IN RE MOULTONBOROUGH HOTEL GROUP, LLC, Debtor. ROK BUILDERS, LLC, Appellant, v. 2010-1 SFG VENTURE LLC, Appellee.
No. 12-2182
United States Court of Appeals For the First Circuit
July 18, 2013
Before Torruella, Thompson and Kayatta, Circuit Judges.
William S. Gannon for appellant.
Gary D. Ticoll, with whom Paul T. Martin, Greenberg Traurig, LLP, Edmond J. Ford, and Ford & Associates, P.A., were on brief for appellee.
I. Background
This dispute has its origins in a project that began in 2006 to build a Hampton Inn & Suites in Tilton, New Hampshire. On December 1, 2006, ROK signed a contract with Moultonborough to construct the hotel. ROK began work, but the project stalled when Moultonborough proved unable to pay its bills. In April 2007, ROK terminated the contract due to nonpayment of roughly $1.6 million. ROK signaled its willingness to resume work if Moultonborough secured adequate financing and paid the balance due, with interest.
On June 26, 2007, Moultonborough signed an agreement letter with Specialty Finance Group in which Specialty committed to extending up to $8.7 million in new funding to restart the project.
ROK then set about finishing the hotel. For its work, it received loan disbursements from Specialty, in conjunction with at least two of which it executed lien waivers. In its final waiver, executed for the period ending May 31, 2008, ROK acknowledged past payments from Specialty of $5,751,419.39 for work done under its 2007 agreement with Moultonborough, and listed a balance due of $954,571.03. The waiver provided,
In consideration of the payment of the above stated sums currently due and amounts previously paid, the receipt of which is hereby acknowledged, [ROK]1 hereby waives, relinquishes, and releases any and all liens, rights, claims and interests (including,
without limitation, all rights to mechanic‘s and materialmen‘s liens) owned, to be owned, claimed or held by [ROK] in and to the [Hampton Inn & Suites in Tilton] . . . by reason of the labor performed and/or materials furnished by [ROK] . . . prior to and including the Payment Date . . . .
At the time it submitted the waiver, ROK was unaware that Specialty had decided to stop payments due to Moultonborough‘s failure to secure additional financing, as its loan agreement with Specialty required. Indeed, Specialty did not inform ROK of this decision even when it received the waiver, and ROK performed further work in June, still unaware that it would not be paid. ROK‘s briefs do not dispute that it received an additional $682,655.01 from Specialty, presumably after the May waiver, yielding a total payout of $6,434,074.40 for work performed under the 2007 construction contract. However, ROK maintains that it is still owed $2,487,411.94 for work under that contract, secured by a mechanic‘s lien.2
Despite the unresolved payment issue, the hotel opened successfully in June of 2008. Moultonborough and Specialty,
On March 15, 2011, SFG initiated an adversary proceeding against ROK in bankruptcy court, seeking a declaration that $6,434,074.40 of the construction mortgage -- the amount Specialty had disbursed to ROK for work performed under the 2007 construction contract -- was senior to ROK‘s mechanic‘s lien. In response, ROK filed a dozen counterclaims: two seeking a determination that its lien was senior to SFG‘s mortgage, and an additional ten advancing causes of action sounding in tort, contract, and equity. SFG filed a motion to dismiss, which the bankruptcy court granted as to the ten secondary counterclaims. SFG then filed a motion for summary judgment on the competing seniority claims, which the bankruptcy court granted. ROK timely appealed to the district court, see
II. Analysis
On appeal, ROK challenges the grant of summary judgment on the competing seniority claims and the dismissal of three of its secondary counterclaims -- specifically, those for breach of an implied contract, promissory estoppel, and unjust enrichment. Although we constitute the second tier of appellate review in this case arising out of a decision by the bankruptcy court in an adversary proceeding, “we cede no special deference to the determinations made by the . . . district court” and instead “assess the bankruptcy court‘s decision directly.” City Sanitation, LLC v. Allied Waste Servs. of Mass., LLC (In re Am. Cartage, Inc.), 656 F.3d 82, 87 (1st Cir. 2011). In doing so, we “scrutinize that court‘s findings of fact for clear error, and afford de novo review to its conclusions of law.” Brandt v. Repco Printers & Lithographics, Inc. (In re Healthco Int‘l, Inc.), 132 F.3d 104, 107 (1st Cir. 1997).
