Lead Opinion
Opinion
The plaintiff, Robert J. Bamabei Contracting, LLC, appeals from the judgment of the trial court rendered in accordance with a report filed by an attorney fact finder (fact finder). The court rendered judgment awarding the plaintiff $292 in compensatory damages pursuant to a subcontract agreement (agreement) with the defendant Aspinet Constmction Company.
The following facts and procedural history are relevant to the resolution of this appeal. In early 2004, the Greater Hartford Jewish Community Center, Inc. (community center), retained the defendant as the general contractor for a renovation project (project) at the community center’s West Hartford location. On March 19, 2004, the plaintiff and the defendant executed the agreement, whereby the plaintiff was to perform subsurface constmction services for the project for a total price of $37,960. The dispositive provisions of the agreement are as follows:
“Section 4. ... If at any time there shall be evidence of any hen or claim forwhich, if established, [the defendant] or the [community center] might be or become hable and which is chargeable to [the plaintiff], [the defendant] shah have the right to retain out of any payment due or to become due by [the defendant] to [the plaintiff] an amount sufficient to indemnify [the defendant] and [the community center] against such hen or claim ....
* * *
“Section 7. The following conditions are hereby made a part of this [agreement . . .
“(d) The [plaintiff] agrees ... to comply with ah [fjederal, [s]tate, [m]unicipal and local laws, ordinances, codes and regulations governing and to pay ah costs and expenses required thereby ....
* H= *
“Section 8. (a) [The plaintiff] shah submit in writing to [the defendant] ah claims for adjustment in the [agreement] price ... for like claims by [the defendant] against [the community center — namely, through a written change order]. . . . [The defendant’s] liability to [the plaintiff] for such claims is limited to any adjustment which shah be made by [the community center] to [the defendant’s] contract on account of [the plaintiffs] claim.”
On the same day that the parties executed the agreement, the defendant approached a third party, George Toreho Engineers, P.C. (Toreho), to perform engineering services in connection with the project, as such services were beyond the plaintiffs expertise. The defendant retained Toreho to ensure that the plaintiffs work complied with apphcable specifications of the West Hartford building code (building code), including, specifically, § 1816.13. After the plaintiff commenced work on the project, the defendant submitted a written change order on May 17, 2004, by which the agreement price was increased from $37,960 to $41,275. On June 11, 2004, the plaintiff submitted an invoice to the defendant in the amount of $51,200, although it is undisputed that the plaintiff failed to submit a written change order pursuant to § 8 (a) of the agreement. Despite the plaintiffs noncompliance with § 8 (a), the defendant submitted the plaintiffs invoice to the community center for approval, which the community center eventually declined to pay due to the lack of supporting documentation. On August 3, 2004, the defendant submitted a second written change order backcharging the agreement price by $16,435.50, the cost of Torello’s services on the project, pursuant to § 7 (d), thereby reducing the plaintiffs total compensation to $24,839.50. The defendant then refused to pay the plaintiff $9925, the difference between the agreement price of $41,275 and the plaintiffs invoice of $51,200, claiming that it was not liable for this amount pursuant to § 8 (a) of the agreement. Additionally, the defendant maintained that the plaintiff was responsible for the expenses associated with Torello’s work pursuant to § 7 (d) of the agreement, as those services were required by the building code.
On July 11, 2005, the plaintiff commenced this action claiming, inter alia, breach of contract by the defendant. In support of its claim, the plaintiff alleged that the defendant was responsible for the full invoice amount of $51,200 and further that the defendant incorrectly backcharged the agreement price by the cost of Tor-ello’s services. In response, the defendant countered that the plaintiff was not entitled to the invoice amount of $51,200 because the community center never approved this adjustment to the agreement price. The defendant also argued that because the plaintiff already had been paid $24,547.50, and because the agreement price of $41,275 was properly reduced by $16,435.50, the cost of Torello’s services,
The plaintiff claims that the court improperly overruled its objection to acceptance of the fact finder’s report and recommendations. Specifically, the plaintiff argues that the fact finder incorrectly concluded that the $51,200 invoice amount in effect constituted a claim for $9925 in extra compensation, rather than a legitimate adjustment to the agreement price of $41,275.
Before addressing the merits of the plaintiffs claims, we begin with the applicable legal principles and standard of review governing our analysis. “A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court ... or the Superior Court reviewing the findings of . . . attorney trial fact finders. . . . This court has articulated that attorney trial fact finders and [fact finders] share the same function . . . whose determination of the facts is reviewable in accordance with well established procedures prior to the rendition of judgment by the court. . . .
