281 F. 904 | 6th Cir. | 1922
Plaintiff in error, being engaged in the business of excavating and grading, entered into a construction contract with the defendant in error for the grading of about nine miles of new railroad. Eventually the work was finished and accepted, and the amount admitted to be due was paid. The contractor brought this action in the court below, seeking to recover the damages caused by three alleged breaches of the contract. The first was for failure to furnish the contractor with the place to do the work as agreed; the second, that the contractor was required to use unsuitable material in making fills; and the third, that the incidental diversion of a water course was required to be made upon such an unskillful plan as' caused injury to the contractor. When the issues were complete by petition, amended petition, and demurrer, the trial court sustained the demurrer and dismissed the petition. The contractor now seeks to have this action reviewed and reversed.
For the purposes now involved, it has not been doubted that the petition states a good cause of action as to each of the three elements of damage, save for those provisions of the contract which gave the defendant’s chief engineer large power of directing how the work should be done and certifying the amount earned, thus making him in many respects am arbitrator; and it is the validity and effect of these provisions which must control the disposition of the case. Sections 25 and 26 of the contract are given in the margin.
We will not undertake to decide whether section 26 can be limited so as not to apply to fundamental questions of law or fact, not arising in the course of the execution of the contract, hut which pertain to a refusal to perform initial obligations. However that may be, and without making here any review of the decisions, we have become satisfied that, unless it can be so limited, it is invalid, and that, if it is so restricted, it does not reach a cause of action for failure to provide the right of way upon which the work can be done. In either case it forms no bar to the prosecution of a suit at law for the damage resulting from the first alleged breach of contract.
More in detail, the case made by the declaration upon this subject is to the effect that the road to be graded was about 11 miles long; that by the contract “the company shall provide lands upon which the work under this contract is to be done”; that the contractor was required to proceed with the utmost diligence; that, in order for the work to proceed as was required, it was necessary 'to have the right of way not only where cutting was to be done, but also where a fill was to be made, and also over the intervening space; that, although the contract was made in May, 1915, and to be completed by August, 1916, yet, because the defendant delayed in furnishing the right of way, the completion of the work was delayed for about one year, and the plaintiff was damaged by reason of its equipment standing idle and expense caused in various specified ways; and that the obtaining of much of the essential right of way was delayed until the summer and fall of 1915, thus throwing the work into the winter, and that some of it was delayed until 1916 and even 1917.
It is plaintiff’s theory that the defendant’s legal duty under the contract was to provide the right of way just as rapidly and completely as necessary to meet the contractor’s reasonable plans to expedite the work and to do it economically; it is defendant’s theory that the contractor must accept, as part of the situation, such delay as was reasonably incident to acquiring the right of way by negotiation or by legal proceeding. Whatever might be the case, if the contractor knew that the right of way was not definitely obtained or contracted for, we find that the declaration here alleges that the contractor supposed the right of way was available to the railroad, ready for use, and had no reason to understand that there would be delay on that account. When the qúestion arises upon demurrer to such a declaration, we think the plaintiff’s theory, above stated, must be adopted, and that cause of action for the resulting damages thus arose.
It is clear to us that such a controversy cannot be distinguished in principle from one where the railroad or contractor might wholly refuse to proceed with, or even to begin the performance of, the contract, and that one of the latter kind would not come within the purview of an arbitration agreement of this character.
So far as the judgment denied any right to recovery on account of the damages claimed for failure to furnish the right of way, it was erroneous; but the conclusions of the trial court are affirmed as to the second and third alleged breaches.
Accordingly, the judgment is reversed, and the case remanded for a new trial.
“25. Power of Engineer. The engineer shall have power to reject or condemn all work or material which does not conform to this contract; to direct the application of forces to any portion of the work which, in his judgment requires it; to order the force increased or diminished; and to decide questions which arise between the parties relative to the execution of the work.”
“26. A djustment of Dispute. All questions or controversies which may arise between the contractor and the company, under or in reference to this contract, shall be subject to the decision of -the chief engineer, and his decision shall be final and conclusive upon both parties.”