First wе note that under N.C. Gen. Stat. § 1A-1, Rule 7(c), “pleas” are specifically abolished; but under Rule 12(b), every defense may be raised by responsive pleading — in this case by reply to defendants’ counterclaims. A defense which introduces new matter in an attempt to avoid defendant’s counterclaim, regardless of the truth or falsity of the allegations in the counterclaim, is an affirmative defense. N.C. Gen. Stat. § 1A-1, Rule 8(c). Thus, plaintiffs’ “plea in bar” asserting that defendants were barred from any recovery of damages for breach of contract or under the theory of quantum meruit or unjust enrichment was an affirmative dеfense to defendants’ counterclaims and the trial court, at the parties’ request, conducted a trial on that issue, prior to a full trial on the merits.
The threshold question which we must consider, although nоt argued by the parties in their briefs, is whether an appeal lies from the order in question. If this is a fragmentary, and therefore premature, appeal, we must dismiss the appeal
ex mero motu. Bailey v. Gooding,
A party has a right to appeal a judgment of a trial court under N.C. Gen. Stat. §§ 1-277 and 7A-27 if the judgment is (1) a final order, or (2) an interlocutory order affecting some substantial right claimed by the appellant which will work an injury to him if not corrected before an appeal from a final judgment.
Bailey v. Gooding, supra; Industries, Inc. v. Insurance Co.,
The question remains whether the judgment in question affects some substаntial right claimed by defendants which will work an injury to them if not corrected before an appeal from a final judgment.
Bailey v. Gooding, supra; Industries, Inc. v. Insurance Co., supra; Veazey v. Durham, supra.
The judgment in question dismissed defendants’ compulsory counterclaims, but did not entirely bar them. The judgment stated that defendants could enforce the contract defensively, as a set-off, to the claim asserted against them by plaintiffs. The set-off, however, cannot exceed the plaintiffs’ claims.
See Furniture Mart v. Burns,
In our opinion, the possibility of being forced to undergo two full trials on the merits and to inсur the expense of litigating twice makes it clear that the judgment in question works an injury to defendants if not corrected before an appeal from a final judgment. The burden on defendants in this case of being forced to undergo two full trials is much greater than that suffered by the appellant in
Waters v. Personnel, Inc.,
Having passed on the threshold question, we now consider the appeal on its merits. Defendants make two arguments on appeal: first, that the provisions of § 87-1 do not apply to a landowner who contracts to construct a dwelling on his own property and to subsequently convey that property with the completed dwelling thereon and second, that § 87-1 is uncоnstitutional as applied to defendants as a violation of Article I, Section 10, of the United States Constitution.
Defendants did not make any exceptions to the findings of fact or conclusions of law made by the court in its judgment. Their sole exception in the record is to their entry of appeal. The scope of review on appeal, therefore, is limited to whether the judgment in question is supported by the court’s findings of fact and conclusions of law. Rule 10(a), N.C. Rules App. Proc. Due to the defendants’ failure to except to any findings of fact, the trial court’s findings are deemed to bе supported by substantial competent evidence and are conclusive upon appeal.
Grimes v. Sea & Sky Corp.,
The courts of this State have held that an unlicensed person who, in disregard of § 87-1, contracts with another to construct a building for the cost of $30,000.00 or more, may not affirmatively enforce the contract or recover for his services and materials supplied under the theory of
quantum meruit
or unjust enrichment.
Helms v. Dawkins,
*652 For the purpose of this Article, a “general cоntractor” is defined as one who for a fixed price, commission, fee or wage, undertakes to bid upon or to construct any building ... where the cost of the undertaking is thirty thousand dollars ($30,000) or more. ...
The contract price is the cost of the undertaking.
Furniture Mart v. Burns,
As stated in
Helms v. Dawkins, supra
at 456,
The court’s conclusions that the defendants were unlicensed general contractors who had contracted to cоnstruct a dwelling for a price in excess of $30,000.00 support its judgment that defendants are barred from affirmatively asserting their
*653
claims under the contract.
Helms v. Dawkins, supra.
The defendants’ argument that they should not be so barred because they contrаcted to build the dwelling on their own property is not persuasive. Although we have been unable to find any case applying the § 87-1 prohibition to a builder who constructed a building on his own land, in our opiniоn, ownership of the land has nothing to do with the purpose of the prohibition. The purpose of § 87-1 is to regulate builders and “to protect the public from incompetent builders by forbidding them to maintain аn action on their contracts, thereby discouraging them from undertaking projects beyond their capabilities.
Builders Supply v. Midyette,
We do not reach defendants’ constitutional argument for two reasоns: (1) the exception on which it is purportedly based is an exception to their entry of notice of appeal and (2) the record discloses that defendant failed to raise it at the triаl court level. This Court will not pass upon a constitutional question not raised and considered in the court from which the appeal was taken.
Brice v. Moore,
For the reasons stated above, we affirm the judgment of the trial court.
Affirmed.