“The factual findings of a[n] [attorney trial fact finder] on any issue are reversible only if they are clearly erroneous. ... [A reviewing court] cannot retry the facts or pass upon the credibility of the witnesses. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” (Internal quotation marks omitted.) LPP Mortgage, Ltd. v. Lynch,
I
The record in the present case unequivocally demonstrates that the fact finder had sufficient evidence to conclude that the plaintiff was entitled to only $292 in compensatory damages pursuant to the parties’ agreement. With respect to the
II
Turning to the plaintiffs claim with respect to the $16,435.50 backcharge, the record is equally supportive of the fact finder’s conclusion that this amount was appropriately deducted from the $41,275 agreement price. In support of its claim, the plaintiff argues that the defendant is “attempting to shift the burden of engineering costs” to the plaintiff. Section 7 (d) of the agreement explicitly provides, however, that “[the plaintiff agrees] ... to comply with all [f]ederal, [s]tate, [m]unicipal and local laws, ordinances, codes and regulations governing [the performance of its work on the project] and to pay all costs and expenses required thereby . . . .” Testimony during trial before the fact finder confirmed that Torello was hired by the defendant to ensure the plaintiffs compliance with applicable specifications of the building code. Indeed, if Torello had not been employed by the defendant, the plaintiff would not have been in compliance with the building code and, as such, would not have been legally able to commence and to continue work on the project. Moreover, there is no dispute that the defendant paid Torello $16,435.50 for services rendered in connection with the plaintiffs work. Because the defendant’s payment to Torello constituted an expense for which the plaintiff was liable pursuant to § 7 (d) of the agreement, we fail to see how the fact finder’s conclusion to reduce the plaintiffs compensation by the cost of such services was clearly erroneous. This determination is further supported by § 4 of the agreement that allows the defendant “to retain out of any payment due” to the plaintiff “an amount sufficient to indemnify” the defendant against an expense chargeable to the plaintiff. Here, the fact finder had ample evidence before him from which to find that the $16,435.50 was an expense chargeable to the plaintiff, and, therefore, the conclusion that the agreement price of $41,275 should be reduced by this amount was not clearly erroneous.
In sum, the plaintiff “essentially requests that we transgress our function as an appellate court and weigh conflicting evidence. . . . This, we cannot do.” (Citation omitted.) LPP Mortgage, Ltd. v. Lynch, supra,
Ill
As a final matter, we address an unpreserved claim that we ordinarily would dismiss in a footnote. The plaintiff contends, for the first time on appeal, that the defendant failed to comply with § 7 (f) of the agreement. For multiple reasons, we reject that claim.
First and foremost, the claim is not properly before us, as there is no indication in the record that the plaintiff properly preserved it for appeal. In neither its October 29, 2007 trial brief nor its November 26, 2007 objection to acceptance of the fact finder’s report and accompanying memorandum of law did the plaintiff mention, let alone distinctly state, the question of the defendant’s alleged failure to comply with § 7 (f) of the agreement, as our law requires. See Practice Book § 5-2; see also Practice Book § 60-5; Remillard v. Remillard,
Apart from that infirmity, the plaintiffs claim concerning § 7 (f) is inadequately briefed, as its analysis consists of a single sentence in its principal brief. After quoting the language of § 7 (f), the plaintiff baldly asserts that the defendant “makes no claim that written notice was given and [the plaintiff] never received any such notice to which [it] had a legal right under [the] subcontract.” The plaintiff does not indicate how that claim was preserved or how the trial court ruled thereon. It further does not set forth an applicable standard of review or any substantive analysis or discussion of applicable precedent. Our appellate courts repeatedly have stated that “[w]e are not required to review issues that have been improperly presented to this court through an inadequate brief. . . . Analysis, rather than mere abstract assertion, is required in order to avoid abandoning an issue by failure to brief the issue properly. . . . Where a claim is asserted in the statement of issues but thereafter receives only cursory attention in the brief without substantive discussion or citation of authorities, it is deemed to be abandoned.”
The concurring and dissenting opinion does not acknowledge that the plaintiff failed to preserve or to brief its claim adequately regarding § 7 (f) in affording review of the plaintiffs claim. In so doing, that opinion conflates the scope of our review with a standard of review, two distinct aspects of appellate practice. “Scope of review and standard of review are often— albeit erroneously — used interchangeably. The two terms carry distinct meanings and should not be substituted for one another. Scope of review refers to the confines within which an appellate court must conduct its examination. ... In other words, it refers to the matters (or what) the appellate court is permitted to examine. In contrast, standard of review refers to the manner in which (or how) the examination is conducted.” (Internal quotation marks omitted.) Brunswick v. Statewide Grievance Committee,
The concurring and dissenting opinion also opines that review of the plaintiffs unpreserved claim is warranted under Practice Book § 60-5, which recognizes the plain error doctrine.