The legal standards traditionally applicable to motions for summary judgment and motions to dismiss apply without change in bankruptcy proceedings. See Soto-Rios v. Banco Popular de P.R., 662 F.3d 112, 115 (1st Cir. 2011); Banco Santander de P.R. v. Lopez-Stubbe (In re Colonial Mortg. Bankers Corp.), 324 F.3d 12, 15 (1st Cir. 2003). Accordingly, in reviewing the bankruptcy court‘s summary judgment ruling, our inquiry is whether any “genuine issue of material fact exists” and whether “the moving party is entitled
A. The Competing Seniority Claims.
We turn first to the competing seniority claims. As assignee of the mortgage, SFG advances the unremarkable position that, to the extent Specialty paid ROK for its work, and to that extent only, the mortgage is senior to any remaining mechanic‘s lien that ROK has. ROK counters that its lien for later work on the project for which it was not paid takes precedence over the mortgage. In support of this position, ROK asserts that because it began work on the project before the mortgage was recorded, any lien arising out of work on the project performed at any time, whether prior to or after recording of the mortgage, remains senior to the mortgage, even to the extent the mortgagee paid for work.
First, the New Hampshire statutory scheme that recognizes mechanics’ liens, provides the procedure for their perfection, and specifies their relative priority over other encumbrances, runs directly against ROK‘s position. The New Hampshire recording statute,
New Hampshire is a “race-notice” jurisdiction. That is, a purchaser or creditor has the senior claim if he or she records without
notice of a prior unrecorded interest. The purpose then of the recording statutes recited above is to provide notice to the public of a conveyance of or encumbrance on real estate. The statutes serve to protect both those who already have interests in land and those who would like to acquire such interests.
In a subsequent decision, the Supreme Court also linked the race-notice rule to section 477:3-a. See Mansur v. Muskopf, 977 A.2d 1041, 1046 (N.H. 2009). Specifically, the Court cited Amoskeag Bank for the proposition that the state is a race-notice jurisdiction. Id. It then explained that “[t]herefore, a purchaser with a senior claim in real estate must record such interest in order to prevail over a bona fide purchaser for value,” and cited “[i]n particular” section 477:3-a. Id.
Here, the race-notice rules favor SFG, because the mortgage was recorded well before the work for which a lien is claimed was performed. This fact alone does not defeat ROK‘s claim, however, because the statutory scheme in New Hampshire creates an exception to the race-notice rule for mechanics’ liens. Specifically, a mechanic‘s lien “shall have precedence and priority over any construction mortgage.”
In response to this conclusion, ROK contends that the scheme envisioned by
In this case, by contrast, payment was in fact “previously made” to ROK by Specialty. Therefore, the lien for that paid work expired, leaving ROK with only a lien for later work. See
Accordingly, we conclude that the bankruptcy court did not err in concluding that section 447:12-a establishes the seniority of SFG‘s mortgage over ROK‘s mechanic‘s lien to the extent of the $6,434,074.40 that Specialty disbursed to ROK.
B. ROK‘s Counterclaims.
We turn now to ROK‘s counterclaims for breach of an implied contract, promissory estoppel, and unjust enrichment. All three claims rest on Specialty‘s course of dealings with ROK as the hotel neared completion, roughly two years before SFG appeared on the scene. In essence, ROK maintains that Specialty, eager to have the value of a finished rather than unfinished hotel as collateral for its loan, misled ROK into believing that it would be paid for completing construction. ROK now demands that SFG, as the assignee of Specialty‘s mortgage, make good on that alleged commitment.
1. Assumption of liability for implied contract and promissory estoppel.
Taking the first two counterclaims together, ROK asserts that although the doctrines of implied contract and promissory estoppel are distinct, the same conduct by Specialty entitles it to recover under either theory. An implied contract is an enforceable agreement that arises from “the conduct of the parties, apart from oral and written words.” Durgin v. Pillsbury Lake Water Dist., 903 A.2d 1003, 1006 (N.H. 2006). Promissory estoppel, in contrast, provides a basis for recovery when no contract exists; if a promisor should reasonably expect a promisee to rely on a promise, and the promisee in fact does so, courts may enforce the promise to avoid injustice. See Great Lakes Aircraft Co. v. City of Claremont, 608 A.2d 840, 853 (N.H. 1992); Panto v. Moore Bus. Forms, Inc., 547 A.2d 260, 266 (N.H. 1988); see also Restatement (Second) of Contracts § 90 (1981).
