Robert and Margaret Spence, plaintiffs below, appeal from the district court’s order granting summary judgment to defendants for claims based on 42 U.S.C. section 1983 and pendant state claims. We affirm.
Background
In 1979 the Spences applied to the City of Clearwater, Florida for a building permit for a single family home in a residential subdivision. In their application, they said that they would be building the house themselves and wished to complete only a portion of the structure before moving in; when the Spences wanted to move in, they would apply to the City for a Temporary Certificate of Occupancy (“TCO”). The City issued the building permit, and Mr. Spence began work at the job site; but six years later construction had progressed so slowly that the structure was still largely incomplete. 1 In 1984 the City declined to issue a TCO, and in 1985 the City told the Spences that their building permit would be revoked if specific items were not completed within six months. Before the six months passed the Spences contracted for the sale of the partially finished house. 2
Our Standard of Review
“Rule 56(c) mandates the entry of summary judgment ... against a party who fails to make a showing sufficient to éstablish the existence of an element essential to the party’s case, and on which that party will bear the burden of proof at trial.”
Celotex Corp. v. Catrett,
*258 Civil Rights Violations Under 42 U.S.C. 1983.
A. SUBSTANTIVE DUE PROCESS CLAIM
1. The Temporary Certificate of Occupancy
The Spences assert that the City’s refusal to issue a TCO deprived them of property without substantive due process. Although the contours of substantive due process are vague, no party in this case denies that substantive due process rights exist or that substantive due process can apply to land use decisions. The substantive due process doctrine proscribes “deprivation of a property interest for an improper motive and by means that were pretextual, arbitrary and capricious, and ... without any rational basis.”
Hearn v. City of Gainesville,
To support a claim under the fourteenth amendment for deprivation of property without due process of law, the Spenc-es must first establish that they had a valid “property interest” in some benefit that was protectible under the fourteenth amendment at the time they were deprived.
Scott v. Greenville County,
The relevant rule is section 109.3 of the Standard Building Code, used by the City of Clearwater, stating that “[a] temporary certificate of occupancy may be issued for a portion or portions of a building which may be safely occupied prior to final completion of the building.” (emphasis added). In April 1984 when the Spences applied for the TCO, they admitted that the structure was incomplete and unsafe and agreed to perform the essential work if the City would allow them to move in. At that time, necessary electrical panels and circuits were absent; the hot water heater, stove, bathing facilities and heating system were missing; interior walls were unfinished; and no insulation existed inside or out.
The Spences claim that after they submitted their application, the City bowed to pressure from the subdivision’s homeowners’ association and illegally increased the TCO requirements to include certain requirements that were also in the subdivision’s restrictive covenants. The Spences admit they never met reasonable minimum housing code standards for safe occupancy of the building. For example, they never installed a shower facility, a heating system other than a small fireplace, a cooking stove, an electrical panel connected with the electrical power supply, interior walls or insulation. The Spences do not dispute that the City had every right to require that they meet reasonable minimum safety requirements before a TCO would be issued. They take issue instead with the City's addition of requirements that the Spences claim go beyond safety requirements for the structure.
In
Littlefield v. City of Afton,
We note first that the Building Code states that a TCO
“may
be issued,” indicat
*259
ing that the municipality has discretion whether to issue the TCO.
See Sullivan v. Town of Salem,
The Spences also have failed to make any showing that they met the safety requirements for a TCO; therefore, they do not meet the second part of the test. The Spences have not demonstrated that but for the alleged addition of new and improper TCO requirements, the city’s officers would have been required to grant them the TCO; therefore they have shown no legitimate claim of entitlement to the TCO.
See Yale Auto Parts, Inc. v. Johnson,
2. The Building Permit
By a March 1, 1985 letter, Building Director Edward Bethel told the Spences that unless various conditions were met within six months — installing a driveway, sodding the yard, finishing the exterior of the structure, installing sidewalks, and removing all construction materials from the outside of the structure — the building permit would be revoked. The Spences, seemingly unable to meet these conditions despite the structure having been under construction for six years, contracted to sell the incomplete structure before the six months expired. The sale price, they claim, was $70,-000 less than the house’s fair market value.
The Spences argue that they were denied substantive due process because they were deprived of a property interest— their building permit — arbitrarily and irrationally. Assuming that the Spences had a protectible property interest in the building permit, we conclude that the Spences’ substantive due process rights were unviolated. The only act the Spences cite in support of their contention that they were deprived of property without due process is the March 1, 1985 letter from Bethel informing them that their building permit
would be
revoked in six months
if
certain conditions were not met. The Spences have, failed to show that they were unentitled in the meantime to continue construction under the permit; no reasonable interpretation of the letter would indicate that it contemplates anything other than future action by the City. The City never revoked the. permit and, because the Spences sold the house, never had to face the question of what would happen if the conditions imposed had not been satisfied in the time allowed. We conclude that the Spences have failed to make an adequate showing that they have been deprived of property without due process.
See Kerley Industries, Inc. v. Pima County,
We alternatively conclude that even if the Spences were deprived of the permit, they have not adequately shown an abuse of government power. The evidence is in
*260
sufficient to support a finding that the City was acting with an improper motive or was acting arbitrarily or capriciously without rational basis for its actions. The City’s actions were not such an abuse of governmental power that would raise the withdrawal of the permit to the stature of a constitutional violation.
