This suit invоlves one pipeline, two litigants, three tracts, and four deeds. In the fourth and final deed, Robert Ford granted a pipeline easement across three traсts of land, but now claims he did so based on misrepresentations about the three previous deeds. The court of appeals unanimously held his fraud claim barred by limitаtions, but in a divided opinion ordered the easement cancelled and the pipeline removed anyway because no statute of limitations applied to an equitable action to quiet title.
In thе summer of 1998, Mobil Chemical Company (predecessor of petitioner Exx-onMobil Chemical Company) bought a 12-inch-wide easement for a propylene рipeline. The recorded deed included a map showing the pipeline crossing three tracts of land, but the text of the easement described the servient еstate by referring to another deed that described only one tract. In an amended easement signed three months later granting temporary access for оperations, the original easement was described as crossing all three tracts. Two days after the amendment, Ford bought all three tracts by special warrаnty deed expressly subject to Mobil’s easements. Four months later, Ford signed another amendment (in return for $20,000) relocating the pipeline’s route across all three of his tracts. Ford claims he signed this amendment only because Mobil falsely represented that the original easement covered all three tracts, when in faсt it covered only one.
*617 Five years after signing the last amendment, Ford sued for real estate fraud. See Tex. Bus. & Com.Code § 27.01. The trial court granted summary judgment for Ford, awarding him $36,167 and ordering the pipeline removed. The court of appeals reversed the damage award (holding limitations barred Ford’s fraud claim) but affirmed the removal order (hоlding quiet title actions have no statute of limitations). Both sides petitioned for review.
As a preliminary matter, we disagree with ExxonMobil that the judgment here is interlocutory because it did not expressly dispose of Ford’s statutory claim for expert witness fees.
See id.
§ 27.01(e) (providing fees for attorneys, expert witnesses, and copies of depositions). There is no presumption of finality for summary judgment orders, and the order here contains no unequivocal statement of finality.
See Lehmann v. Har-Con Corp.,
ExxonMobil argues that the undisputed summary judgment evidence established attorney’s fees of $36,167 and expert fees
of $1,500,
1
and that the trial court’s award of precisely $36,167 means it adjudicated only the former. But the award was a lump sum that did not specify what it was for; that it may have been
incorrect
if it did not include both fees does not mean it was
interlocutory.
We have never held that an order disposing of all claims can be final only if it itemizes each and every element of damages pleaded. Similarly, a summary judgment order clearly disposing of a suit is final even if it does not break down that ruling as to each element of duty, breach, and causation.
See, e.g., M.O. Dental Lab v. Rape,
On thе merits, Ford argues the court of appeals erred in holding his fraud claim barred by limitations. The parties agree this claim had to be brought within four years of when the fraud should have been discovered by reasonable diligence. Tex Civ. PRau
&
Rem.Code § 16.004(a)(4);
Little v. Smith,
But we agree with ExxonMobil that the court of appeals erred in holding Ford’s demand for removal of the pipeline was not barred toо. The court stated two reasons limitations did not apply: (1) Exxon-Mobil’s motion did not assert limitations as to Ford’s quiet title claim, and (2) an action to quiet title is never time-barrеd.
As to the first, ExxonMobil did not have to assert limitations separately as to quiet title because Ford’s pleadings, construed liberally, did not plead it as an independеnt cause of action. Quiet title is not mentioned among the facts or claims in Ford’s petition, appearing instead only in an introductory section and the prаyer as part of a list of items (like a mandatory injunction and attorney’s fees) that are merely forms of relief. 2 Having asserted limitations against Ford’s fraud claim, ExxonMоbil did not have to assert limitations against each item of legal or equitable relief that stemmed from it.
As to the second, limitations would have barred an action tо quiet title here even if it had been pleaded as an independent cause of action. Granted, an equitable action to remove cloud on title is not subject to limitations if a deed is void or has expired by its own terms.
Watson v. Rochmill,
Deeds obtained by fraud are voidable rather than void, and remain effective until set aside.
Nobles v. Marcus,
Accordingly, without hearing oral argument, we (1) rеverse the portion of the court of appeals’ judgment granting Ford quiet title, requiring removal of the pipeline, and granting other related relief, (2) affirm the court of appeals’ holding that Ford’s fraud claim was barred by limitations, and (3) render judgment for Exxon-Mobil. See TexR.App. P. 59.1.
Notes
. In his summary judgment motion, Ford sought $51,667 in attorney's fees (one-third of the easement’s alleged value) and $1,500 in expert witness fees (based on an affidavit). ExxonMobil did not respond to the expert-fee claim, but challenged the attorney’s fees by attаching an affidavit disputing the value of the easement. In his response, Ford accepted ExxonMobil’s lower property valuation "to avoid a fact questiоn," lowering his attorney's fee claim to $36,167.
. Paragraph 2 of Ford’s complaint identified the parties and the property at issue, and described the suit as one "to аnnul and cancel an easement on real property, for a mandatory injunction requiring removal of a pipeline located upon real prоperty as set forth below and removing the cloud on title to the pipeline strip and quieting title to said pipeline strip in Plaintiff.” Ford's prayer in his petition requested judgment for each of those items as well as attorney and expert witness fees.
