RMI Company (RMI) petitions for review of a decision of the Occupational Safety and
FACTS
RMI is engaged in the production of titanium at its Ashtabula, Ohio, facility. As a part of this process it is necessary to remove or chip “spalt” (a combination of titanium sponge and sodium chloride) from 10,-000 pound pots. The pots are put in place on a chipping deck by a forklift truck and the chipping operation is performed by three stationary chipping guns. These guns, resembling large horizontal jackhammers, are fifteen feet long and located six to seven feet apart. Each gun consists of a control console area, a gun support, a hydraboom, and a chipping hammer and bit that move along a rail to contact the spalt. During a typical work shift, the operator of each gun spends roughly three hours at the control console operating the gun, two hours at the pot site breaking up large lumps of spalt, cleaning up, performing miscellaneous maintenance, and replacing bits, and one-half hour maneuvering the pots.
The impact of the gun bits on the spalt emits a continuous staccato noise. The noise level is very high and was measured at approximately 107 decibels (dBA) over the seven hours of exposure during the normal work shift. This combination of noise level and duration of exposure per day exceeds that permitted by Table G-16 of 29 C.F.R. § 1910.95(b).
RMI has long realized the danger to its employees from such high noise levels. It has implemented a safety program requiring the chipping gun operators to wear “personal protective equipment,” viz., earmuffs. The ALJ found, and it is not disputed by the Secretary, that the earmuffs reduced the sound to which the employees were exposed to levels permitted by Table G-16. The Secretary has not disputed that RMI’s program was effectively enforced.
RMI contested the Secretary’s citation. The ALJ, after a hearing, determined that enclosures around' the pot area were not feasible and he modified the citation to that effect.
On discretionary review by the OSHRC,
TECHNOLOGICAL FEASIBILITY
Under 29 U.S.C. § 660(a), “any person adversely affected or aggrieved by an order
In reviewing OSHRC determinations other than factual findings, this circuit has held that our scope of review is that applicable to administrative agencies generally as found in the Administrative Procedure Act, 5 U.S.C. § 706(2)(A). Empire-Detroit Steel Div. v. OSHRC,
“The reviewing court shall—
(2) hold unlawful and set aside agency action, findings, and conclusions found to be—
(A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
We continued:
The Supreme Court in Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc. et al.,419 U.S. 281 , 285-286,95 S.Ct. 438 , 442,42 L.Ed.2d 447 (1974), stated:
“Under the ‘arbitrary and capricious’ standard the scope of review is a narrow one. A reviewing court must ‘consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment. . Although this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.’ The agency must articulate a ‘rational connection between the facts found and the choice made.’ . . .
While we may not supply a reasoned basis for the agency’s action that the agency itself has not given, we will uphold a decision of less than ideal clarity if the agency’s path may reasonably be discerned. [Citation deleted.]”
Applying the above standard to all aspects of the OSHRC decision other than economic feasibility, we hold that the decision passes muster. We cannot say that the decision on technological feasibility is “arbitrary and capricious” inasmuch as it clearly implements a substantial reduction in noise levels for at least the three hour period every day that the employees spend at the control consoles of the chipping guns. It was not unreasonable to hold that the enclosures represented “feasible engineering controls,” as that phrase is used in the
Given the fact that the employees will still be required to wear personal protective equipment for the remaining time they spend in the vicinity of the chipping guns,
ECONOMIC FEASIBILITY
Neither the statute nor the particular regulation involved here specifically discuss economic considerations relative to their implementation. Both, however, speak in terms of “feasibility.” 29 U.S.C. § 655(b)(5); 29 C.F.R. § 1910.95(b)(1). A consensus is developing among the circuits that the term should encompass both technological and economic feasibility. Numerous cases have held that the Secretary should weigh the estimated costs of compliance against the benefits reasonably expected therefrom when promulgating or enforcing a regulation. American Petroleum Inst. v. OSHA,
More particularly, the seventh circuit has held that the word “feasible” in § 1910.95(b)(1) should be construed to include both technological and economic feasibility. Turner Co. v. Secretary of Labor,
The economic feasibility test adopted by the seventh circuit in Turner Co. was that espoused by the OSHRC itself in another case. In Continental Can Co., 1976-77 CCH OSHD H 21,009,
“ * * * we conclude that the standard should be interpreted to require those engineering and administrative controls which are economically as well as technically feasible. Controls may be economically feasible even though they are expensive and increase production costs. See Arkansas-Best Freight Systems, Inc.,529 F.2d 649 , 653 [3 OSHC 1910] (8th Cir. Jan. 29, 1976); Industrial Union Department, AFL-CIO v. Hodgson, supra, [162 U.S.App.D.C. 331 ,] 499 F.2d [467] at 477. But they will not be required without regard to the costs which must be incurred and the benefits they will achieve. In determining whether controls are economically feasible, all the relevant cost and benefit factors must be weighed.’ ”561 F.2d at 85 , quoting Continental Can Co.19
We agree that economic feasibility should be considered by the Secretary both in promulgating and enforcing regulations.
