*1 for further Accordingly, we will remand opinion. with this
proceedings consistent SYSTEM, INC., PACKAGE
ROADWAY Quality Express KAYSER
Scott d/b/a Kayser, Appellant.
Scott
No. 99-1907. Appeals,
United States Court
Third Circuit.
Argued Sept. 7, 2001.
Filed June (Argued), Tomar Ballow &
Laurence I. Hills, PA, Tomar, Ap- for Fairless Counsel pellant. (Ar- Botta,
Frank
Ellen P. Milcic
C.
LLP,
gued), Thorp,
Armstrong,
Reed &
PA,
Appellee.
Pittsburgh,
Counsel
*2
BECKER,
private
terms of
Judge,
courts must enforce the
Chief
Before:
AMBRO,
agreements.
Judges.
Circuit
and
NYGAARD
must decide
question
The second
we
OF THE COURT
OPINION
conceptually complex
involves the
issue of
BECKER,
Judge.
Chief
par-
how courts should determine whether
from an order of the
appeal
This is an
de-
ties have contracted out of the FAA’s
vacating an arbitrator’s
Court
District
contains a
fault rules. The LCOA
Package Sys-
Roadway
Plaintiff
award.
clause, stating that it “shall
choice-of-law
(RPS)
tem,
packages for
ships
Inc.
small
in
governed by and construed
accor-
linehaul
“Independent
clients.
corporate
dance with the laws of the Commonwealth
contractors,”
Defendant Scott
such as
Pennsylvania.” Kayser
submits
we
RPS ter-
Kayser,
operations.
assist
its
expressing
should read this clause
alleging
contract
Kayser’s
minated
opt out of the FAA’s default
desire to
obligations
had failed to fulfill his
he
regime
incorporate
and to
arbitration rules
Operating
Linehaul
under the
Contractor
from
law.
dis-
borrowed
We
(LCOA),
governed their
Agreement
which
agree.
Kayser exercised his contrac-
association.
why
explain
first
the choice-of-law
We
and
tual
to demand arbitration
right
little,
any, light
if
on the
clause sheds
damages. RPS then
awarded substantial
parties’ actual
us
intent.
issue before
in the District Court for the
brought suit
contract construction
simply
a matter of
Pennsylvania, asking
Eastern District of
rather than one of choice-of-law. Because
Applying
the award.
the court to vacate
designed
are
to deal
choice-of-law clauses
in the Fed-
the vacatur standards set forth
with a different issue from the one with
(FAA),
Act
the District
eral Arbitration
faced,
currently
which we are
and because
grounds
on
granted
the motion
than
few federal statutes other
scope
exceeded the
that the arbitrator
permit parties to contract out of their re-
authority.
affirm.
his
We will
quirements, we do not read the LCOA’s
requires us to
Kayser’s appeal
decide
evidencing
clause as
a clear
significance
questions
two
of considerable
displace
intent
the FAA’s default re-
arbitration,
governing
for the law
both
gime.
conclusion is consistent with
Our
currently
subject
of circuit-
which are
Lehman Hut-
Mastrobuono
Shearson
splits.
question
The first
is whether con-
ton, Inc.,
115 S.Ct.
parties may opt out of the FAA’s
tracting
(1995),
though
L.Ed.2d 76
Volt Infor-
default
and fashion their
vacatur standards
Sciences, Inc.,
mation
v. Board
Trustees
is a “contract
own. Because the LCOA
University,
Leland
Junior
Stanford
evidencing
involving
a transaction
com-
contracting parties opt intended to out forty-one The pages long and regime. the FAA’s default This rule will: is divided into sixteen sections. This ap- (1) parties ensure who have never peal implicates Sections 9 and Section thought about the issue will not be found 9.3 binds the disputes to arbitrate to have elected out of the FAA’s default and outlines procedures for doing so. (2) Its regime; comparatively simple introductory provides: for sentence apply; arbitrators and district courts to In the event that RPS acts to terminate (3) preserve ability and sophisticat- Agreement this ... [Kayser] and dis- opt agrees ed out. our Applying rule to with such termination ... then (but others) case, disagreement each such this no conclude the District shall be settled in accor- apply Court was correct to the FAA’s va- dance with the Commercial Arbitration catur standards. Rules of the American Arbitration Asso- Analyzing the issue under those stan- .... ciation dards, we hold the District Court 9.3(e) Section states: correctly determined that the arbitrator authority arbitrator shall have the scope authority. exceeded the of his only to conclude whether the termi- Though our cases against exploit- caution [Kayser] nation of was within terms ing an in ambiguity an arbitrator’s award Agreement, of this to deter mine dam- support inference he or she ages if required to do so under this powers, they exceeded his or her also es- subparagraph, provide and to for the that a reviewing pre- tablish court is not expenses division of the of the arbitra- examining cluded from an arbitrator’s parties_If between the the arbi- case, statement of reasons. In this trator concludes that the termination opinion crystal arbitrator’s written makes was not Agree- within the terms of this clear that his decision was based on the ment, then, (2) option at the ... RPS fact that thought procedures he that RPS’s [Kayser] shall nevertheless be terminat- notifying Kayser of its dissatisfaction ed, and ... shall damages be entitled to performance with his were unfair. Yet the equal to the arbitrator’s determination procedures intrinsic fairness of RPS’s [Kayser’s] of what earnings net ... not before the empow- arbitrator —he was during period would have been be- ered to only decide the termi- tween the date of termination to the last nation was within the terms of the LCOA. day of the Agreement, term Accordingly, we conclude that the District (without renewals). any [Kayser] shall award, in vacating was correct damages any have no claim for other will, therefore, affirm its order. amount, and the arbitrator shall have no power punitive any award or other I. damages. A. 9.3(f) Finally, specifies: Section Kayser RPS and entered into the LCOA authority The arbitrator shall have no required Kayser alter, 1996. It to conform to modify any amend or of the terms (in- Managers. only This is up by Local Agreement of this and conditions to the contractor.... estoppel, waiv- verbalized by application cluding ratification), further, er, the arbi- larger equipment at [Kayser] bought any award which may not enter trator took on that the behest of RPS and alters, modifies the terms or amends or responsibility, when his financial but Agreement conditions of this unsatisfactory, he performance was (including by applica- manner form or warnings point until the received verbal ratification). waiver, or estoppel, tion of course, which of is writ- of termination with warehouse aggressive Section 16 contains ten. He is stating get that the LCOA “shall be provision, people several locations *4 in accordance governed by and construed other ... customers. When out serve remiss, employees the laws of the Commonwealth driver were with his own brought once Pennsylvania.” replaced he them RPS attention. He was an problem to his B. very man in a com- aggressive business termination of the Following warnings RPS’s petitive environment. Verbal arbitration, LCOA, Kayser demanded persuade not him of RPS’s serious did Mech- which was conducted before William concerns. $141,961.40in total sought Kayser mann. many years dealing on Based $129,930.00 projected for lost damages: jurisprudence industrial relations $12,031.40 in- expenses for profits plus business, sys- I American find the RPS a tractor-trailer at purchasing curred lacking process [Kay- tem in due toward Mechmann request. Arbitrator RPS’s ser]. $174,431.15 Kayser and awarded ruled for system, which I re- Here the RPS Kayser more than in damages $32,469.75 — spect, thinking long itself into blinds —as originally requested. document our side of the business as we decision consists of Mechmann’s written arrangement, is sufficient. For ir- paragraphs. The first is short twelve per reputable organization business para- appeal. to this The second relevant in the important forms an service econo- arbitra- graph acknowledges “[t]he my, inadequate. that is 9.3(e) authority set forth Section tor’s Paragraph eight gives Mechmann’s conclu- The third characterizes LCOA].” [of sion: question” main before Mech- the “[t]he wrongful I conclude that this was ter- mann RPS’s termination of as whether mination RPS of the LCOA and de- proper.” The “wrongful or LCOA was (after earnings termine the contractor’s sixth, fourth, fifth, paragraphs and seventh expenses all are payment of which bor procedures focus on RPS’s opinion of the contractor) according ne LCOA contractors notifying independent for 9.3(e). 9.3(e) pro- As Section Section perfor- their it is dissatisfied with
when
vides,
damage period here runs from
manner in which
mance and discuss the
05/21/98, the date of RPS’s termination
Kayser’s
procedures played out
those
01/25/99,
of the
the normal
They read as follows:
case.