It is elemental that this court, as an intermediate appellate body, is bound by the precedent set forth by our Supreme Court. See, e.g., Stuart v. Stuart,
Numerous doctrines of reviewability are contained in our case law and our rules of appellate procedure. Uniform application thereof ensures that similarly situated litigants are treated in a consistent and, hence, just manner. See, e.g., Silkwood v. Kerr-McGee Corp.,
“Plain error is a doctrine that should be invoked sparingly.” (Internal quotation marks omitted.) State v. Bowman,
In addition, even if the plaintiff had requested review of its claim pursuant
The judgment is affirmed.
In this opinion HARPER, J., concurred.
Notes
The plaintiff withdrew its cause of action as to the defendant Sovereign Bank and the defendant Greater Hartford Jewish Community Center, Inc., on May 19, 2006. Because Aspinet Construction Company is the sole defendant in this appeal, we refer to it as the defendant.
The $9925 figure represents the difference between the plaintiffs invoice amount of $51,200 and the agreement price of $41,275, as documented by the defendant’s change order, dated May 17, 2004.
We note that the plaintiffs appellate brief also fails to comply with the requirements of Practice Book § 67-4. The statement of issues on page one does not include “[a] concise statement setting forth, in separately numbered paragraphs, without detail or discussion, the principal issue or issues involved in the appeal, with appropriate references to the page or pages of the brief where the issue is discussed . . . .” (Emphasis added.) Practice Book § 67-4 (a). Even more troubling is the fact that although its statement of issues includes multiple claims, the brief does not include an “argument, divided under appropriate headings into as many parts as there are points to be presented, with appropriate references to the statement of facts or to the page or pages of the transcript or to the relevant document”; Practice Book § 67-4 (d); nor does it include “on each point ... a separate, brief statement of the standard of review the appellant believes should be applied.” Practice Book § 67-4 (d). (Emphasis added.) As in the defendants’ appellate brief in Paoletta v. Anchor Reef Club at Branford, LLC,
We are perplexed by the concurring and dissenting opinion’s invocation of the “ ‘exceptional circumstances’ ” exception. That exception, as noted by the secondary authority relied on by that opinion, was set forth in State v. Evans,
While the secondary source cited by the concurring and dissenting opinion states that the plain error doctrine allows an appellate court “to consider almost any new issue on appeal”; C. Tait&E. Prescott, Connecticut Appellate Practice and Procedure (3d Ed. 2000) § 8.5, p. 299; that statement must be read in the context of the precedent of our Supreme Court governing the application of that doctrine. We thus read that statement as pertaining to unpreserved claims for which the appellant affirmatively has requested review. Indeed, neither the authors of that secondary authority nor the concurring and dissenting opinion cite to any Supreme Court authority indicating otherwise.
Concurrence Opinion
concurring in part and dissenting in part. Two cardinal principles of law inform our review of contracts. One is that courts will not rewrite a contractual provision unwisely made by a party. Crews v. Crews,
I respectfully disagree with the majority’s refusal to review the plaintiffs claim on appeal that the defendant improperly failed to comply with a contractual condition precedent when it withheld a $16,435.50 back-charge from the plaintiffs compensation. The trial court’s decision to enter judgment on that issue for the defendant is contrary to both cardinal principles of contract interpretation and to the plain language of § 7 (f) of the agreement of the parties which provided that as a condition precedent to the defendant’s undertaking any work that it claimed was the plaintiff subcontractor’s responsibility forty-eight hour prior notice had to be given to the plaintiff subcontractor. The effect of the majority opinion is to apply a condition precedent to prevent the plaintiffs recovery for extras but to ignore another unfulfilled condition precedent to permit the defendant’s backcharge. This result is unjust. Although the president of the defendant acknowledged that the plaintiff had performed satisfactorily, yet 40 percent of the contract price has been withheld from the plaintiff in a $16,435.50 backcharge. This has been withheld on the theory that the defendant was entitled to deduct this amount because it contracted with Torello for work that was the plaintiffs responsibility under its subcontract with the defendant. Yet, the record is devoid of any evidence that the defendant complied with the contractual provision requiring forty-eight hours prior notice to the plaintiff before doing so. “A condition precedent is a fact or event which the parties intend must exist or take place before there is a right to performance. ... If the condition is not fulfilled, the right to enforce the contract does not come into existence.” (Internal quotation marks omitted.) Gianetti v. Health Net of Connecticut, Inc.,
The plaintiff has briefed its claim that the actions of the defendant in withholding the $16,435.50 were “unilateral.” As pointed out in the plaintiffs brief, our review of contractual disputes arising out of definitive contract language is plenary. Embalmers’ Supply Co. v. Giannitti,
There could be no surprise to the trial court or the defendant by virtue of the plaintiffs failure to brief this provision at trial that § 7 (f) requiring forty-eight hours notice was pertinent. The trial court was to consider all definitive provisions of the contract as a whole, whether the plaintiff did or did not brief them at trial. Lar-Rob Bus Corp. v. Fairfield,