It must be emphasized that the primary purpose of the statute and regulations is “to assure so far as possible every working man and woman in the Nation safe and healthful working conditions and to preserve our human resources.” 29 U.S.C. § 651(b). Thus, the benefits to employees should weigh heavier on the scale than the costs to employers. Controls will not necessarily be economically infeasible merely because they are expensive.
Therefore, the OSHRC erred in not making a determination of the economic feasibility of the Secretary’s proposed engineering controls. Coming as it did after the OSHRC decision in Continental Can Co., this failure to consider economic feasibility was especially “arbitrary, capricious, an abuse of discretion [and] otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). In this regard, the decision of the OSHRC is set aside and the cause is remanded for further proceedings.
CAN RMI RAISE ECONOMIC FEASIBILITY?
As noted earlier, RMI did not specifically urge the issue of economic feasibility before the ALJ or the OSHRC. The Seeretary argues that this failure bars this court from considering the issue becausfe of the portion of 29 U.S.C. § 660(a) which provides: “No objection that has not been urged before the [OSHRC] shall be considered by the court [of appeals], unless the failure or neglect to urge such objection shall be excused because of extraordinary circumstances.” The Secretary’s reliance upon this provision is misplaced.
The OSHRC decision in Continental Can Co.,
The unusual procedural posture of this case arose because of the fact that Continental Can Co. was not decided by the OSHRC until after the ALJ’s decision here and the filing of RMI’s brief to the OSHRC. Thus, neither the Secretary nor RMI were on notice to litigate the issue of economic feasibility since it was not until the Continental Can Co. decision that anyone knew the OSHRC considered this to be an element of the Secretary’s case. It would be fundamentally unfair to bar RMI from arguing economic feasibility to this court when the company had no reason to know it was a discrete element involved in the proceedings below and when, once it became such after Continental Can Co., the burden of proof on the issue was not on RMI but was on the Secretary. See Brennan v. OSHRC,
It would be equally unfair, however, to simply set aside the OSHRC decision by holding that the Secretary failed to meet his burden of proof since he, too, was unaware of the OSHRC’s position until Continental Can Co., decided after the ALJ hearing and submission to the OSHRC here.
Notes
.
.
. 29 C.F.R. § 1910.95(b), quoted infra, note 4.
. 29 C.F.R. § 1910.95(b):
(1) When employees are subjected to sound exceeding those listed in Table G-16, feasible administrative or engineering controls shall be utilized. If such controls fail to reduce sound levels within the levels of Table G-16, personal protective equipment shall be provided and used to reduce sound levels within the levels of the table.
(2) If the variations in noise level involve maxima at intervals of 1 second or less, it is to be considered continuous.
(3) In all cases where the sound levels exceed the values shown herein, a continuing, effective hearing conservation program shall be administered.
Table G-16 — Permissible Noise Exposures1
Sound Level dBA slow
Duration per day, hours response
8.................................... 90
6.................................... 92
4.................................... 95
3.................................... 97
2.................................... 100
iy2.................................. 102
1.................................... 105
y2................................... no
V4 or less ............................ 115
When the daily noise exposure is composed of two or more periods of noise exposure of different levels, their combined effect should he considered, rather than the individual effect of each. If the sum of the following fractions: (■',/T, + C2/T2 Cn/Tn exceeds unity, then, the mixed exposure should be considered to exceed the limit value. Cn indicates the total time of exposure at a specified noise level, and Tn indicates the total time of exposure permitted at that level.
Exposure to impulsive or impact noise should not exceed 140 dB peak sound pressure level.
. A nonserious violation is one cited pursuant to 29 U.S.C. § 666(c) for any violation other than a serious violation, defined in § 666(j)
to exist in a place of employment if there is a substantial probability that death or serious physical harm could result from a condition which exists, or from one or more practices, means, methods, operations, or processes which have been adopted or are in use, in such place of employment unless the employ-er did not, and could not with the exercise of reasonable diligence, know of the presence of the violation.
. 29 U.S.C. § 654(a):
Each employer—
(1) shall furnish to each of his employees employment and a place of employment which are free from recognized hazards that are causing or are likely to cause death or serious physical harm to his employees;
(2) shall comply with occupational safety and health standards promulgated under this chapter.
§ 654(a)(1) has been dubbed the “general duty clause” and § 654(a)(2) the “specific duty clause” since the former imposes a general duty to provide a workplace free of recognized hazards while the latter imposes a specific duty to comply with applicable regulations. See, e. g., General Electric Co. v. OSHRC,
See generally M. Rothstein, Occupational Safety and Health Law §§ 61 et seq. & 121 et seq. (West 1978) (hereinafter “Rothstein”).
. The ALJ also deleted the proposed $50 penalty.
. Table G-16 provides that the combined effect should be considered when daily noise exposure consists of two or more periods at different levels. See note 4, supra.
. Discretionary review was directed by one member of the OSHRC, pursuant to 29 U.S.C. § 661(i).