present
of the
date of termination
dealing with
procedure for
The RPS
(LCOA).
Agreement
com-
by its contractors is
performance
nine,
explanation, sets
Paragraph
without
Documentation
mendable.
[sic]
$174,431.15. Para-
Kayser’s damages at
are written
by the contractors
breaches
ten, eleven,
ruling
are not
view a district court’s
on a
and twelve
motion to
graphs
appeal.
relevant to this
vacate
arbitration award de novo. See
Inc.,
Kaplan
Options
v. First
Chicago
C.
1503, 1509 (3d Cir.1994).
19 F.3d
suit, asking
filed
the District
RPS then
modify the
Court to vacate or
arbitrator’s
II.
granted
District
RPS’s
award.1 The
Court
must first
We
decide whether
(1)
motion,
FAA,
that:
not
holding
properly
District
applied
the FAA’s
the standards
Pennsylvania
supplied
vacatur
standards or whether
it should
judicial
review
arbitrator’s deci-
have,
submits,
Kayser
used
laid
those
(2)
sion; and
the arbitrator had exceeded
out
Arbitra
Uniform
In
authority
light
under the contract.
his
(PUAA).
tion Act
For
conclusion,
reasons we set
of this
the Court did not reach
margin,
forth in the
the answer
to this
proffered
RPS’s other
bases for vacatur.
appeals.
appellate juris-
question
quite important
could be
Kayser
§
disposition
diction under 28 U.S.C.
1291. We re-
ultimate
of this case.2 We have
Indus., Inc.,
Botany
Act
1. The Federal Arbitration
does
create
*5
(3d Cir.1972)
question jurisdiction.
(noting
federal
See Moses H.
that an arbitrator's
Hosp. Mercury
Corp.,
award must meet the test
Cone Mem’l
Constr.
of fundamental ra-
32,
927,
tionality). Correction
460 U.S.
25 n.
103 S.Ct.
74
and modification under
(1983).
§
the FAA are covered
9in U.S.C.
which
L.Ed.2d 765
But because RPS is a
“(a)
empowers
Kayser
courts to act:
Where there
corporation
Delaware
is a
and
citizen
(and
fig-
was an evident material
miscalculation
Jersey
of New
because the amount in
ures or an evident material mistake in the
case),
controversy requirement met in
is
this
any
description
person, thing,
property
or
diversity jurisdiction
the District Court had
award!;
(b)
referred to in the
Where
or]
§
under U.S.C.
28
upon
arbitrators have awarded
a matter not
”
submitted to them....
2. The FAA
where a
lists four circumstances
may grant vacatur
three under
court
and
governed
law is
arbitration
modify
may
which it
correct or
an award.
PUAA,
by the
which sets forth two discrete
10(a).
by
governed
§
Vacatur
It
9 U.S.C.
regimes.
"statutory
The first is known as
ar-
provides
may
a
vacate
award
court
an
if:
bitration,”
which the standards for va-
under
fraud,
(1)
by
procured
corruption,
it "was
or
catur, modification,
parallel
and correction
means,”
10(a)(1); (2)
§id.
undue
the arbitra
Compare
perfectly
almost
the FAA.
those of
],"
"partial!
corrupt!
id.
tor was
or
7314(a)
1
(governing
§
42 Pa. Con. Stat.
vaca-
10(a)(2); (3)
§
unjustifiably
the arbitrator
re
tur),
7315(a) (covering
§
and id.
modification
hearing,
postpone
fused to
refused to con
10(a) (vaca-
correction),
§
with 9 U.S.C.
pertinent
sider
and material to the
"evidence
tur)
(modification
§
and id.
and correc-
controversy,”
any
engaged
or
other "mis
tion).
regime
second
is known as "com-
The
rights
par
prejudiced
behavior” that
of a
power
Judicial
to set
mon
arbitration.”
10(a)(3);
(4)
ty,
§
id.
or
the arbitrator "ex
aside common law arbitration awards is
powers,
imperfectly
or
ceeded[his
her]
or
so
sharply
circumscribed. See
Pa. Con. Stat.
mutual, final,
executed them that a
and defi
"may
(stating
§
not
that such awards
upon
subject
nite award
matter submitted
clearly
vacated
unless it is
or modified
made,”id.
courts,
10(a)(4).
§
was not
Some
hearing
parly
a
or
shown that
was denied
one,
including
recognized
fraud, misconduct,
addi
also
corruption
or other
tional, nonstatutoiy
upon
bases
which a re
irregularity
unjust,
caused the rendition of an
viewing
may
award”).
court
vacate an arbitrator’s
inequitable or unconscionable
The
generally
award under the FAA. See
Tanoma
provides that
to arbitrate
PUAA
Mining
conclusively presumed”
Co. v. Local Union No.
"shall be
to be
(3d Cir.1990) (recognizing
agree-
that an
common law arbitration “unless
may
writing
displays
expressly
award
be set aside if it
"mani
to arbitrate
ment
Indus.,
law”);
disregard
provides
statutory
pursuant
fest
for the
Inc.
for”
arbitration
Swift
Hutton, Inc., 514 U.S.
this case is Shearson Lehman
determining
no trouble
Subject
52, 57,
a few
L.Ed.2d 76
FAA.
by the
governed
here,
(1995). Thus,
the statute
implicated
if
contract
arbi
exceptions
any
“written
applies
pro
rules or
pursuant
trate
to arbitration
in
evidencing a transaction
... contract
law, the fed
from state
cedures borrowed
arbitration
commerce
settle
volving
long
so
as their
policy
eral
satisfied
out of such contract
controversy arising
Sci.,
enforced. See Volt
agreement is
Info.
language
§ 2. This
transaction.” 9 U.S.C.
Inc., Board
Trustees
Leland Stan
r each to the limits
the Act’s
“extend[s]
468, 478,
University, 489 U.S.
