168 Mo. App. 363 | Mo. Ct. App. | 1912
This is a suit on a builder’s bond. The finding and judgment were for plaintiff, and defendant surety on the bond alone prosecutes the appeal.
Henry A. Christophel and W. H. Pearson contracted in writing with plaintiff to furnish the materials and erect a building for him at the agreed price of $6200. Among other things, the contract stipulated the building was to be completed and delivered to plaintiff free of all liens, etc. In connection with this contract and in assurance of its fulfilment, defendant Essig, as surety, executed the bond in suit in the amount óf $6200, whereby he bound himself to answer for the default of Christophel and Pearson in respect of any matter stipulated for in the contract. After settling with the contractors on the certificate of the architect, plaintiff was required to expend' $516.87 in liquidation of lien claims against the building, and prosecutes this suit upon the bond to recover therefor.
It is first argued the court should have directed a verdict for defendant Essig, the surety, for the reason that the names of Christophel and Pearson, principals, were not affixed to the bond. It appears the building contract and the bond in suit were executed by the use of printed forms both on the same sheet of paper. In other words, the builder’s contract is printed on one side of a sheet of paper and the bond for the faithful
The builder’s contract provides, among other things, that the plaintiff should pay, during the course of construction, to the builders not to exceed seventy-five per cent of the contract price and retain1 a balance of twenty-five per cent, thereof as security against possible liens, etc., and that the final payment of this twenty-five per cent should be made ten days after the building was completed and on its acceptance by plaintiff. All payments were to be made on the certificate of J. L. Wees, architect and superintendent of the building. It appears that plaintiff made payments on the contract in accordance with this agreement on the certificate of the architect and retained twenty-five per cent of the contract price 'until ten days after the building was completed, when, upon its acceptance, the remaining twenty-five per cent of the contract price was paid to the contractors on the certificate of the architect. It is argned the court should have directed a verdict for defendant surety on the ground that plaintiff released the security in his hands by paying out the remaining twenty-five per cent of the contract price without regard to the probable liens that might be run upon the building. There can be no doubt that when the contract stipulates the owner shall- withhold from the contractor a percentage of the contract price as a security against probable liens and until such lien claims are settled, without more, the surety, is discharged if the owner surrenders this security with out his consent. [Such is the doctrine of Evans v. Graden, 125 Mo. 72, 28 S. W. 439; Harris v. Taylor, 150 Mo. App. 291, 129 S. W. 995.] But the rule invoked is wholly without influence here, for it appears con
The judgment should be affirmed. It is so ordered.