Robert Hroch appeals the district court’s 1 grant of summary judgment dismissing his action under 42 U.S.C. § 1983 against the City of Omaha and Anderson Excavating & Wrecking Company. Hroch argues that the defendants violated his procedural due process rights by demolishing buildings not included in the City’s notice of condemnation, and violated his Fourth Amendment rights when they implemented the condemnation order without a warrant. We affirm.
I.
Hroch is in the business of demolishing buildings. He also owns numerous parcels of real property. In 1978, Hroch purchased the abandoned Alamito Dairy buildings in Omaha. The premises included at least four structures and were defined by a single legal description. The entire property was typically identified by Hroch and others as “2601 Leavenworth Street,” which was the only street address used for the premises by the *695 Postal Service, local utilities, and the county tax assessor. Hroch utilized the dairy buildings for storage until their demolition in early 1990. The buildings deteriorated, became a haven for transients, and were the subject of numerous public complaints. The City condemned these structures in 1984 and again in 1986, but each time Hroch obtained a state court injunction blocking the proposed demolition.
On May 18, 1989, following a warrant search of one of the buildings, the City sent Hroch a letter that listed some thirty-nine cited “deficiencies,” suggested that Hroch obtain a permit to repair or demolish “this commercial building,” and advised that a hearing would be held if he did not do so. Hroch did nothing. On June 29, the City sent Hroch notice that a condemnation hearing would be held on August 3, 1989. The notice recited the legal description of the entire Alamito Dairy property but specifically referred only to “the commercial building situated on the above described property.” Though he received this notice, Hroch did not attend the condemnation hearing.
On August 7, 1989, the City sent Hroch a formal notice of condemnation. This notice set forth the legal description of the entire property, added the reference, “Commonly known as 2601 Leavenworth Street,” and then recited:
WHEREAS, on August 3, 1989, a condemnation hearing was held and the above mentioned buildings was declared a nuisance and condemned.
THEREFORE, you as owner ... are hereby ordered to demolish and remove the above mentioned buildings. You shall have fifteen (15) days from the date of this hearing to appeal to the City Council____ If no appeal is taken by that time, this order will become effective at that time and will be final, as provided by Chapter 43 of the Omaha Municipal Code.
Hroch did not appeal. Instead, in September 1989, he petitioned the Douglas County District Court to enjoin the demolition on due process and other grounds. The state court denied an injunction. The record does not reflect the final disposition of that lawsuit.
In December 1989, after the City had selected Anderson Excavating as the demolition contractor, Hroch’s attorneys wrote Anderson, stating:
It is our understanding that you have been awarded the contract for the demolition of 2601 Leavenworth. Please be advised that the validity of the condemnation order is currently the subject of litigation in the District Court of Douglas County, Nebraska. You are advised that the bid calls for the demolition of 2601 Leavenworth, not 2615 Leavenworth.
In early 1990, Anderson Excavating demolished all of the Alamito Dairy buildings lying within the legal description set forth in the condemnation notices. Hroch then commenced this damage action.
II.
Hroch first contends that, because some of the Alamito Dairy buildings were located at 2615 Leavenworth Street, his right to procedural due process was violated when those buildings were demolished without fair notice. At the outset, we must disagree with the City’s contention that this issue is controlled by
Parratt v. Taylor,
Nevertheless, we conclude that Hroeh’s procedural due process contention is without merit. Hroch does not challenge the predeprivation procedures prescribed in the City’s condemnation ordinances as facially invalid. Thus, he does not challenge the “established state procedure,” as the plaintiff did in
Logan v. Zimmerman Brush Co.,
455
*696
U.S. 422, 436,
First, Hroeh abandoned this claim when he failed to take advantage of any of the prede-privation remedies afforded by the City. Hroeh did not respond to the City’s May 18, 1989, suggestion that he apply for a permit to repair or demolish the cited building; if he had, he would surely have learned whether the City was also concerned about the condition of the other Alamito Dairy buildings. Nor did Hroeh attend the August 3 condemnation hearing, where the scope of the requested condemnation order could have been clarified and debated. He did not appeal the August 7 condemnation order to the City Council, even though the ambiguous breadth of the order was apparent by comparing the legal description contained in the notice with its grammatically incorrect reference to “buildings was declared a nuisance.” Finally, Hroeh did not include this issue in his unsuccessful petition to the state court to enjoin the demolition. “The fundamental requirement of due process is the
opportunity
to be heard ‘at a meaningful time and in a meaningful manner.’ ”
Mathews v. Eldridge,
Second, Hroeh obviously had actual notice, as well as fair notice, that the City was seeking to condemn all the Alamito Dairy buildings. This was the City’s third attempt to condemn these structures. Although the notices sent by the City were not models of clarity, they consistently recited the legal description of the entire property, and the critical August 7 notice repeatedly referred to “buildings.” As Hroeh himself alleged in requesting an injunction from the state court, the entire premises were “commonly known as 2601 Leavenworth Street.” Hroch’s December 1989 warning letter to Anderson — written when state court injunc-tive remedies were presumably still available^ — demonstrates that he knew the scope of the intended demolition
2
and was raising the street address issue to throw yet another obstacle into the City’s condemnation path. Because Hroeh had actual notice that the City intended to condemn all buildings on the premises, there was no procedural due process violation.
See generally Mullane v. Central Hanover Bank & Trust Co.,
III.
Relying upon
Soldal v. Cook County,
— U.S. -,
Conner
is distinguishable from this ease in at least two critical respects. First, Hroeh petitioned for state court review of the condemnation order and sought a temporary injunction preventing demolition. The state court denied an injunction, and Hroeh does not allege that he urged that court to restrict or monitor the manner in which the demolition was then accomplished. Hroch’s Fourth Amendment argument simply ignores the question whether this judicial oversight of
*697
the condemnation process “provides a constitutionally adequate substitute for a warrant.”
Donovan v. Dewey,
Second, in
Conner
city officials broke down a fence and seized the vehicles from plaintiffs’ enclosed backyard.
See
The Fourth Amendment protects against unreasonable searches and seizures. Particularly given the strong dissent in
Conner, see
The judgment of the district court is affirmed.
Notes
. The HONORABLE LYLE E. STROM, Chief Judge of the United States District Court for the District of Nebraska.
. Hroch's reply brief explains that he "received notice that buildings at 2615 Leavenworth might be targeted for demolition only because he is a demolition contractor himself, and fortuitously received a proposal for bids on demolition of the structures."
.
Compare United States v. Articles of Hazardous Substance,