Junior
ford
power[.]”
Clause
Congress’
Commerce
(1989).
1248,
intent, contracting parties have an incen- tive to include choice-of-law clauses in III. agreements. their Commercial parties of- We first consider whether RPS and also bargain ten clauses, for arbitration Kayser manifested a clear intent hoping to benefit from pur- arbitration’s judicial review of the ported arbitrator’s award advantages over litigation. As a result, would be pursuant conducted many to standards commercial contracts include borrowed from Pennsylvania Though law. both arbitration clauses. our ultimate is to goal effectuate their required When to determine the legal intent, we little evidence with which standards governing particular contro- to work. Section 9.3 of the LCOA binds versy, courts typically confront two choice- them to any disputes “by resolve arbitra questions. of-law The first is the horizon- accordance with the Commercial question: tal whether the laws X of State Arbitration Rules of the American Arbitra or State Y supply the relevant rule of tion Association.” Section 16 directs that (and, decision. Choice-of-law doctrines governed “shall and con clauses) consequently, choice-of-law speak strued accordance with the laws of the this issue. The second choice-of-law *7 of Pennsylvania.” Commonwealth The question that courts face is vertical the says LCOA itself nothing about the issue one: whether rule of sup- the decision is us, before and there is no extrinsic evi plied by the laws of State X or federal by dence that Kayser gave RPS the mat law. Judge-made choice-of-law doctrines ter All consideration. (and, we have to accordingly, attempts by contracting us, guide therefore, anis arbitration clause parties to influence application their and a clauses) choice-of-lawclause. choice-of-law have no applicability See, e.g., 3. Corp. Kyocera Tech. 247, Corp., LaPine v. Corp., F.Supp. Prods. 248-49 884, (9th Cir.1997); 130 F.3d Syncor Int'l (E.D.Wis.1994); Flight Sys. v. A. Paul Lau 96-2261, McLeland, Corp. v. No. 1997 WL Co., (D.D.C. 715 F.Supp. rence 1127-28 (4th Cir., 1997) at *6-*7 Aug.11, (per 1989). Management But see UHC Co. v. Com curiam) (unpublished opinion); Gateway (8th puter Corp., Sciences Tech., Inc. 64 F.3d Corp., MCI Telecomm. 1998) ("It Cir. is not clear ... (5th 1995); 996-97 Cir. M&L Power any say have in how a federal court will Servs., Int'l, Inc. v. American Networks Congress review an arbitration award when F.Supp.2d (D.R.I.1999); Eng New specific, self-limiting proce has ordained a F.Supp.2d Hydro-Quebec, land Util. v. occur."). dure for how review such is to (D.Mass.1998); Mfg. Sys. Super Flexible two broker a securities pute between rel- because the question answering this
to agreed parties had The its customers. by the Constitution supplied rule is evant by any disputes any to resolve preempts law federal a valid itself: agree their to have a desire indicated the same had regulate to purporting law state of the State by the laws “governed ment VI. Art. Const. U.S. See issue. ar permits Though the York.” New however, one is not us, issue before The damages, the punitive award to bitrators is sim- preemption of choice-of-law —it Supreme Court the before question No construction. contract matter of ply a incor to intended parties had the whether gov- this matter were contests that one York a New into their porate rule relevant law, then the erned awarding from arbitrators that barred rule the Com- laws of by supplied be would them. But, we as Pennsylvania. monwealth governed examining is not this case began explained, Court The by federal Id. at governed “in isolation.” law—it clause by state choice-of-law decide must only reason It noted law. stan- merely or state federal apply “reasonably to as be read
whether could clause analy is because case in this dards for conflict-of-laws a substitute by contract “specify to what determine permits would that otherwise sis will be ... arbitration under which out of arising rules disputes apply to to 479, 109 Volt, 489 id., i.e., whether relationship,” conducted.” contractual in this case issue 1248. The or those of York the laws New apply to choice-of-law LCOA’s was the reading If this state. another specifying as observed, be read should then clause one, the Court correct deci- arbitrator’s any judicial review in the contract nothing would “there according to conducted should be sion constitute evidence possibly could arbi- forth set damages standards punitive to exclude intent an in the set out of those law instead tration also stated Id. The Court claims.” FAA. intend clause was the choice-of-law even if for ordi a substitute than “more to be ed the choice-of-law construe decline still analysis” conflict-of-laws nary a clear evidencing case in this clause punitive award preclude “might stan- Pennsylvania’s incorporate intent allows its York New damages because into the LCOA. judicial review dards arbitrators, enter courts, though not its above, claus- explained As we this, the Because of Id. awards.” such speak intended generally es are might that “the reasoned one with from wholly distinct issue rights substantive New York’s include Moreover, currently faced. arewe which *8 alloca and, not State’s obligations other (if statutes any) federal few because tribu alternative between power opt permit even the FAA than 60, 115 1212. S.Ct. Id. at nals.” them, contained standards out of the issue particular are confident interpre- resolving which Though never ex contracting parties rarely occurs was the clause choice-of-law tation ante. that it held one, squarely Court best opt an intent clearly evidence not did conclusion for our support
findWe
arbitra-
rule that
default
of the federal
Hut
out
Lehman
v. Shearson
Mastrobuono
re-
damages
punitive
may
1212,
award
131 tors
52,
Inc.,
S.Ct.
ton,
115
York
from New
one borrowed
it with
place
a dis
(1995),
involved
which
76
L.Ed.2d
295
they
law that
may not award them. See
terms.
474-76,
See id. at
Our conclusion that RPS and Kayser
rights are at stake.
supposition
This
have expressed
clear
no
intent as to
supported by Mastrobuono, where the
the District Court should have
Court was reviewing a
applied
federal court’s con
federal or state vacatur standards
struction of a
is not
choice-of-law clause.
undermined
Re
Volt Information
sponding
Sciences,
to Justice
dissent,
Inc. v. Board
Thomas’s
Trustees
Le
which
land
relied heavily
Volt,
Junior
on
University,
489
Stanford
U.S.
clarified that in
103
that case
L.Ed.2d
it had
488
not con
(1989).
case,
In that
strued the
underlying con
contract de novo. See Mastro
tract
buono,
included both an
clause
at 60 n.
parties had intended to incorporate Cali
Our understanding of Volt is bolstered
fornia’s arbitration rules into
agree
their
by case law from our sister circuits. Six
ment,
471-73,
see id. at
296 consis is guidepost This to do so. Cir.1998).4 intend there- (9th Volt
1205, 1212-13
admonition
Court’s
Supreme
with
tent
our
undercuts
that
nothing
contains
fore
“in the
control
standards
the FAA
that
expressed
Kayser
RPS and
that
conclusion
con
intent
contractual
absence
incorporate
to
intent
no clear
59, 115
Mastrobuono,
at
trary.”
into their
review
judicial
standards
with
It is also consonant
S.Ct.
agreement.
d’etre,
tois
overcome
which
raison
FAA’s
legisla
(whether
by state
created
rules
IV.
courts)
it more
make
or
tures
of a
presence
Because the
agreements.
enforce arbitration
to
difficult
(if any-
little
us
clause tells
choice-of-law
478,
1248
109
Volt,
S.Ct.
