In this appeal, the Morrises challenge the decision of the United States Court of Federal Claims, which dismissed as unripe their claim that regulatory provisions of the Endangered Species Act effected a taking compensable under the Fifth Amendment.
See Morris v. United States,
I
In 1995, the Morrises paid $2,500 to purchase a half-acre lot adjacent to the Eel River in Humboldt County, California.
Morris,
After being contacted by the Morrises, the National Marine Fisheries Service (“NMFS” or “the agency”) visited the property to evaluate whether harvesting the trees would violate the Act by interfering with the behavior patterns of certain fish in the Eel River.
The government moved to dismiss the claim on the pleadings, contending that it was unripe because the Morrises never applied for an ITP and, consequently, the government never took a final action restricting the use of the property. The Court of Federal Claims agreed, holding that the Morrises must at least make an application for an ITP before their claim can ripen.
Absent an express statutory grant of jurisdiction to the contrary, the Tucker Act provides the Court of Federal Claims exclusive jurisdiction over takings claims for amounts greater than $10,000.
See Palm Beach Isles Assocs. v. United States,
II
According to the Morrises, their takings claim is ripe for review because the cost of the permitting process exceeds $10,000 and is greater than the value of their property, and the government has no meaningful discretion to change those facts. Thus, argue the Morrises, the agency has no further discretion to reduce the economic impact of the regulatory scheme and the effects of that scheme are known to a reasonable degree of certainty. The Morrises also conditionally challenge the Court of Federal Claims’s decision on procedural grounds. They argue that if the Court of Federal Claims dismissed their claim on the premise that their allegations of the cost of the permitting process were not accurate, the court erred because it is required to accept their factual allegations as true.
The government responds that the Mor-rises’ claim is unripe because the Morrises have made no attempt to use the available permitting procedure. It argues that there has been no agency decision impacting the property in question and that the futility exception extant in the law applies only where the agency’s conduct operates as a constructive denial of a permit, not where the permitting process is merely complex, arduous, or expensive. Concerning the Morrises’ procedural argument, the government argues that the condition has not been met because the Morrises’ claim was dismissed for not filing any application, not because the court disbelieved the Morrises’ allegations concerning the cost of the application. Addressing the alternative, the government argues that even if the Court of Federal Claims had decided the case on the grounds the Mor-rises suggest, such a decision is proper because a court addressing a challenge to subject matter jurisdiction in a dispositive motion is not bound to accept all of the allegations in the complaint as true and can look beyond the pleadings to determine whether it has jurisdiction.
Ill
The Morrises’ theory of taking is not grounded in any agency restriction of the actual use of their property, but on their obligation to apply for and secure a permit before harvesting the trees. That is to *1376 say, the agency has not told the Morrises that they either may or may not harvest the trees they seek to harvest, and if they may, what conditions, might apply to such permission. Instead, to be confident that they comply with the take prohibitions of the Act, the Morrises must file an application, which, accepting their assertion of the relevant costs, will cost more than their property is worth. Thus, it is the burdens attending the administrative procedure rather than the burdens attending a decision on restriction of use that define the Morrises’ claim.
We have no comment on whether a regulatory taking can arise in these circumstances. However, the Morrises’ theory of taking directs the ripeness inquiry. Under the Morrises’ theory, ripeness depends not on a final agency decision pertaining to the actual use of their property, but, instead, on a final agency decision establishing the cost of the application process.
The general rule is that a claim for a regulatory taking “is not ripe until the government entity charged with implementing the regulations has reached a final decision regarding the application of the regulations to the property at issue.”
Williamson County Reg’l Planning Comm’n v. Hamilton Bank,
Where further administrative process could reasonably result in a more definite statement of the impact of the regulation, the property owner is generally required to pursue that avenue of relief before bringing a takings claim.
See id.
(“The failure to follow all applicable administrative procedures can only be excused in the limited circumstance in which the administrative entity has no discretion regarding the regulation’s applicability and its only option is enforcement.”). Indeed, in
Heck
we went so far as to state: “the futility exception simply serves ‘to protect property owners from being required to submit
multiple
applications when the manner in which the first application
was rejected
makes it clear that no project will be approved.’ ”
IV
Here the Morrises’ claim is not ripe because there has been no final agency decision that has sufficiently fixed the cost
*1377
of the application. Even accepting that the Morrises must file an application to harvest their trees, the agency has discretion to assist the Morrises with the application. Because we have no idea and no way to predict what influence the wielding of that discretion will have on the cost of the application to the Morrises, this case cannot be ripe,
see Greenbrier,
The assumption that the cost of applying for the ITP is fixed and knowable is simply incorrect. The statute requires that an ITP applicant submit an HCP. 2 Notably, however, the Habitat Conservation Planning and Incidental Take Permit Processing Handbook, (Nov. 4, 1996) (“Handbook”), which guides NMFS in processing ITP applications, explains that NMFS is to provide assistance to an ITP applicant. It “strongly recommend[s]” that an applicant request technical assistance from NMFS and further states that the NMFS Field Office is “to provide[] technical assistance to the permit applicant.” We also note that the Handbook makes the Field Office “responsible for assisting the applicant in preparing the HCP” and contemplates an involved role for NMFS throughout the process. This is consistent with the agency’s position in this litigation and consistent with the estimate provided by the appellants’ consultant, which reflects that NMFS offered to prepare the National Environmental Policy Act Assessment and committed to providing technical assistance for the design of mitigation or conservation measures. Moreover, at argument, Appellants’ counsel candidly conceded that the agency has discretion concerning what the Morrises must do to complete a satisfactory HCP.
The cost of an ITP application is unknowable until the agency has had some meaningful opportunity to exercise its discretion to assist in the process. Because the cost to the Morrises of the ITP application following the exercise of NMFS’s discretion may be less than the alleged economic value of their property, deciding whether a taking would occur if the cost is greater is a hypothetical exercise. It is no more than asking the court to advise whether a taking will occur if the agency were to exercise its discretion in a particular manner. To allow a claim to ripen on the assertion that the exercise of an agency’s discretion would have a certain result, without permitting the agency to exercise that discretion would offend the requirement from
Abbott Laboratories v. Gardner,
V
Because the Morrises have not allowed NMFS to exercise its discretion, their claim is not ripe as a matter of law. Accordingly, this claim is not ripe until the Morrises make a meaningful attempt to engage NMFS by filing an application and requesting assistance. In addition, because the Court of Federal Claims correctly dismissed this claim as a matter of law, the Morrises’ procedural arguments do not establish reversible error.
The decision of the Court of Federal Claims to dismiss the complaint is affirmed.
COSTS
No costs.
AFFIRMED
Notes
. In relevant part, the Act states:
(a)(1) Except as provided in sections 1535(g)(2) and 1539 of this title, with respect to any endangered species of fish or wildlife listed pursuant to section 1533 of this title it is unlawful for any person subject to the jurisdiction of the United States to ...
(B) take any such species within the United States or the territorial sea of the United States;
16 U.S.C. § 1538 (2000).
. (2)(A) No permit may be issued by the Secretary authorizing any taking referred to in paragraph (1)(B) unless the applicant therefor submits to the Secretary a conservation plan that specifies—
(i) the impact which will likely result from such taking;
(ii) what steps the applicant will take to minimize and mitigate such impacts, and the funding that will be available to implement such steps;
(iii) what alternative actions to such taking the applicant considered and the reasons why such alternatives are not being utilized; and
(iv) such other measures that the Secretary may require as being necessary or appropriate for purposes of the plan.
16 U.S.C § 1539 (2000).
