ORDER
There have been no objections to the report and recommendation of Magistrate Judge Frank Maas, dated January 16, 2009. S.T.A. is entitled to judgment on its cross-claim against Golden Vale as recited therein.
As this disposes of the final open matter in this case, the Clerk shall enter final judgment, which shall include the award in favor of STA and against Golden Vale as set forth in the report and recommendation, and close the case.
SO ORDERED.
REPORT AND RECOMMENDATION TO THE HONORABLE LEWIS A. KAPLAN
I. Introduction
In 2005, construction work at the site of a parking garage on East 76th Street in Manhattan caused damage to a neighboring apartment building. After honoring the building’s insurance claim, the carrier commenced this action against the owner of the garage, defendant S.T.A. Parking Corporation (“S.T.A.”), and the entities that performed work at the site pursuant to contracts or subcontracts. Following extensive negotiations, all but one of the claims have been resolved. The only issue remaining concerns S.T.A.’s cross-claim against co-defendant Golden Vale Construction Corporation (“Golden Vale”) al
After Golden Vale filed an answer to the cross-claim, its counsel sought to withdraw based on Golden Vale’s lack of cooperation and nonpayment of fees. (See Docket Nos. 29, 36). That motion was granted on June 2, 2006, (Docket No. 51), but Golden Vale did not retain new counsel and has failed to participate further in this litigation. Accordingly, S.T.A. filed a motion for a default judgment against Golden Vale, which Your Honor granted on March 1, 2007. (See Docket Nos. 83-84, 90).
The remaining parties subsequently agreed to proceed before me pursuant to 28 U.S.C. § 636(c), but Golden Vale, which had already defaulted, did not sign the consent form. (Docket No. 115). For this reason, my determinations with respect to Golden Vale’s liability to S.T.A. take the form of a Report and Recommendation.
S.T.A.’s cross-claims against Golden Vale for contribution and indemnification were dismissed pursuant to a Stipulation of Partial Settlement dated July 23, 2007. (Docket No. 107). Accordingly, the only claim before the Court is S.T.A.’s negligence claim against Golden Vale. By order dated April 29, 2008, I directed S.T.A. to serve and file its inquest papers concerning the damages owed to it by Golden Vale by May 16, 2008, and gave Golden Vale until June 2, 2008, to respond. (Docket No. 122). S.T.A.’s papers were timely filed. (See Docket Nos. 128-29). To date, however, Golden Vale has neither retained counsel, nor submitted any papers in opposition to the S.T.A. submission.
For the reasons set forth below, I recommend that S.T.A. be awarded damages in the amount of $904,391.12, consisting of $326,089 in cost overruns and $578,302.12 in lost revenue.
II. Standard of Review
Although a plaintiff seeking to recover damages against a defaulting defendant must prove its claim through the submission of evidence, the Court need not hold a hearing as long as it has (a) determined the proper rule for calculating damages on the claim,
see Credit Lyonnais Sec. (USA), Inc. v. Alcantara,
III. Facts
The unrefuted allegations of S.T.A.’s cross-claim, together with its inquest papers, establish as follows:
A. Jurisdiction
The Court had subject matter jurisdiction over the original diversity action pursuant to 28 U.S.C. § 1332. Although S.T.A. and Golden Vale both are corporations organized under the laws of the State of New York, (Answer ¶¶ 13, 125), the Court has ancillary jurisdiction over S.T.A.’s negligence cross-claim pursuant to 28 U.S.C. § 1367.
See Owen Equip. & Erection Co. v. Kroger,
In 2004, S.T.A. sought to expand its garage from 90 to 150 parking spaces by-adding a sub-basement below its existing basement. (Aff. of Michael Zacharias, sworn to on May 15, 2008 (“Zacharias Aff.”), ¶¶ 7, 31). Accordingly, on October 25, 2004, S.T.A. entered into a construction contract with King Sha, which was to construct the sub-basement. (Id. ¶ 7; Ex. F). 1 The contract provided for King Sha to be paid $457,000, plus $675 for each cubic yard required for the underpinning of neighboring structures. (Zacharias Aff. ¶¶ 8, 12; Ex. F). Subsequently, the scope of work of the contract changed somewhat, bringing the base contract price to $463,000. (Zacharias Aff. ¶ 12; Ex. H). The contract provided that any subcontractors'hired by King Sha were to assume “all the obligations and responsibilities” set forth in the principal contract. (Ex. F § 10.3). The contract did not specify when the project was to be completed, stating instead that King Sha would have a “reasonable period for performing the Work” and that time was “of the essence.” (Id. § 13.1; Zacharias Aff. ¶ 9). Finally, the contract stated that New York law would govern the terms of the contract. (Ex. F § 18.2).