U.S.
489
See
contracting parties
about
thing)
‘to overrule
(“The
designed
FAA was
default
the FAA’s
opt
to
out
intended
to enforce
refusal
long-standing
judiciary’s
ones borrowed
incorporate
and
standards
”)
Dean
(quoting
to arbitrate.’
agreements
a
to establish
we need
from
Byrd,
v.
470
Inc.
Reynolds,
Witter
adopt is that
rule,
the one we
default
158
219-20, 105
84 L.Ed.2d
standing
clause,
states
(1985)).
acknowledge that some
We
finding
support
to
alone,
insufficient
to
protection
much or more
as
provide
opt
to
intended
contracting
than does
agreements
eW
standards.
default
FAA’s
out
§ 7302 et
see,
42 Pa.
Stat.
FAA,
e.g.,
Con.
in-
three considerations
lay out
first
see,
Garrity v.
not,
e.g.,
do
seq, but others
rule
why the
articulate
analysis,
our
form
354, 386
Inc.,
Stuart,
40 N.Y.2d
Lyle
them,
consistent
today is
announce
we
(1976)
793
353 N.E.2d
N.Y.S.2d
case
in line with
rule is
why our
show
precluding
law as
York
(construing New
and six
Supreme Court
from both
dam
awarding punitive
from
arbitrators
to
respond
then
circuits. We
our sister
en
is to
goal
FAA’s ultimate
ages).
proposed
approach
alternative
any de
bargains, but
actual
parties’
force
by applying
conclude
Ambro. We
Judge
inaccurate
to be
doomed
rule
fault
case.
rule to this
our
therefore,
must,
decide
cases.
some
concluding
wrongly
is worse:
error
which
A.
out, wrong
opt
parties intended
light of
not. In
they did
concluding
ly
guide us
considerations
Three
history,
believe
FAA’s
we
First,
aimwe
rule.
formulating a default
latter.
than the
former worse
par
with which
frequency
minimize the
regime
Second,
to create
strive
we
out of
opted
found
ties will be
easy for arbitrators
it will
which
not under
they did
regime when
FAA’s default
Cucchiella,
cur.,
Mass.App.Ct.
32
Inc. v.
are decisions
acknowledge that there
4. We
decisions,
(1992). Other
870
little
to be of
594 N.E.2d
them
contrary, but
find
Mastrobuono, never so
before
though
were decided
after
Many
decided
cases
value.
meaning of Volt.
on
tend
focus
clarified the
the decision
Mastrobuono
much
cite
Hutton, Inc.,
v. Shearson Lehman
Barbier
construction.
See
than contract
preemption rather
Cir.1991);
Sys.
Mfg.
(2d
Co.,
Flexible
117
Inc.
Painting & Constr.
ASWAllstate
See
Cir.1999);
247
Ltd.,
F.Supp.
Corp., 874
Super
(5th
Prod.
v.
Co.,
307
F.3d
Lexington Ins.
Sys.
A. Lau
(E.D.Wis.1994);
v. Paul
Flight
Inc.,
Health,
F.3d
v. Value
trom
Eks
1391
(D.D.C.1989);
Co.,
F.Supp. 1125
rence
Servs., Inc.
(D.C.Cir.1995); & L Power
M
Co.,
Inc.
&
Barney,
Upham
Harris
Smith
Int’l,
F.Supp.2d
Network
v. American
Luckie,
N.Y.S.2d
85 N.Y.2d
(D.R.I.1999).
(1995);
Se
McKinnon
Thomson
N.E.2d
*10
and district courts to
provide
deter mine whether
“any
that
controversy shall be set
parties
opted
have
out of federal stan-
by
tled
arbitration in accordance with the
Finally,
dards.
we seek to
a
create
rule
terms of the Pennsylvania Uniform Arbi
sophisticated parties may
that
bargain
tration Act.”
Ford v. NYLCare Health
Cf.
significantly
around without
increasing
Coast, Inc.,
Plans
of Gulf
(5th
their transaction costs.
Cir.1998)
that
(noting
parties’
contract provided
“[a]ny
that
controversy
In light of
guideposts,
these
we believe
... shall
by
be settled
accor
that
best rule is that a generic choice-
dance with the Texas General Arbitration
clause,
alone,
of-law
standing
no in-
raises
Act”).5 We note also
that
other rule
ference that
parties
contracting
intended
impose
would
transaction costs as
well
opt
out regime.
FAA’s default
impelling parties not wishing
opt
out to
rule will
parties
This
ensure that
who have
include a
saying that
their
never thought
particular
about this
issue—
choice-of-law clause should not be read to
that,
a characterization
suspect,
would
raise such an inference.
apply
parties
in this case—will not
be found to
opted
out.
It will also
Our rule is also consistent with the case
make life easier for
First,
both arbitrators and law.
it honors Mastrobuono’s di-
judges
analysis
because the
will be com-
rective that FAA
apply
standards
“in the
plete once they
agree-
conclude
absence
contractual intent to the con-
ment
nothing
contains
more than a
trary.”
Lastly, the rule we pre- announce will with a premised discussion that is on the serve and ability facilitate the of parties to assumption that presence of a choice- contract around the default federal stan- of-law clause can render contract ambig- Sophisticated (i.e., dards. parties those uous to whether the parties intended to employ experienced lawyers who to draft incorporate state arbitration rules into contracts) their will soon learn ge- that a agreement. 63-65, their See id.
neric choice-of-law enough. Court, clause however, S.Ct. 1212. The was care- Assuming that both genuinely wish ful to make clear that it rendering no governed by holding standards other than as to the meaning of the clause FAA’s, requiring something See, more will e.g., itself. id. at (“At impose minuscule most, costs. It is the choice-of-law clause transaction intro- difficult, not particularly example, ambiguity duces an into an arbitration We do suggest parties may not mean to might inference. The case well be different if not be found opted to have out unless their language other contractual or other evidence contract includes a statement such as this suggested intended to be one. We hold that a choice-of- bound standards borrowed from state law. clause, alone, standing raises no such *11 298 is based First, proposal Judge Ambro’s pu- allow otherwise that would a must that we find premise the false on add- (emphasis damages awards.”
