130 Mo. App. 401 | Mo. Ct. App. | 1908
Tbe plaintiff was superintendent of the Metropolitan Life Insurance Company and had engaged in service, in places of trust, a number of employees, the one concerned in this case was John W. Clary. He desired to be indemnified against loss through the dishonesty of Clary, if such misfortune should occur. The latter applied in writing to defendant as a surety company for a bond indemnifying plaintiff. A bond was afterwards executed by defendant to plaintiff, dated July 15, 1904. Afterwards, in the latter part of September, Clary embezzled funds of the company in the sum of |494.55, and absconded. This action is founded on that bond and plaintiff recovered judgment in the trial court.
Written application was made for the bond on July 23rd with the request that it be dated back to July loth, that being the time of the last examination of Clary’s account with his employer. Plaintiff signed an employer’s statement by filling out a. blank furnished by defendant. The application and statement were delivered by plaintiff to defendant’s agent at St. Louis on July 25th, and the premium, $3.75, was paid to him for which he gave a written receipt: “For premium on bond, as follows: . . . J. W. Clary from 7-15-04, $500. Premium $3.75.” The application made by Clary and delivered by plaintiff contained the names of persons whom he gave as reference and the trial court found that the evidence showed a valid agreement for a bond if these references responded satisfactorily to defendant’s inquiries. It further found that such responses were favorable and that they were received by defendant about August 3rd and that on August 15th the application was approved by the endorsement thereon: “Approved 8-15-1904. J. W. Anderson.” Though the application was thus approved, the surety
Plaintiff’s office was at Sedalia, while Clary’s headquarters were at Warrensburg, the distance being about forty miles. Plaintiff was notified on September 26th that Clary had absconded and on next day he went to Warrensburg to investigate and examine his accounts. Realizing that he had not yet received the Clary bond, plaintiff, on September 27th, next day after learning of his having absconded, wrote to defendant’s agent at St. Louis asking if the application had been approved and if so when he might expect the bond. He said nothing as to what he had learned about Clary. Several days later, on October 4th, plaintiff wrote to defendant at Philadelphia asking if the application had been approved and what was causing the delay, and if it was for lack of replies from references he could perhaps assist in getting such replies. In this letter plain-tiff also failed to state that he had information that Clary had absconded.
It, was in answer to this last letter that defendant wrote under date of October 6th that it had sent the bond on October 4th and had not sent it sooner because of the impression spoken of above and expressing regret at the delay. Plaintiff received the bond and then, on October 12th, he wrote to both the agent at St. Louis and to defendant at Philadelphia notifying them that Clary had absconded on September 26th, leaving a shortage of $494.55. On the next day, October 13th, the agent at St. Louis acknowledged receipt of the notice and asked plaintiff to send any other information
The defendant contends that it was led to issue the hond through the fraud and deception of plaintiff in the letters asking that the bond be sent to him when he knew of the defalcation and fraudulently suppressed such knowledge. The contention is that no valid contract was made by defendant. A contract of surety-ship against loss by dishonesty of employees is, for all practical purposes, a contract of insurance, and the •contract must be governed and construed as an insurance policy. [Shockman v. U. S. System Co., 92 Wis. 366; Champion Ice Co. v. American Bond Co., 115 Ky. 863, 75 S. W. 197]. An insurance company’s contract, drawn by such company, is to be construed most strongly against the company. [Wertheimer Shoe Co. v. Casualty Co., 172 Mo. 135; American Surety Co. v. Pauly, 170 U. S. 133.] And no reason exists why the •same rule should not apply to a bond surety company giving bond to secure employers against loss by dishonesty of employees. With this preliminary statement of the law, we will ascertain whether there was a valid contract between the parties and when it took effect.
When an application for fire insurance is made and "the terms thereof agreed upon between the company’s authorized agent and the insured, and a policy agreed to be issued embodying such terms, the agreement is -complete; even though credit be extended for the premium. [Baldwin v. Insurance Co., 56 Mo. 151; Worth v. Insurance Co., 64 Mo. App. 583; Palm v. Insurance Co., 20 Oh. 529; Krum v. Insurance Co., 40 Oh. St. 225. If a policy is afterwards issued it relates back to the time specified for the insurance to begin and covers a loss within that time, and from the time of issuance its conditions become effective. [The cases of Horton v. Insurance Co., 151 Mo. 604, and Kilcullen v. Insurance Co., 108 Mo. App. 61, are so unlike this in essen
Plaintiff thus having a complete and valid contract of insurance against loss through Clary’s dishonesty, was not guilty of fraud in not disclosing his knowledge of such loss when he wrote on September 27th and October 4th, inquiring why the bond had not been issued. He doubtless wanted the bond in his possession. He knew that he had come to an agreement about the insurance, that he had paid for it and done all that was incumbent upon him to do. His contract was in every way complete and there is no room for the charge of fraud in his asking for that to which he was entitled. This is made manifest by the suggestion that if plaintiff, in his letters to defendant asking why the bond had not been issued, had stated that Clary had absconded, defendant would still have been obliged, to
But, even if we were wrong as to what has just been written, another consideration in respect to the insistence of fraud disposes of it adversely to defendant in so far as concerns its right to complain. As already stated, the ground for the charge of fraud rests upon the deceit of plaintiff in his letter of October 4th asking why the bond had not been sent and making various statements therein calculated to cause defendant to think nothing was wrong at that time. Yet when plaintiff gave the notice on October 12th, he disclosed in such notice that he had knowledge of the defalcation and absconding of Clary when he wrote the letter of October 4th, in which it is claimed were the fraud and concealment. Defendant was thereby informed of whatever concealment and deception had been practiced and yet chose either to regard it as not a fraud, or else to waive it. If a fraud it was discovered by this notice of October 12, which was the time defendant should have repudiated the bond and offered to return the premium. It will not be permitted to first ignore the
But it is urged that plaintiff failed to comply with the terms of the bond in regard to giving notice of ■defalcation. It was provided that “As soon as any act ■of omission or commission on the part of any employee tending to fix a liability on the part of the company shall come to the knowledge of the employer ... it shall be the duty of the employer to at once notify the company in writing of said act,” etc. On the 12th of October, as we have already stated, plaintiff wrote of the whole matter to the agent at St. Louis and to the defendant at Philadelphia. Was this delay sufficient, under the circumstances of delay in issuing the bond, to avoid the policy? It is certain that defendant ■either thought it was not, or else determined to waive it, as Ave shall proceed to show. In thus showing a waiver, we avoid the necessity of passing on the question argued by counsel whether the want of notice was made an issue by the pleadings, considering the allegations of both the petition and the answer.
The notice which plaintiff sent on the 12th of October to both the agent at St. Louis and defendant at Philadelphia, informed them of the time when he first learned of anything wrong with Clary, viz.: on the night of the 26th of September. It informed them of his going to Warrensburg and investigating the account and the report he made to his company. He gave particulars of information he had received as to Clary’s departure, as well as his photograph, with many ■other suggestions which might be of assistance to defendant. In acknoAvledging the receipt of this notice no suggestion was made or intimation given to plaintiff
Letters were received by plaintiff from the agent through the winter and into April, 1905, in which are •apologies for delay in settlement and an admission that plaintiff had ground to complain. In no one of these is there any suggestion of a want of proper notice. On
For the several reasons herein we are satisfied with the judgment of the trial court, and hence affirm the judgment.