Riverkeeper, Inc. v. CrottyRiverkeeper, Inc. v. Crotty
Mercure, J.P. Appeal from a judgment of the Supreme Court (Kavanagh, J.), entered September 3, 2004 in Albany County, which, in a combined proceeding pursuant to
Respondent Dynergy Northeast Generation, Inc. owns and operates the Danskammer power plant, which is located on the Hudson River near the City of Newburgh, Orange County. Danskammer houses four steam turbine generator units that produce electricity. To cool the steam condensers, the plant uses a process called “once-through cooling,” which consists of drawing water out of the Hudson River, passing it through the steam condensers and then discharging the heated water back into the river. This type of thermal discharge—which deleteriously impacts fish populations—falls within the definition of water pollution regulated by the Clean Water Act (see
As relevant here, DEC last issued a permit for Danskammer in 1987, with an expiration date of November 1, 1992. In May 1992, the prior owner and operator of Danskammer, Central Hudson Gas and Electric (hereinafter CHG&E), filed an application for the renewal of that permit. On May 20, 1992, DEC
In February 2001, petitioner Riverkeeper, Inc., a public interest environmental organization, complained to DEC about the delay in the processing of the 1992 renewal application for the Danskammer permit, and demanded that DEC issue a notice that the application was complete and hold a prompt adjudicatory public hearing on the application. Ultimately, in October 2002, respondent Commissioner of Environmental Conservation denied the request for an adjudicatory hearing, finding that petitioner lacked standing to compel DEC to determine when a permit application is complete. The Commissioner further found that the permit was properly extended pursuant to
Petitioners then commenced this combined
Petitioners assert that their second and third causes of action accrued in 1997 and are subject to the six-year statute of limitations typically applicable to declaratory judgment actions (see
In their second cause of action, petitioners contend that DEC‘s initial extension of the 1987 Danskammer permit was invalid because
In short, on both causes of action, petitioners argue that DEC‘s interpretation of the State Administrative Procedure Act as permitting it to rely on CHG&E‘s 1992 application for renewal to extend the Danskammer permit for more than five years was arbitrary, capricious and affected by an error of law. Such claims are cognizable in a
“[A]gency action is ‘final and binding upon the petitioner’ when the agency has ‘reached a definitive position on the issue that inflicts actual, concrete injury . . . [that] may not be prevented or significantly ameliorated by further administrative action or by steps available to the complaining party‘” (Matter of Best Payphones, Inc. v Department of Info. Tech. & Telecom. of City of N.Y., 5 NY3d 30, 34 [2005]; see Matter of Essex County v Zagata, 91 NY2d 447, 453-454 [1998]). That a particular agency action is merely a step in the agency‘s decision-making process does not render that action nonfinal for purposes of review under
We are not persuaded by petitioners’ argument that the four-month limitations period could be triggered only by an official announcement from DEC that the extension of the Danskammer permit was going to span beyond the five-year term—which indisputably ended in May 1997. In so arguing, petitioners effectively seek to extend the statute of limitations indefinitely despite their awareness that the five-year term had run in 1997. Indeed, DEC‘s de facto determination that a
In light of our decision, the parties’ remaining arguments, including respondents’ assertions that petitioners lack standing and failed to exhaust administrative remedies, are academic.
Spain, Mugglin and Rose, JJ., concur.
Peters, J. (dissenting). Even accepting the majority‘s determination that the applicable statute of limitations period for both the second and third causes of action is four months (see
The decision of respondent Department of Environmental Conservation (hereinafter DEC) to delay its review of the 1992 renewal application of the Danskammer power plant was articulated in its letter, dated May 20, 1992, to Central Hudson Gas and Electric. It is beyond refute that petitioners were not intended recipients of that letter, that they did not otherwise receive that letter and that, even if they were entitled to the information contained therein, nothing could possibly have put them on notice that the “temporary extension” was going to last for this extended period. In fact, the only time that DEC actually made a “determination” that the extension for the Danskammer permit was going to span beyond the five-year term was in October 1, 2002 when respondent Commissioner of Environmental Conservation reviewed petitioners’ challenge to DEC‘s determination that petitioners lacked standing to compel DEC to review the Danskammer permit and that the permit was properly extended pursuant to
For the purpose of a