nitive Mastrobuo Volt and “reconcile[ ]” way to with ed)).6 holding is in accord Third, our at supra explained, But as we Id. no. that circuits sister of our by six decisions already III, has Supreme Court the Part generic choice-of- a construe declined the two relationship between the clarified that an inference raising as law clause its rule Volt, the Court followed In cases. incorporate intended contracting parties interpretations court deferring their into standards arbitration state law as no federal long so contracts private agreement.7 no had The Court at stake. rights are because in Mastrobuono obligation such one) (like originated B. fed this that case Mastrobuono, at court. eral See ap- a different proposes Ambro Judge Volt, 1212; also 489 4, see 60 n. containing that contracts arguing proach, 474-76, Judge 1248. at and arbitra- clauses by Mas- unconvinced apparently Ambro incor- be construed should tion clauses Volt, distinguishing method trobuono’s that are rules all state porating 2, & n. but Op. at 303 Ambro see and “substantive” in nature “procedural” persuasive or not find Mastrobuono we “con- that do not rules state arbitration province It is not of no moment. Op. at FAA. See Ambro flict” with on an a based to craft rule unconvinced, believing are Court was Supreme 304-05. We that assumption that coun- above have meant outlined it could not wrong that the reasons or that earlier, numer today. noted announce it said. As we of the rule we what sel favor interrelation examined the with cases problems three ous Additionally, we have and Mastrobuono. See ship between Volt proposal. Judge Ambro’s proferen- ambiguous, contra legally is not in- Mastrobuono’s this reason 6. It is for justify inapplicable. its proferentem to tem is contra vocation of we rule is not decision inconsistent party that 589, drafted here. Elahi, announce PaineWebber, 87 F.3d Inc. v. See 7. case contended at issue contract Cir.1996); 592, (1st Union Fire National 594 preclud- York rule that incorporated a New 129, Corp., 88 F.3d Belco Petroleum Ins. Co. v. awarding punitive dam- from ed arbitrators Cir.1996); Hayden Co. (2d Porter 134-35 opinion the Court its ages. the end of Near Co., Indemnity 136 F.3d Century v. come could not "over the drafter stated that Indus., Cir.1998); (4th Corp. v. Garrison Ferro interpreta- of contract rule the common-law 927-28, (6th Inc., Cir. 142 F.3d ambiguous construe a court should tion that Co., 1998); Comput Management Inc. v. UHC party against the language interest (8th Corp., 148 F.3d er Sciences But as Id. at drafted it.” Foodmaker, Inc., Cir.1998); Wolsey, Ltd. v. text, the Mastrobuono explained Cir.1998). (9th 1205, 1209, 1212-13 144 F.3d deciding that Court assumed without Co., Painting & Constr. ASW Allstate But see Consequently, ambiguous. agreement was Co., F.3d Lexington Ins. Inc. that, arguing Judge Ambro incorrect otherwise); curiam) 1999) (concluding (5th (per Cir. Mastrobuono, generic choice-of-law "a under Inc., Health, Value trom Eks any in the specific electing provision (same). (D.C.Cir.1995) 1391, 1394-96 Op. ambiguous.” Ambro agreement, is same a Elcstrom for unpersuaded ASW and are holding added). Under our (emphasis gives opinion rea neither simple reason: is insuf- clause today, generic choice-of-law a concluding choice-of- sons for law to show as matter ficient evidencing an be read as law clause should displace contracting parties intended regime. default result, of the FAA’s opt intent out contract rules. As FAA's default *12 pp. n. supra 295-96 & 5. We have not determine whether a given rule sup- was located, cited, Judge nor has Ambro a plied by the FAA or was instead borrowed single case that “reconciled” the Court’s from state law would first need to classify opinions on proposed by two the basis the relevant being rule as either “substan- Judge Ambro. “procedural” tive” or for purposes of the It possible FAA.8 that arbitrators and
The second reason for our disagreement courts simply would the import distinctions Judge with proposal Ambro’s is that we that have been believe that drawn the diversity would not con- effectively ad- pursuant purpose vance its stated text to effectuating Erie Railroad Co. v. the intent of most contracting parties. Tompkins,
Judge Ambro concludes his (1938), concurrence L.Ed. 1188 jurisprudence but the by arguing that practice “custom and that area is always not a model of clarity, among contract drafters” counsel favor and, events, at all we do not understand construing contracts such as this one as why distinctions drawn in a totally differ- incorporating arbitration standards bor- ent context necessarily would transfer well Op. rowed from state law. Ambro at 308. the FAA. But that would not happen even under problematic Judge nature of Am- Judge approach; rather, Ambro’s Judge proposal bro’s only would increase in any approach Ambro’s would have courts con- case where the party seeking vacatur com- strue contracts like this as incorporat- one plained issues, about multiple ing all at least one arbitration rules that are “procedural” nature, “procedural” of which was and at only but least one those (however “substantive” of which rules do not “conflict” “substantive” those defined). with the FAA. Though people case, reasonable are terms In a such a quarrel may over most whether to reviewing court could required apply be contracts such as the one before us would (i.e., some rules borrowed from state law wish to be by bound the FAA’s default “procedural” rules and the relevant state’s standards or would instead choose to be “substantive” rules that do not conflict bound standards borrowed from state FAA) with some rules taken from law, we think it unlikely most (i.e., “substantive” rules where number sizeable would wish to rule from the relevant state is “con- be bound some federal standards and FAA). flict” with the involving Issues va- some state ones. catur are difficult enough without the addi- tional Lastly, challenge balancing applying we believe Judge Ambro’s proposal unduly multiple legal regimes would complicate within the the law same in this area. Under Judge ap- reasons, Ambro’s case. For all of these we decline proach, seeking arbitrators and courts adopt Judge proposal. Ambro’s Although Judge Pennsylva- Ambro, Ambro regime cites two proposed by Judge under the proposition nia cases for the categorization given standards of of a rule as “substan- procedural, review are we think "procedural” tive” large part or would in question would have to be a of federal law. determine preempted by whether it was Judge view, Ambro's view is that a choice- FAA. In our scope because of the incorporates of-law clause all of the preemptive chosen effect aof federal statute is itself a state's except portions arbitration law question those question of federal incorporation whose given be "procedur- would inconsistent a rule was "substantive" law, i.e., federal substantive purposes rules that al” for of the would likewise consequence, “conflict” with the FAA. question As of federal law. court Op.). The Arb. (quoting Op. at
C. “[t]he stressed of this rule to facts our Applying authority to limits the arbitrator’s clearly answer. The simple yields an case termination only whether decide clause contains Agreement, the terms within of an evidence no extrinsic there is proce- of the extrinsic fairness examine FAA’s default out of to contract intent *13 of notifies contractors RPS by which dures the hold that Dis- therefore regime. “[b]y that It concluded Id. problems.” concluding that correct Court was trict such consider- his decision on grounding govern review of FAA standards the altering the thereby of fairness ations case. pre-termi- require to certain Agreement over- the arbitrator procedures, nation V. authority grant- the of the bounds stepped standards, we FAA the Applying at 14- Agreement.” Id. him the ed to that the Court the District agree adopts the essentially RPS appeal, 15. On his scope of au the exceeded arbitrator analysis. Court’s District the under judicial review Though thority. in re arguments three advances Kayser circumscribed,” Local “narrowly that *14 mance. See supra page 290. The conclu- Workers, Bhd. Int’l Elec. 886 F.2d sion that arbitrator Mechmann derived (3d Cir.1989) (concluding particular that a from this Kayser’s discussion was not that