ROBERTS ELECTRIC, INC. v. Foundations, Etc., Inc.ROBERTS ELECTRIC, INC. v. Foundations, Etc., Inc.
COLIE, J.A.D.
Roberts Electric, Inc., instituted suit against Foundations & Excavations, Inc., alleging that it contracted with the defendant to perform electrical work on a garage of Public Service Interstate Transportation Company at an agreed price of $3,520, payable monthly as work progressed. The complaint alleged that there was due and unpaid $1,060 for labor and materials furnished in the months of May, June and July, 1948, and also a claim for loss of
“Plaintiff alleges that the defendant engaged him to do certain electrical work. Plaintiff started to do the work and under the contract was to submit monthly bills as the work was completed. Plaintiff submitted bills and the defendant failed to pay. Plaintiff stopped work. Plaintiff sues for $1,914.00.
“Defendant alleges the plaintiff was guilty of faulty performance, and that it was not in keeping with the contract; that plaintiff was guilty of breach of contract.
“Defendant denies the allegations of the plaintiff.
“Defendant files counterclaim to recover the cost of completing the job started by the plaintiff. That total cost of completing the job over and above the money already paid to the plaintiff was $4,912.36 which exceeded the amount of the contract with the plaintiff by the sum of $2,342.76.”
The case was tried and the jury returned a verdict in favor of the plaintiff for $1,737.32 from which judgment this appeal is taken.
Four grounds are advanced why the judgment should be reversed. The first ground has to do with the action of the court in permitting an amendment to the pretrial order to include an item of $106 for work said to have been performed by the plaintiff in August, 1948. The complaint filed in the cause limited the period for which recovery was sought to the months of May, June and July. At the trial, however, the plaintiff‘s witness, Hosey, was asked the amount of the bill for August. Objection was made on the ground of surprise but after a colloquy between counsel and the defendant‘s attorney, the latter requested and was granted a recess to discuss the matter with his client and then reported that certain records had been sent for and expressed the hope that
It is next argued that since plaintiff had served a stop notice under which its claim against the owner, if established by judgment against the defendant, was limited to $1,064, it was error to permit the plaintiff to include a claim for loss of profits. This argument loses sight of the fact that the suit was one for damages against the defendant for breach of contract. Among the damages recoverable, if established by adequate proof, was loss of profits. The fact that the plaintiff saw fit to serve a stop notice against the owner of the property does not limit his recovery against the defendant to the sums stated in the stop notice. In Friedman v. Stein, 4 N.J. 34 (1950), it was pointed out that the statutory lien is separate and distinct from the underlying debt, the lien affording a cumulative remedy for the enforcement of the debt. Stop notices exist only by virtue of the Mechanic‘s Lien statute, and we think that what was said in the Friedman case is equally applicable to them.
The judgment is affirmed.