The construction was essentially complete in February 1995, and in March or April 1995, a real estate agent showed Rosenheimer the house. On April 15, 1995, Rosenheimer and Soland signed a contract to purchase the house. Tidal obtained a certificate of occupancy on June 22, 1995, and the closing took place on June 26, 1995.
According to Rosenheimer, after closing on the house, he began noticing moisture problems *700 with the house, which he attributes to both the "defective" nature of Colormatch's synthetic stucco as well as Tidal's improper application of the product. On April 19, 1999, Rosenheimer and Soland filed suit against Tidal. On June 22, 1999, Colormatch was added as a party to the suit. The plaintiffs asserted claims for negligence, negligent misrepresentation, breach of implied warranty, breach of implied contract, and bad faith. With respect to Colormatch, the plaintiffs also asserted a strict liability claim.
Both defendants moved for summary judgment, arguing that the plaintiffs' claims were barred by the statute of limitation in OCGA § 9-3-30(a), which provides that "[a]ll actions for ... damage to realty shall be brought within four years after the right of action accrues." According to defendants, the right of action accrued four years after Tidal finished building the house in February 1995. Thus, they reasoned, the April 1999 complaint was not timely filed. The trial court agreed and granted both motions for summary judgment.
1. In several enumerations of error, the plaintiffs contend that the trial court erred in concluding that their tort claims are barred by the statute of limitation. The parties agree that tort claims are governed by a four-year statute of limitation.[3] The issue on appeal is when the right of action accrues for damage to realty claims. "It is well settled that the starting date for [such] damage to realty claims is the date of `substantial completion.'"[4] According to the plaintiffs, the house was not substantially complete until the builder obtained the certificate of occupancy on June 22, 1995. The defendants, on the other hand, argue that the house was substantially complete in February 1995, when the construction was complete. We agree with the plaintiffs.
In the recent case of Hickey v. Bowden,[5] this Court addressed this exact issue. We held that "[b]ecause the [plaintiffs] could not legally occupy the house for the purpose for which it was intendedas their residence until the certificate of occupancy was issued," the date the certificate is issued serves as the earliest date the house can be deemed substantially completed.[6] Here, it is undisputed that the plaintiffs filed suit prior to June 22, 1999, four years from the date the certificate of occupancy was issued. It follows that the trial court erred in concluding that their tort claims are barred by the statute of limitation.
2. The plaintiffs also contend that the trial court erred in finding that the contractual claims are governed by the four-year statute of limitation set forth in OCGA § 9-3-30. We agree. In several recent cases, this Court has made abundantly clear that "the six-year statute of limitation governing simple written contracts applies to a contract for the sale of new construction."[7] Thus, to the extent that the plaintiffs' complaint alleges breach of the written contractincluding claims for breach of implied warranty stemming from that contractsuch claims are governed by the six-year statute of limitation.[8] To the extent that the complaint alleges breach of an implied contract, such claim would be subject to the four-year statute of limitation.[9] For the reasons set forth in Division 1, such claims were timely asserted. Accordingly, the trial court erred in granting defendants' motions for summary judgment.
Judgment reversed.
JOHNSON, P.J., and ELLINGTON, J., concur.
NOTES
[1] See Swan Kang, Inc. v. Kang, 243 Ga.App. 684, 685, 534 S.E.2d 145 (2000).
[2] Id.
[3] See Mitchell v. Jones, 247 Ga.App. 113, 115-116(2), 541 S.E.2d 103 (2000).
[4] Hickey v. Bowden, 248 Ga.App. 647, 649(2), 548 S.E.2d 347 (2001).
[5] Id.
[6] Id. at 650(2), 548 S.E.2d 347.
[7] Smith v. KLS Constr. Co., 247 Ga.App. 493, 494(1), 544 S.E.2d 197 (2001). See also Stimson v. George Laycock, Inc., 247 Ga.App. 1, 3(1), 542 S.E.2d 121 (2000); and Mitchell v. Jones, supra at 114(1), 541 S.E.2d 103 (2000).
[8] See Hickey, supra at 649(1), 548 S.E.2d 347.
[9] See Bauer v. North Fulton Med. Center, 241 Ga.App. 568, 572(3)(b), 527 S.E.2d 240 (1999).