As the bankruptcy court recognized, however, even assuming that Specialty‘s actions created an implied contract between Specialty and ROK or entitled ROK to recover from Specialty under a theory of promissory estoppel, there is no basis for holding SFG liable for the actions of Specialty. No language in the assignments purports to transfer such liabilities to SFG. ROK is therefore left to contend that SFG “implicitly assumed” Specialty‘s liability to ROK when SFG accepted assignment of the mortgage and loan agreement between Specialty and Moultonborough
With certain exceptions, section 328 treats a general assignment of all rights under a contract as a delegation of unperformed duties under the same contract, enforceable against the assignee by the obligor of the assigned rights. Without commenting on whether and to what extent section 328 might in some cases apply to assignments of mortgages and defaulted notes, we can easily reject any assertion that section 328 helps ROK in this case. The contract assigned to SFG was an agreement or agreements between Moultonborough as borrower/mortgagor and Specialty as lender/mortgagee. If SFG assumed any obligations as a result of that assignment, they would have been the obligations of the lender/mortgagee under those agreements. The alleged liability that ROK seeks to impose on SFG, however, arises from an alleged implied contract (or promise) between Specialty and ROK. SFG received no assignment of any rights under any contract such as that. In short, even if we were to assume that obligations under a contract follow rights upon assignment absent indication otherwise, nothing in section 328 would suggest that obligations under one contract follow rights under another. For this simple reason, ROK‘s argument does not get to first base.
2. Unjust enrichment.
ROK‘s claim of unjust enrichment fails, too, although for a reason other than that relied on by the bankruptcy court. “Unjust enrichment is an equitable remedy” that entitles a party to restitution from one who has “receive[d] ‘a benefit which would be unconscionable for him to retain.‘” Clapp v. Goffstown Sch. Dist., 977 A.2d 1021, 1024-25 (N.H. 2009) (quoting Kowalski v. Cedars of Portsmouth Condo. Assoc., 769 A.2d 344, 347 (N.H. 2001)). The bankruptcy court dismissed ROK‘s claim for unjust enrichment on the basis that SFG could not be liable for the conduct of Specialty -- the same basis on which it dismissed ROK‘s implied contract and promissory estoppel claims. New Hampshire law is clear, however, that restitution may be required even if the party receiving the benefit has not itself engaged in wrongful acts. Gen. Insulation Co. v. Eckman Constr., 992 A.2d 613, 621 (N.H. 2010). Passive acceptance of a benefit can be enough, as long as it would be unconscionable for the recipient to retain the benefit. See id.
Having convinced us that SFG‘s lack of involvement in the alleged wrongdoing by Specialty is not itself grounds to dismiss ROK‘s claim for unjust enrichment against SFG, ROK nevertheless fails to point to any allegation that would support a finding that SFG received a benefit, the retention of which would be unconscionable. ROK relies on the case of Nute v. Blaisdell, 374 A.2d 923 (N.H. 1977). That case, however, serves simply to show by contrast what was lacking in ROK‘s allegations in this case.
In Nute, George Blaisdell acted as a fiduciary for June McKeage. Nute, 374 A.2d at 924. Blaisdell caused McKeage to borrow funds, which Blaisdell then used to buy a house, which he placed in his mother‘s name. Id. There was no evidence that the mother, who knew McKeage, paid anything for the home. Id. at 924-25. The New Hampshire Supreme Court held that those facts could support a finding that the mother had been unjustly enriched. Id. at 925. After all, she got a house for nothing when it was clear that the person whose money and credit paid for the house intended no gift. Here, SFG simply bought a mortgage on a completed hotel, from a failed bank through the FDIC. ROK alleges no facts plausibly demonstrating that the purchase transaction was not negotiated at arm‘s length. Nor does ROK allege any fact suggesting that SFG would have paid the same amount for a mortgage on an uncompleted hotel. Therefore, even assuming that Specialty received a benefit from the unpaid work, it is certainly not unconscionable for SFG to retain that which it bought. See Axenics, Inc. v. Turner Const. Co., 62 A.2d 754, 766-67 (N.H. 2013).
Accordingly, although our analysis differs from that of the bankruptcy court, the court did not err in dismissing ROK‘s unjust enrichment claim.
Affirmed.