On October 27, 2004, King Sha hired Golden Vale to perform the excavation and underpinning required in connection with the sub-basement project. (Zacharias Aff. ¶ 10; Ex. G). Shortly after Golden Vale began that work, it became apparent that the soil beneath the foundation of the neighboring apartment building at 430 East 77th Street was loosening, causing the building to sink. (See Ex. J at 2). As construction progressed, so did the damage, until the New York City Department of Buildings (“DOB”) issued a stop work order on March 14, 2005. (Zacharias Aff. ¶ 14). Eventually, the DOB required that S.T.A. remove Golden Vale’s defective underpinning and replace it before resuming its work on the sub-basement. (Id. ¶ 16). By then, S.T.A. had paid $370,500 to King Sha and Golden Vale. (Id. ¶ 17; Ex. K).
Neither King Sha nor Golden Vale ever returned to the project. (Zacharias Aff. ¶ 17). As a consequence, on October 27, 2005, S.T.A. hired Coffey Contracting, Inc. (“Coffey”), to remove and replace the defective underpinning at a cost of $90,039. (Id. ¶ 19; Ex. L). S.T.A. subsequently contracted with Coffey to complete the original subbasement project for $298,750. (Zacharias Aff. ¶ 22; Ex. M). Unlike King Sha’s contract, Coffey’s contract did not include the cost of steel fabrication and installation. (Zacharias Aff. ¶ 23). S.T.A. therefore entered into a separate contract with MNS Construction and Renovation to complete that work for $85,000. (Id.; Ex. N). The DOB also required S.T.A. to retain the services of a consultant to monitor any movement of the neighboring buildings, which cost $13,330. 2 (Zacharias Aff. ¶ 21; Ex. K).
S.T.A. alleges that it eventually spent $857,589 to complete the sub-basement. (Zacharias Aff. ¶26). According to its construction expert, but for Golden Vale’s negligence, the project would have cost S.T.A. only $531,500 to complete.
(Id.
¶ 27; Aff. of James R. Beach, P.E., sworn to on May 14, 2008 (“Beach Aff.”), ¶ 4). S.T.A. contends that it consequently incurred $326,089 in cost overruns as a result of Golden Vale’s negligence. (Za
IV. Discussion
S.T.A.’s cross-claim against Golden Vale seeks to recover the damages resulting from Golden Vale’s negligence in performing the underpinning work. (Answer ¶¶ 124-29). To state a claim for negligence under New York law, S.T.A. must allege that: (a) Golden Vale owed it a duty; (b) Golden Vale breached its duty; and (c) the breach was the proximate cause of S.T.A.’s injuries.
Lerner v. Fleet Bank, N.A.,
As set forth below, however, because S.T.A. was in privity of contract with Golden Vale, an independent legal duty separate from the contract must exist in order for S.T.A. to recover on its negligence claim. Such a duty exists on the facts of this case.
A. Privity of Contract
In New York, there ordinarily is no contractual privity between owners and subcontractors.
See Morse/Diesel, Inc. v. Trinity Industries, Inc.,
Here, several factors establish that S.T.A. and Golden Vale were in privity. First, the prime contract provided that the subcontractors would assume “all the obligations and responsibilities” that King Sha had assumed with respect to S.T.A. and bound them to “the terms of the Contract Documents.” (Ex. F § 10.3). Under New York law, this alone is sufficient to establish privity.
See Brownell Steel, Inc. v. Great Am. Ins. Co.,
B. Negligence Claim
New York law does not recognize a cause of action for the negligent performance of a contract.
See Med. Research Assocs., P.C. v. Medcon Fin. Servs., Inc.,
To give rise to a tort claim, the independent duty “must spring from circumstances extraneous to, and not constituting elements of, the contract.”
Ross v. FSG PrivatAir, Inc.,
No. 03 Civ. 7292(NRB),
In its cross-claim, S.T.A. asserts that Golden Vale had a duty “to perform construction at the Project with ordinary and reasonable care.” (Answer ¶ 127). Notwithstanding this generalized tort language, it is clear that this duty in fact stemmed from Golden Vale’s statutory obligations under the Code. This suffices to make out a negligence claim under New York law.
See Goodyear Tire & Rubber Co. v. Kirk’s Tire & Auto Servicecenter of Haverstraw, Inc.,
No. 02 Civ. 0504(RCC),
C. Damages
Pursuant to its negligence claim, S.T.A. seeks to recover from Golden Vale damages consisting of cost overruns, lost revenue, and prejudgment interest. S.T.A. also argues that any award should not be offset by the payments it already has received from King Sha because Golden Vale is in default.
1. Cost Overruns
S.T.A. contends that it is entitled to $326,089 in cost overruns, based on the difference between the King Sha contract price and the amount ultimately paid by S.T.A. to complete the work. (See Inquest Mem. 3-4; Zacharias Aff. ¶ 28). It is clear from S.T.A.’s contract documents and the affidavit of its expert that the original contract would have cost $531,500 to complete. (S ee Exs. F, H; Beach Aff. ¶ 4). S.T.A., however, will ultimately pay $857,-589 3 to complete the project. {See Ex. K). Accordingly, the difference of $326,089 should be awarded to S.T.A.
2. Lost Revenue
S.T.A. also seeks to recover $1,156,604 in lost revenue, a figure it computes based on twenty-two months of decreased parking receipts in the amount of $52,572.92 per month. (Inquest Mem. 5; Zacharias Aff. ¶ 30, 37). Although twenty-two months appears to be a reasonable estimate of the length of time the project was delayed as a result of Golden Vale’s negligence, {see Beach Aff. ¶ 5; Ex. V), the alleged amount of the losses incurred is excessive.