dispute was not arbitrable and remarking termination contrary had been to the “[n]othing that in the arbitrator’s two rul- (the question actually him), before ings contrary” convinces us because but rather that system “the RPS [was] opinions the that the revealed arbitrator lacking in due process [Kayser].” toward based had his decision “on general the Kayser would have us believe that the desirability of arbitration” than the rather arbitrator devoted four paragraphs language of agreement). the dicta,” “mere but not one sentence ex- hand, On the other also cau- plaining have supposed his “holding” that the against tioned exploiting ambiguity” “an in termination violated the terms of the an arbitrator’s support decision to “an in- agreement. reading That simply not ference” that he or she his or her supported by exceeded the opinion, arbitrator’s authority. Corp. NF&M demonstrates, United Steel- which beyond peradventure, Am., (3d workers that Mechmann ruled on an issue that was Cir.1975). The reason for policy properly this is not him. before require opinions “[t]o ambigui- free of Moreover, RPS, by as noted the arbitra- ty [could] lead by arbitrators to it safe play tor never framed or decided in the issue writing no supporting opinions. This by the terms stated the LCOA: “[W]heth- undesirable, would be for a well-reasoned er the [Kayser] termination was within opinion engender tends to confidence Instead, the terms of Agreement.” this integrity process aids Mechmann stated ques- “[t]he main clarifying the underlying agreement.” tion” was whether “the termination” was United Steelworkers Am. v. Enterprise “wrongful proper.” And Mechmann’s Corp., & Car Wheel was “that this wrongful “conelu[sion]” (1960). L.Ed.2d 1424 LCOA,” termination RPS of the not We distill the following principles from that the termination violated “the terms (1) precedents: our a reviewing court Though of’ LCOA. these latter two presume should that an references, arbitrator acted alone, standing would not suf- scope within the of his or her authority; fice show that the arbitrator exceeded (2) presumption this may not be rebutted authority, they his lend support further ambiguity a written opinion; but our conclusion that he so. did We hold (3) a may court conclude that an arbitrator District Court was correct to va- But I contract construction.1 matter of award, and will there- the arbitrator’s
cate conclusion my colleagues’ disagree with its order.9 fore affirm construction, that, a matter of contract Concurring: AMBRO, Judge, Circuit law to Pennsylvania parties’ choice Operating Linehaul Contractor govern by my reached outcome in the I concur “LCOA”) (the requires that Agreement arbitrator in agree I colleagues. FAA, pro- making authority exceeded his this case to be judicial review vide standard Kayser against Mr. in favor of the award provi- to that contract’s arbitration applied (“RPS”). Inc. Roadway Package System, (which govern- mention of makes no sion result, I that the agree arriving at In law). determining In ing (the “FAA”), Act Arbitration Federal a “clear contain that the LCOA requires by pri- seq., permits § 1 et U.S.C. govern Pennsylvania law intent” have around the to contract vate by default or else provision, its arbitrators’ by which standards FAA’s believe, I colleagues, applies, my agree I also are vacated. awards Supreme Court’s decision misapply our out of contracted Hut- Lehman Shearson a Mastrobuono v. standard is of awards vacatur the FAA’s According to Section profits.” ior his "lost Court's vaca- District affirmance of the 9. Our *15 LCOA, 9.3(e) Kayser to was controversy of the entitled as gives to rise to tur order earnings during ... damages for his "net Kayser may rearbitration. The whether seek "[wjhere to date of termination period award is va- between the an the provides that Agreement.” agree- day term of this the of the which the last the time within cated and text, originally sought Kayser not to be made has required the award noted in the As ment discretion, $141,961.40 ($129,930.00 profits may, di- lost and in its expired, the court $12,031.40 9 rehearing by arbitrators.” U.S.C. the be- purchasing the a truck at rect a for 10(a). previous RPS), discussion indi- § As our him but the arbitrator awarded hest of cates, opinion is unclear as to $174,431.15. the arbitrator's truck satisfied that We are the issue that was before ruled on the scope whether he of plainly the purchase was outside Kayser's of RPS’s whether termination him: damages support no and can find allowable terms of LCOA. Un- within the contract was of arbitrator's award record for the the circumstances, rehearing would der these $32,469.75 originally Kayser re- than more query whether "the appropriate. But seem said, panel expresses being the quested. That agreement required the which the within time of an award opinion as to whether no Though expired.” ... award to be made has $129,930.00 justified this case. by particular date no itself sets LCOA the entered, parties the be an award must which colleagues My use "contract construction” in accordance the agreed "arbitration to interpretation,” and I instead of "contract the Rules of Ameri- Arbitration Commercial deliberately. con they presume so Under do [(AAAor Associa- Association can Arbitration construes effect a court the tract construction tion)].” question § seems to 9.3. The Con agreement applicable law. under of an therefore, be, impose AAArules by attempt a court interpretation is the tract limit, may well be time outer parties the to an intent of to ascertain the by the Association. resolved better matter they express by use agreement words to the issues, which are not decide these difficult do of agreement. former is matter The us, for further them before but leave not law, F. Har one of fact. See John the latter may occur. proceedings Co., Waldinger Corp., F.2d 796 Inc. v. kins 657, (3d Cir.1986); Ram Co. Const. 659-60 matter, this If a rearbitration occurs 1049, Co., 1052-53 F.2d Am. States Ins. 749 guidance all members note Cir.1984); (3d Patter generally Edwin W. events, see that, at all agreement are in panel son, and Construction Interpretation been reduced have arbitrator's award should 833, (1964); Contracts, $129,930.00 Colum. L.Rev. amount no more than to —the 534, (1960). § at 9 3 Corbin on Contracts compensate him Kayser originally sought ton, Inc., 514 U.S. generic2 S.Ct. choice of “the law of place (1995), L.Ed.2d 76 disregard custom Project (in where the case, is located” California). practice among agree- drafters of Ruling that “where par ments. agreed ties have their arbitration
agreement
governed
will
the law of
A. The FAA
California,”
court,
a California
pursuant to
its
stay
could
The issue of
preemption
the FAA’s
arbitration pending the results of related
subject
state arbitration law is a
of consid
litigation involving third parties, something
See,
52, 56,
e.g.,
erable debate.
id. at
contemplate
does not
and thus
1212;
Scis.,
S.Ct.
Volt
Inc. v. Bd.
Info.
permit
would not
if it governed. Volt, 489
Univ.,
Trustees Leland
Junior
Stanford
U.S. at
“Where,
pro-arbitration policy
operate
does
bitration under the[FAA] is a matter of
regard
without
intent
consent, not coercion.” Id. Understood
to an
to arbitrate.
may
Parties
way,
where
have a
choose that their
governed
arbitration be
governing their
by rules other than
supplied by
those
contract, they must affirmatively choose to
FAA, Volt,
489 U.S. at
*16
agreement
have their
gov
arbitrate
FAA “simply
and the
requires courts to
by
erned
only
the FAA.
exception
The
privately
enforce
negotiated agree
[those]
if
would be
the state
chosen
rule
“would
...
ments
accordance with their terms.”
goals
undermine the
policies
and
of the
478, 109
Id. at
S.Ct. 1248.
478, 109
FAA.” Id. at
1248.
S.Ct.
Supreme
B.
Jurisprudence—
Court
Mastrobuono,
only
years
decided
six
af-
Volt and Mastrobuono
Volt, held,
ter
in the
of a form
context
Supreme
Our
Court has twice within the
contract containing
generic
a
New York
years
twelve
last
dealt with the deceptively
provision
separate
and a
ar-
difficult
(which
issue of whether the FAA impli-
provision,
bitration
the FAA
edly governs an agreement
permitted
to arbitrate
punitive damages
awards
ar-
bitrators)
within a
specifically
contract
(which
chosen
the
preempted
York
New
law
not).
governed by
to be
state law.