Cf. Hull v. City of Duncanville,
Municipal building permits do not have to extend forever. The Standard Building Code section 106.3, titled Conditions of the Permit, stated that “Every permit issued shall become invalid unless the work authorized by such permit is commenced within six (6) months after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of six (6) months after the time the work is commenced, .... ” The City was troubled about the Spence situation, in which a permit had been issued five years earlier to build a one-family house in a well-kept neighborhood and Spence did just enough work to receive an inspection every six months to keep the permit alive. 4
After five years, the house was approximately one-half completed; because there was no landscaping, grading, or driveway, silt ran onto a neighbor’s yard and into the street. The citizens of the community were distressed, worried and complaining about their property values. The City could rationally care that a structure that was only half-completed after five years presented a problem with rodents, transients, sand erosion or vandals, injuring the surrounding neighborhood economically, environmentally, and aesthetically. Avoidance of such harms is a constitutionally permissible objective.
Jackson Court Condominiums v. City of New Orleans,
The City could rationally conclude that the building code did not intend for a building permit, once issued, to continue indefinitely. Even though there was no time limit expressed, the City could rationally interpret the Code to require that permitted construction must be substantially completed within a reasonable time of the permit’s issuance.
5
Cf. 7 P.
Rohan
Zoning
*261
and Land Use Controls
sec. 48.01[3] (1988) (if no time limit fixed, permit must be exercised within reasonable period after issuance);
Trans-Oceanic Oil Corp. v. City of Santa Barbara,
Finally, the conditions placed on continuation were not unrelated to land use planning, but were rationally related to the City’s protection of its neighborhoods.
Compare Pace Resources, Inc. v. Shrewsbury Township,
B. EQUAL PROTECTION CLAIM
The Spences contend that the City’s actions violated their equal protection rights under the fourteenth amendment. We disagree. The equal protection clause “is essentially a direction that all persons similarly situated should be treated alike.”
City of Cleburne, Texas v. Cleburne Living Center, Inc.,
In this case, the Spences have shown no one similarly situated who has been treated more favorably. No other single-family lot owner had spent six years constructing a bare shell that was unfit to live in, yet demanded the right to live in it and build it around him at his convenience. Building Director Bethel stated that in his thirty-eight-year experience — including the years before he was employed by the City of Clearwater — he had never issued a TCO for a single family residence. Assistant City *262 Manager Haeseker stated that she knew of perhaps three single family TCOs that had been issued during her seven-year tenure with the City. In those instances, all construction had been completed except for the sidewalks, and the City had put money in escrow to construct the sidewalks if the owner did not do so.
The Spences were not in the same situation as those persons issued a TCO for a single family residence and have thus completely failed to show how the City’s denial of the TCO deprived them of equal protection under law.
Compare Cordeco Development Corp. v. Santiago Vasquez,
We stress that federal courts do not sit as zoning boards of review and should be most circumspect in determining that constitutional rights are violated in quarrels over zoning decisions.
Raskiewicz v. Town of New Boston,
Notes
. The Spences do not contend that the City was responsible for the lack of construction progress. Instead they cite financial and other personal difficulties as the cause, including inadequate financing, inadequate manpower, inexperience, loss of job, inadequate time, redesign of building, head and chest injuries, oral surgery, surgery on hand, a broken foot, wife’s employment, poor health of Spence’s father, and the weather.
. The deed was transferred on October 1, 1985.
. The Spences also contend that they had an oral contract with the City that the City would issue the TCO upon their meeting minimum housing code requirements in their new home. We do not decide whether such a contract existed, but conclude that the Spences have failed to show that the City breached any duty to perform under the agreement because the Spences never demonstrated that they met minimum housing code requirements.
. Because of its concern, the City wrote to the Executive Director of the Building Code Congress for an interpretation of the Code: “I realize Section 106.3 does not address this situation as strictly interpreted, but it is hard to believe the intent of the code is to allow construction to go on for this length of time in any neighborhood.” Letter from Edward Bethel, Director, Bldg. Inspection Dept, to William Tangye, Executive Director Southern Building Code Congress International (May 14, 1985). The Manager of Codes replied that although no official interpretation was on the books, the Code intended to require work to be done in a timely manner and that should Bethel exercise his right to revoke the permit, the parties could solve the problem at the Board of Appeals. Letter from Richard A. Vognild, Manager/Codes to Edward Bethel, Director Bldg. Inspection Dept. (May 20, 1985).
. If the City officials incorrectly applied the building code language in their decision to put conditions on the continuation of the building permit (and we do not decide that question), we stress that not every wronged party has a valid claim for a constitutional violation whenever a local building official makes an incorrect decision regarding a building permit.
See Brady v. Town of Colchester,
. Because we conclude that the Spences had no protectible property interest in the TCO and were never deprived of the building permit, we do not address the Spences’ claim that they have been deprived of a property interest without procedural due process. For the same reasons, we conclude the district court correctly denied the Spences’ motion to amend their complaint to add a claim that the City’s action resulted in a taking of their real property without just compensation.
. We conclude that the other claims raised by appellants are meritless, although we do not discuss them in this opinion,
