208 P. 600 | Mont. | 1922
delivered the opinion of the court.
Upon a former appeal this cause was remanded to the
The finding that the agreement upon the original estimate constituted "a separate and independent contract” embracing more than one account was erroneous, because it gave no effect to the contemporaneous agreement that such additional material as might be needed for the completion of the building were to be furnished at the same rate and upon the same terms. That understanding comprehended but one indivisible contract, one account, and the foundation for but one lien. The difficulty in anticipating the precise quantity of material required for a job of that character is clearly indicated by the disparity between the original estimate and the materials finally found to be needed to complete the work. Indeed, the entire indebtedness resulted from a contract to furnish articles for a single building, to be delivered from time to time as the work progressed and until the job was finished. The uncertain element entering into a transaction of this nature make it a case similar to one arising upon a contract where no definite time is fixed for the completion of the work, and where the account is to run until the last item required is furnished.
As is very well understood, a builder or owner of property is rarely able to anticipate the exact amount of material he may require for the erection of a building. Unless, therefore, there is room for a different conclusion, when it is found necessary, as the work advances, to order more materials, the items should all be deemed to have been ordered upon an account current, and the aggregate, when they have all been furnished, constitute the lien. (Helena S. H. & S. Co. v. Wells,
A substantial, rather than a technical, view should be taken
The work was one continuous job, although materials were furnished at different times after the original estimate had been satisfied, and, although they may have been furnished under separate orders, each order was a related contract for some part- of the work and formed the basis for but one lien. A lien filed within ninety days preserves a lien for all the items, and all of them together furnished but one account. (Taylor v. Dall Zinc & Lead Co., supra; Northwestern Lumber Co. v. Parker, 125 Minn. 107, 145 N. W. 964.) In the latter case the court said: “This work was done under several little contracts, each for some small part of the work. One lien statement was filed covering all the contracts. The whole work was part of one general improvement, or one job, and was practically continuous in point of time.”
In finding No. 13 the court found that none of the items under date of December 26, 28, and 29, 1914, and January 4 and 16, 1915, were used in the construction of the building, and none “were sold and delivered on said dates.” For this finding there is no support in the evidence. After a careful reading of all of the evidence, we are satisfied that it was clear and convincing enough to sustain the opposite conclusion, and the court should have so found.
In conclusion, we recommend a careful reading of the case of Taylor v. Dall Zinc & Lead Co., supra. A comparison of its facts with those in the present case will convince the most skeptical of the justness and the soundness of the conclusion reached above. In almost every particular the facts are similar to those found in the record before us. The only distinguishing feature we are able to discern is that in the Wisconsin case the parties had no contemporaneous understanding that any additional items needed after the filing of the original estimate should be supplied at the same price and upon the same terms. After an able review of the cases upon the subject, the learned justice closes the unanimous opinion of the court in these words: “After careful examination and consideration of all this evidence, we are forced to the conclusion that, practically without dispute, it establishes both an understanding, tacit perhaps, that plaintiffs were to be called on and would respond to furnish such other lumber as might, in accordance with usual experience, have been omitted from the specifications upon which they originally bid, and that both parties fully understood that all the subsequent deliveries were in pursuance of such original understanding. It is too plain for controversy that they were all so closely connected in time, and so in response to the continuous and uninterrupted construction of the' building, that no' doubt it cast upon the
• The judgment against defendant W. D. Welch is affirmed. The judgment in favor of defendants F. A. Flanagan, John McKenzie, F. J. Gies and O. W. Belden is reversed, with directions to enter judgment in favor of plaintiff foreclosing the lien.