Supreme
See did
Court determined
Mastrobuono,
52,
514
at
U.S.
115 S.Ct.
that New York
govern
law would
substan-
Volt,
1212;
ing the 56, 115 S.Ct. FAA. at of the Id. policies 1212. trobuono, at 115 S.Ct. U.S. (“New against ar prohibition York’s or to reverse purport did not Mastrobuono ... is a punitive damages awards of Instead, distin bitral the Court even limit Volt. hostility to judicial ‘ancient’ vestige in a footnote: Volt guished arbitration.”). principle is The second California ... deferred In Volt that, a in its contract by placing state’s of its own construction court’s law_ and an arbitration choice of law case, by con- present In the law, Shearson specific without choice court’s inter- trast, a federal we review contract, ambiguous “drafted an Lehman contract, inter- our and pretation of the benefit of ... cannot now claim accords pretation 1212. at 115 S.Ct. Id. the doubt.” to def- arguably entitled decision-maker read to “a be Finally, document should arbitrator.3 erence—the and to ren provisions to all its give effect 4, 115 1212. n. S.Ct. Id. at 60 Id. with each other.” der them consistent in Mas decision Court’s Underlying discussed below principles these is Each of the con that “the wishes is trobuono of this case. context at prevail, id. tracting parties” and Mas- between Volt The difference 468, 109 Volt, at (citing 489 U.S. S.Ct. there, trobuono, difficult “while 1248), contra even if those wishes Co., Republic Ins. Lanier v. Old grasp.” unequivocal exclu by “an the FAA vene (M.D.Ala.1996). But F.Supp. at claims.” Id. punitive damages sion of believe, can, reconciled. I cases those these ascertaining In 1212. they require that sub- together, to Taken wishes, instructs a court Mastrobuono (such as rule stantive state arbitration of con principles three take into account award- barring York’s of arbitrators The New interpretation. construction tract by the superseded (which Volt, ing damages) punitive at in line with first 1248) there is a between FAA where conflict application is that rule, though even that and the state mine FAA not under the law would chosen 'encourage re- would pointed out To hold otherwise Ironically, Supreme Court Furthermore, shopping.... forum the case ward that it would decide in Mastrobuono interpreta- court’s premise that a defer Court's either a de "the same novo under Mastrobuono, is entitled to a choice of law clause *17 ential standard.” Moreover, interpreta- court's 1, while federal Mastrobuo deference 55 n. 115 S.Ct. insupport- subject review is to de novo distinguish received is Volt effort to has no's omitted); Diamond, able.”) (citations also Heather J. see strong See Thomas criticism. A. Note, Haase, Rights to Preemptive In Parties’ Clauses and Their Law Choice Defense of the Federal Arbi- Arbitral Awards Under Act: Recon Limit the Federal Arbitration on Effect Lehman v. Shearson Itself, tration Act: Mastrobuono 39 Ariz. Supreme Court with ciling the 309, Hutton, Inc., 331- 35, (1997) (“This Wake Forest L.Rev. suggest 31 would 56-58 L.Rev. (1996) ("Although to follow purporting only 32 applicable when is Mastrobuono Volt, ignored its own Supreme Court has meaning is clause’s intended choice of law rights 'contractual in Volt to enforce State would mandate in court. courts resolved federal parties,’ has in- expectations of the while fed ignore remain free to Mastrobuono meaning of the federal distorted the obligated it. stead to honor courts would be eral to the conclusion policy in order reach Southland Supreme Court held When the in 852, in arbi- damages be allowed punitive should 79 Keating 104 Corp. [465 U.S. (citations omitted); tration.”) Joshua M. Bar- (1984)] provisions of the that the L.Ed.2d 1 Note, rett, Policy Arbitration Federal as well must be honored courts FAA After Hutton, Lehman courts, v. Shearson uniformi Mastrobuono Inc., it did so to assure as federal (1996). 534 32 Willamette L.Rev. forum. irrespective of the ty of law selected (the “PUAA”)4 if ex- Act governs can be overcome dealt with tration conflict hand, parties’ in the contract. On the other arbitration. plicitly easily This issue is procedural FAA state arbi- only defers resolved favor of the PUAA if Volt (such rule tration rules as California But applies. Mastrobuono creates pending an arbitration resolution delaying I complexity. Consequently, analyze our in litigation), of another matter even when my issue reading princi- based on of the Mastrobuono, the FAA is in conflict. See ples of Volt and Mastrobuono. (“We 63-64, at 1. Application Principles of the way think that the best to harmonize the of Volt and Mastrobuono with the arbitration read ‘the laws of the State provision is to a. Law Chosen to Govern LCOA provi- of New York’ the choice-of-law [in (Pennsylvania) Does Not encompass principles substantive sion] Undermine apply, that New York courts would but In applying Volt and Mastrobuono to special limiting to include rules the author- case, question our the initial is whether the arbitrators.”); Volt, at ity of application Pennsylvania law to the arbi- (“Where, here, par- tration section of the LCOA undermines agreed ties have abide state rules view, my FAA. requires, pre- This arbitration, enforcing those rules accord- liminary vacating consideration of whether ing fully to the terms of the an arbitrator’s award because the arbitra- FAA, goals consistent with the even authority procedural tor exceeded his stayed if the result is that arbitration is former, If the substantive. permit would otherwise [FAA]
where the Pennsylvania govern choice of law to forward.”); Diamond, go A. Thomas governs LCOA means that the all PUAA Preemp- Choice Law Clauses and Their substantive, If aspects of arbitration. on the Federal Arbitration Act: tive Effect then must address whether the PUAA is Supreme Itself, Reconciling the Court with FAA, in conflict then (1997) (hereinaf- 39 Ariz. L.Rev. 60-65 the FAA preempt does our case. “Diamond”). ter
I
vacating
believe that
an arbitrator’s
C. Our Case
award because the arbitrator exceeded his
authority
procedural,
see Hade v. Na
case,
Applied to our
the issue is this: in
Co.,
Pa.Super.
tionwide Ins.
containing
provi-
a contract
an arbitration
(1986),
A.2d
overruled on other
FAA,
making
sion
no mention of the
is the
Co.,
grounds by
Keystone
Ins.
affirmative choice of
law a
Ostroff
(1986)
Pa.Super.
b. LCOA Is
and Must
from
we need to establish a
Against
be Construed
its
rule,
adopt
default
the one we
(RPS)
Drafter
clause,
choice-of-law
alone,
standing
support
is insufficient to
teaching
Following the further
of Mas-
trobuono,
provision,
finding
contracting parties
intend-
choice-of-law
deciding
My colleagues
Court assumed without
conclude that
Mastrobuono
Mastrobuono
merely
prem-
ambiguous.”). What
“a discussion that is
that the
contains
they ignore
following Shermanesque
presence of a
is the
assumption
ised on the
that the
"Respondents
clause can render a contract
statement of Mastrobuono:
Lehman,
ambigu-
ambiguous
al.]
intended
et
drafted an
[Shearson
as to whether the
document,
they
incorporate
rules into
ous
cannot now claim
state arbitration
*19
Mastrobuono,
298;
agreement.'' Maj. Op.
their
at
see also
benefit of
doubt.”