. Compare our “enigmatic” scope of review under § 655(f) for cases involving the issuance of a standard by the Secretary. See American Petroleum Inst. v. OSHRC,
. See Empire-Detroit Steel Div. v. OSHRC,
. Most other circuits addressing the issue have adopted the same standard of review. Titanium Metals Corp. v. Usery,
The second circuit has articulated the scope of review to be whether the OSHRC’s decision is unreasonable and inconsistent with the purpose of the regulation in question. General Electric Co. v. OSHRC,
See generally Rothstein § 485.
. RMI has argued that this determination was unreasonable as contrary to numerous ALJ decisions. The OSHRC is not bound by unreviewed ALJ decisions so we see no merit to this argument. The OSHRC decision was consistent with the prior OSHRC decisions in Continental Can Co.,
. See note 8 supra, and accompanying text.
. The Secretary’s brief in this court emphasizes the serious but gradual damage caused by high noise levels. It also cites several extra-record studies showing a tendency of workers not to use personal protective equipment since hearing loss occurs gradually and is not noticeable from day to day or week to week and since personal protective equipment is often uncomfortable to wear. The Secretary thus considers engineering controls preferable to personal protective devices since the former are not as subject to the human element as are the latter. We question the reasonableness of this highly paternalistic attitude on the facts of this case. The employees may be even more likely not to wear their personal protective equipment when away from the control console since the enclosures would obviate wearing such when at the control console and they would be required to continually put on and take off the earmuffs. If the response to this argument is that the employees should have the earmuffs on continually, then the engineering controls become totally superfluous since the employees presently wear earmuffs continually, which achieves Table G-16 levels. The OSHRC apparently rejected this logic, however, and we cannot say it clearly erred in doing so.
. While some cases suggest that we should pay even greater deference to the OSHRC decision when it agrees with the position of the Secretary, the second circuit has refused to adopt this distinction and pays the same deference to the OSHRC decision regardless of whether it dovetails with the Secretary’s position. See General Electric Co. v. OSHRC,
. The questions presented in the certiorari petition in American Petroleum include whether a health and safety standard promulgated pursuant to 29 U.S.C. § 655(b) must satisfy a cost-benefit test. See 47 U.S.L.W. 3541, 3542-43 (1979). The Supreme Court’s eventual decision in the case can thus be expected to shed some light on the issue presented in the instant case.
. In Turner Co., a case very factually similar to the instant case, the OSHRC decision had ordered the company to install engineering controls designed to bring noise levels within those permitted by Table G-16. The estimated cost of such controls was approximately $30,000. The company had an effective program requiring the use of personal protective equipment and no employee was shown to have suffered any loss of hearing.
. The OSHRC has subsequently reaffirmed and employed this standard in several cases. Atlantic Steel Co., 1977-78 CCH OSHD Ü 22,-843,
. See generally Rothstein §§ 81 & 99.
. The Secretary cites three cases in support of his argument. Keystone Roofing Co. v. OSHRC,
Cf. Todd Shipyards Corp. v. Secretary of Labor,
See generally Rothstein § 483.
. See also Atlantic Steel Co., 1977-78 CCH OSHD !i 22,483,
. 29 C.F.R. § 2200.73(a).
See generally Rothstein § 418.
. The OSHRC itself recognized this when, in subsequent proceedings in Continental Can Co., it held that the Secretary was not collaterally estopped to litigate economic feasibility despite his failure to raise the issue initially before the ALJ. The OSHRC realized that the Secretary did not fully litigate the matter since he did not then recognize his burden of proof. Continental Can Co.,
. The only indication as to cost before the ALJ was the estimate given by the Secretary’s expert as to the cost ($125,000) of the entire enclosure scheme which he recommended, but the ALJ modified this proposed scheme substantially so this estimate is not helpful. RMI has indicated the cost of the enclosures required by the ALJ, and the OSHRC, would exceed $100,000. But this representation was made in the form of an affidavit submitted in connection with a motion for a stay presented to this court. Reliance on this estimate, not subject to scrutiny by the Secretary, would also be inappropriate.
. We are clearly empowered to render this disposition by the following portion of 29 U.S.C. § 660(a):
If any party shall apply to the court for leave to adduce additional evidence and shall show to the satisfaction of the court that such additional evidence is material and that there were reasonable grounds for the failure to adduce such evidence in the hearing before the Commission, the court may order such additional evidence to be taken before the Commission and to be made a part of the record. The Commission may modify its findings as to the facts, or make new findings, by reason of additional evidence so taken and filed, and it shall file such modified or new findings, which findings with respect to questions of fact, if supported by substantial*575 evidence on the record considered as a whole, shall be conclusive, and its recommendations, if any, for the modification or setting aside of its original order.
We are willing to construe the relevant portions of the Secretary’s brief to this court as an application ‘‘for leave to adduce additional evidence,” for the reasons stated supra regarding his failure to adduce such evidence initially. This clearly constitutes “reasonable grounds for the failure to adduce such evidence.”
