115 Mass. 57 | Mass. | 1874
The only question presented for our decision, by this agreed statement, is whether the application for a jury to assess damages for land taken under the St. of 1869, c. 291, was made in the mode and within the time prescribed by law. The only point argued before us is that as to the limit of time. The statute, § 5, provides as follows :
“ The laws of the Commonwealth relating to the taking of lands for railroad purposes and the location and construction of railroads, shall be applicable to, and govern the proceedings in the taking of the lands described in the preceding sections; except that instead of the county commissioners, three disinterested persons shall be appointed by the Supreme Court as a board of commissioners, to adjudicate the damages for the taking of said lands and property, from whose decision an appeal to a jury shall he in behalf of either party, as is provided in cases of lands taken for railroad purposes.”
By the Gen. Sts. c. 63, §§ 21 & 22, it is provided in cases of lands taken for railroad purposes, that the damages “ shall upon the application of either party be estimated by the commissioners in the manner provided in laying out highways; ” and “ Either party, if dissatisfied with the estimate made by the commissioners, may, at any time within one year after it is completed and returned, apply for a jury to assess the damages.”
This application is also to be made to the county commissioners, who thereupon issue their warrant for a jury to be summoned by the sheriff; and the trial takes place in the county before the sheriff, or some person specially designated to preside.
The land in this case was within the city of Boston; the statute contemplated the taking of lands in the city of Boston only ; the application for a jury was made within one year after the estimate of the commissioners was completed and returned, but not at the next term of the Superior Court for the county after the estimate was made known to the parties.
The petitioners rely upon the phraseology of the section of the statute above quoted, contending that as the commissioners appointed under it are to act “ instead of the county commissioners,” it must have been intended that those provisions of the General Statutes and only those which are applicable to proceedings before county commissioners, should govern the proceedings under this statute. If we were to adopt this construction so far as to give the petitioners the benefit of the provision of law allowing them to apply for a jury at any time within one year from the return of the estimate by the commissioners, it would not avail to support this application; because it was not made to the tribunal contemplated by the provisions which contain that limitation of time, nor to one corresponding thereto or acting instead thereof.
When this application was made and until the St. of 1873, c. 261, there was no general provision of law for a jury in cases of land taken for railroad purposes, by application to the Superior Court, except in cases of land taken within the city of Boston. And the right so to apply to the Superior Court for the county of Suffolk was expressly limited to the next term after the estimate was made known to the parties.
This application must fail therefore, whether the construction contended for be adopted or rejected; and the judgment of tho Superior Court dismissing the same must be Affirmed.