S.T.A. states that it had ninety usable parking spaces before construction began, but at most only forty-five usable parking spots while the construction was underway. {See Zacharias Aff. ¶¶ 31-32; Ex. O). Because the completed construction increased the number of parking spots to 150, S.T.A. contends that it was deprived of the use of 105 parking spots throughout the period that the project was delayed. (Zacharias Aff. ¶ 32). To arrive at its monthly lost revenue figure, S.T.A. computed a per parking spot rate for monthly renters ($385) and daily users ($115.69) and multiplied these figures by 105. (Id. ¶¶ 36-37). S.T.A. contends that it is entitled to recover the monthly rental income for the 105 spots ($40,425/month) and the daily parker income for those same spots ($12,147.92/month); i.e., monthly lost revenue in the amount of $52,572.92. {Id. ¶ 37).
In these circumstances, I recommend that the monthly lost revenue figure be reduced by one-half. Thus, the monthly lost revenues would be $26,286.46, resulting in a total lost revenue award of $578,302.12.
3. Prejudgment Interest
S.T.A. also seeks to recover prejudgment interest. (Inquest Mem. 5-6). The Federal Rules provide, however, that a default judgment “shall not be different in kind from or exceed in amount that prayed for in the demand for judgment.” Fed.R.Civ.P. 54(c). Citing that language, the Second Circuit has held that a demand for prejudgment interest is not implied by a “generic request for ‘such other and further relief which this Court deems just and proper.’ ”
Silge v. Merz,
In its complaint, S.T.A. did not expressly seek prejudgment interest. Instead, S.T.A. simply sought judgment on its fifth cross-claim against Golden Vale in “an amount not finally determined, but believed to be in excess of $1,000,000.” (Compl. ¶ 129, Demand). S.T.A. also requested that it be granted its “costs, disbursements and attorneys’ fees incurred herein” and “such other and further relief as this Court deems just and proper given the circumstances.” (Compl. Demand).
Since S.T.A. did not specifically demand prejudgment interest in its complaint, the Court cannot award it based solely on its boilerplate request for “other and further relief.” Accordingly, S.T.A.’s request for prejudgment interest must be denied.
4. Offset
S.T.A. has received certain sums as part of its settlement with King Sha. (See letter from Russell Wolfson to the Court, dated April 23, 2008). In its papers, S.T.A. asserts that this money should not be credited against the amount it seeks from Golden Vale because Golden Vale is in default. (See Inquest Mem. 6).
In general, New York law protects non-settling tortfeasors from paying more than their equitable share.
See
N.Y. Gen. Oblig. Law § 15-108(a). To receive such protection, a tortfeasor must plead it as an affirmative defense; otherwise it is forfeited.
See Schipani v. McLeod,
Where, as here, a non-settling defendant has defaulted, and the remaining parties have settled their disputes, each party’s equitable share of the fault obviously has not been determined by a finder of fact.
See Godfrey v. Soto,
No. 06 Civ. 428(NG)(JO),
“The few New York courts confronted with a non-settling defendant who has defaulted have decided that the windfall should not accrue to the benefit of the party who has refused to participate in litigation.” Id;
see also Sniadach v. Gonzales,
V. Conclusion
Although the relationship between S.T.A. and Golden Vale was based on a contract, the Code gives rise to an independent legal duty which allows S.T.A. to recover on its negligence claim. Furthermore, S.T.A. has demonstrated a breach of that duty by Golden Vale. For the reasons set forth above, I therefore recommend that S.T.A. be awarded a total of $904,391.12, consisting of $326,089 in cost overruns and $578,302.12 in lost revenue.
VI. Notice of Procedure for Filing of Objections to this Report and Recommendation
The parties are hereby directed that if they have objections to this Report and Recommendation, they must, within ten days from today, make them in writing, file them with the Clerk of the Court, and send copies to the chambers of the Honorable Lewis A. Kaplan and to the chambers of the undersigned, at the United States Courthouse, 500 Pearl Street, New York, New York 10007, and to any opposing parties.
See
28 U.S.C. § 636(b)(1); Fed. R.Civ.P. 6(a), 6(d), 72(b). Any requests for an extension of time for filing objections must be directed to Judge Kaplan. The failure to file timely objections will result in a waiver of those objections for purposes of appeal.
See
28 U.S.C. § 636(b)(1); Fed.R.Civ.P. 6(a), 6(d), 72(b);
Thomas v. Arn,
Notes
. "Ex.” refers to the exhibits annexed to the Zacharias Affidavit.
. Paragraph 21 of the Zacharias Affidavit indicates that this "Vibranalysis” work cost $13,615, but paragraph 26 states that it cost $13,300. The latter figure is consistent with the cancelled checks and payment details outlined in Exhibit K.
. This figure includes $19,789 that S.T.A. still owes Coffey. {See Ex. K at n. 4).