("[A]s
Maj. Op.
explained,
at
I give do not understand this statement. document should be read to effect to ge- provisions Mastrobuono nowhere that a all its and to render them con- states Mastrobuono, neric choice of law is insufficient as a sistent each other.” hardly matter of law to show that at 1212. It displace internally intended to the FAA. The Su- inconsistent to determine that preme position govern Court’s is more subtle. the choice of law to agreement involving governs an interstate also its section on When arbi- But, My colleagues displace 6. never state what the FAA’s intent” to it. as I note in this Instead, they posit by concurring opinion, default rules are. ukase I believe that Mastrobuo- they what determine to be the default rule for approach. no takes a more nuanced choice of law in an con- taining electing My colleagues any attempt an arbitration write that its own internal choice law. Their default reconcile Volt Mastrobuono is a "false that, rule is absent a "clear intent” to choose premise,” Maj. Op. at and that I "craft govern agreement's state law to assumption rule based on the that the Su- provision, applies. Maj. Op. the FAA at wrong." preme Court was Id. To the con- 293-94. trary, Supreme I believe that the Court itself supplies the two reconciliation between these brings This default rule into focus where however, light FAA, suggest, that in cases. I would my colleagues part. They and I read the issue, Maj. split Op. of the Circuit on this see presumably by preemptive principle some may (though they deny Supreme at n. wish to pre- that this is a case of 294), emption, Maj. Op. requiring clarify holding "clear its in Mastrobuono. *20 agree all implicates that choice a rule Where does this leave us? We tration when (which contracting parties and in no that the intentions of procedural I believe FAA) relating I prevail with the over the FAA. believe that the event inconsistent reviewing govern for an arbitra- choice of state law to to the standard provi- governs tor’s award. contract also arbitration that contract when arbitration sion within preempts The FAA procedure is affected. Among and Practice Drafters 2. Custom law is and the when substantive affected Agreements Support the Determi- state law chosen conflicts with the Pennsylvania nation that Law Gov- explicit agreement absent to override that erns the LCOA applied preemption. The standard to be practice among the drafters Custom and vacating modifying when or an arbitrator’s agreements support my belief that the submit, is, I procedural award matter. Pennsylvania in the choice of law LCOA Notwithstanding, law governs (including the entire contract its vacating arbitrators’ awards does not con- provisions). practice, In arbitration flict FAA. with the Therefore the PUAA. provisions highly are often apply should to the arbitration LCOA’s always They negoti- contested. are almost provision. comports This result with Volt agree- ated one Moreover, and Mastrobuono. under Mas- (as LCOA) usually ment and provisions trobuono the contractual here agreement. near the end of ambiguous are and must be construed invariably choice of law almost is meant to RPS, against the drafter of the Usually encompass agreement. the entire only Pennsylvania govern chose law to it thought given having no a bifurcated argues governing and now for the as is, choice of but if it the bifurcated Following approach arbitration. choice of law is set forth the choice-of- internally. leaves LCOA consistent provision itself. law thing One is certain to me. No default apply If that the FAA RPS had intended rule is called for which an unclear LCOA, to the section of the (as find) my colleagues intent becomes Moreover, would have so stated. to re- transmogrified legally unambiguous. quire within the arbitration section of the event, done, analysis In all when Pennsylva- LCOA the redundant choice of Pennsyl- result is the same whether under logically nia leads conclusion vania law or the FAA—the arbitrator’s provisions may that other of the LCOA Thus, I award is vacated. concur with the choice, also need to contain that redundant not, judgment part, my Court’s but col- e.g., provisions treating indemnification reasoning. leagues’ rights or termination events contracts involving transportation the interstate Thus,
products. express preemp- absent FAA,81 Pennsylva- believe that governs
nia law the LCOA’s arbitration
section.
[******] Volt, preemptive provision.”). 8. There is none. 489 U.S. at ("The express S.Ct. 1248 FAA contains no notes Mechmann rightly He sponse. Jersey Coast Teamsters Int’l Bhd. 863 justify or rationalize required (3d was not Inc., 533 Producers, F.2d Egg F.2d at Local his decision. See au of an arbitrator’s Cir.1985), scope the the correctly observes He also by the confined thority is defined sugges make was entitled arbitrator see, arbitrate, e.g., In Swift of his scope beyond that went tions Inc., Indus., F.2d dus., Botany Inc. v. Apex Fountain See authority to decide. Cir.1972). (3d Accordingly, the 1125, 1131 Sales, Kleinfeld, 818 F.2d Inc. v. make “may a court provides Cir.1987). (3d though ac Finally, [wjhere ... vacating [an] award order “ref made that the arbitrator knowledging powers.” their exceeded arbitrators issues,” Kayser process to due erence 10(a)(4). § U.S.C. of Mech eighth paragraph stresses pre- only issue undisputed that It “I decision, conclude which states: mann’s whether was arbitrator sented wrongful termination this was within [Kayser] was “termination RPS’s Kayser argues of the LCOA.” RPS District LCOA].” [the terms of not, analysis, “in the final did Mechmann exceeded the arbitrator found that issues process to the due tie his reference it manifest powers, his claims, Instead, Kayser decision.” into his text on the was based conclusion court’s simply process [was] to due “the reference decision, the rele- written arbitrator’s Mr. Mech irrelevant surplus, [was] pages set out are portions of which vant been not have and should mann’s decision noted that court opinion. The of this suggest by the court a basis used issue as “fram[ed] had the arbitrator au beyond his went the Arbitrator proper termination” wrongful one 14-15. Br. at thority.” Appellant’s the inade- to discuss “proceed[ed] and then opinion arbitrator’s parsing Before warning inde- procedure quacy of RPS’ au- his he exceeded whether to determine defi- performance contractors of pendent ques- first confront thority, must that ‘the finally conclude[d] ciencies and Kayser so. to do proper it is process to- in due lacking system[is] RPS ” from are barred that courts argue Ct. does Dist. contractor.’ the Claimant ward examining an statement of rea- arbitrator’s exceeded his or her authority when it is sons, and, events, at all such a contention obvious from the opinion. written contrary would be to our cases. See Unit- standards, Under these we hold that the Carnegie ed States Steel & Pension Fund District Court was correct in concluding (3d v. McSkimming, 759 F.2d that Mechmann exceeded authority. his Cir.1985) (vacating an arbitrator’s award Although opinion Mechmann’s begins by payment that ordered the pension bene- acknowledging that his authority is set fits where an examination of the arbitra- 9.3(e) forth LCOA, Section tor’s written decision convinced the Court contains paragraphs four of substan- that “the arbitrator’s award patently [was] tive discussion—all of which focus on the statutory interpretation based on rather way in which RPS communicated to Kay- Plan”); than the see also that it ser perfor- dissatisfied with his Power Co. Local Union # 272
