History
  • No items yet
midpage
Rissler & McMurry Co. v. Atlantic Richfield Co.
559 P.2d 25
Wyo.
1977
Check Treatment

*1 COMPANY, & McMURRY RISSLER

Appellant Cross-Appellee

(Plaintiff below), COMPANY, RICHFIELD

ATLANTIC

Appellee Cross-Appellant

(Defendant below), COMPANY,

CERTIFIED WELDING Cross-Appellee

Appellee below).

(A Defendant Joined

Nos.

Supreme Court of Wyoming.

Jan. *2 Pаrk, Harry Leimback and David B. E. material furnished to ARCO at its Sinclair Harry the briefs and E. signed Casper, position took a consistent refinery. ARCO agrument in oral appeared Leimback agreed and still does then appellant cross-appellee behalf under written contract for a the work McMurry Company. & $35,000.00, price of guaranteed *3 subcontractor, its the work Owens, was Murane, James W. Bostwick, unsatisfactory and incomplete to its McDaniel, Scott, Owens, Greenlee & Casper, $15,000.00, the sum of and damage in the signed the appeared briefs and in argu- oral against claimed now it and what it has total of appellee ment behalf and cross-ap- price. already paid guaranteed exceeds the pellant Atlantic Richfield Company. judgment Summary granted ARCO for Mullikin, R. Lathrop, Michael Uchner & interest, $46,088.94,' plus May Mullikin, Cheyenne, signed the briefs and there remained the counterclaim oral appeared argument on behalf of the Rissler. appellee and cross-appellee Certified Weld- Thereafter, joined defendant Rissler Cer- ing Company. as light tified defendant plaintiff GUTHRIE, J., Before C. and McCLIN- joined ARCO’s claim that defendant was RAPER, ROSE, TOCK, JJ. THOMAS contractor, not Rissler, praying that if RAPER, Justice. it be found Certified ordered work done judgment Rissler have against money judgments in plain- From favor of $40,967.94, for the firm together with inter- McMurry & Company against Rissler tiff at the rate of est 7% July 1970. Company defendant Atlantic Richfield denied Certified and still denies that it em- $35,569.30 sum and against defend- ployed or contracted with Rissler to do the sum Welding Company ant Certified paving ARCO. For the purposes of $5,398.64, verdict, based upon jury plain- prevent confusion, Rissler was re- appeals and partially tiff defendant Atlan- designated plaintiff as with ARCO and Cer- cross-appeals. Plaintiff tic Richfield Rissler tified, defendants. We continue that redes- principal is satisfied with the amounts of ignation. against judgments each of the defendants trial court al-

but claims the should have Apparently, during trial, the issues were: prejudgment lowed interest. Defendant contract, 1. Did a valid oral, written or cross-appeal Atlantic Richfield in its exist between Certified and pav- Rissler for have been entirely should ing plant roads at ARCO’s Sinclair refin- against joined Welding. defendant Certified ery? leaving it at mystery point Without . 2. Did valid either oral or lengthy opinion, in this we announce our written, exist between Certified and ARCO to affirm the district court ex- intention plant paving roads at the ARCO rеfin- cepting prejudgment to allow interest and ery Sinclair, Wyoming? judgments for correction ac- remand cordingly. shall refer hereafter to Ris- 3. aDid valid contract, oral, written Rissler, McMurry & as sler Atlantic Rich- exist between Rissler and ARCO for the Welding as field ARCO Certified plant paving of Sinclair, roads at Wyoming? Certified. 4. What was the reasonable or contract originally There by action filed price of labor and performed materials plaintiff ARCO Rissler for as- supplied by Rissler in connection with its phaltic petroleum materials and products work done on plant roads? the latter in its highway sold construction performed Was work in a work- $46,088.94. sum work Rissler re- manlike manner? payment, fused admitted the pay Its Was debt. refusal was based on the Certified limited to the sum of $35,000.00 ARCO, for all ground by way set-off, work performеd by owed either it for paving, equipment plant Certified Rissler on rental and base roads? (or) Certified and discussed with him the extent interest of Certified what

7. To it per- for work paving job. bidding liable paving. to do equipped was not At the formed? time, doing Rissler was in the area paving here are: issues The work for the State De- Highway interest add- prejudgment 1. Should about to finish partment, up its contract by judgments obtained ed to During the move on. course discus- Certified as ‍‌​​‌‌​‌​​​​‌‌‌‌‌​‌​‌​‌‌​​‌​‌​​​‌​​​‌‌‌‌‌​‌​‌​​​‌‍claimed against ARCO Certified, between ARCO sions it was matter of interest was not appellant? might that Rissler mentioned be available jury. None nor considered tried paving, after preparation by base jury consideration requested parties Certified. trial court de- allowance. of interest rep- Rissler was contacted a Certified on the verdict nied *4 prepared a Rissler’s estimator resentative. timely by it was demanded though amounts subject to the limitations that the quotation Rissler. Certified, work would be done by base unsup- a verdict reach Did primed oil by compa- would be base another evidence, in favor of Rissler by the ported and ny, and ARCO would furnish deliver ARCO, cross-ap- as a ARCO? against and asphalt liquid material to mix Rissler’s an errone- reached pellant, up set plant already vicinity. Rissler it instead of Certified ous mix, lay deliver and paved surface. would by instructions inadequate because price quoted “three Rissler inches thick a real is the issue judge, which seventy square yard. five a dollar That by cross-appellant. 11,000 square yards.” (The based on was advantageous appeal, evidence On figurе was 11,000 10,000). later reduced to given every party must be prevailing then, ARCO, a proposal Certified in reasonably can that be inference favorable paving in described its bid various it, in support of a fairly drawn and sq. price per yd. “Bid ways: based on Ford, Wyo.1970, Berta jury’s verdict. 10,000 sq. yds. asphalt paving 3" thick Wyoming Digest, West’s See * * existing *. Lump Sub-Grade Firm ®=^930, Error, many for other and Appeal 10,000 sq. yds. based on main price Sum court, reviewing we cannot As a cases. 3“ roadway paving thick.” The bid of Cer- our facts substitute job, prep- was for whole including tified Lander, 1969, City Miller jury’s. sub-grade drainage, aration and ex- Wyoming Digest, West’s 889. See cept that ARCO would liquid furnish the Error, ®=>999(1). Any mention Appeal The prime for hot mix coat. “Firm will opinion be set out in this of facts $35,- Lump price” Sum referred otherwise noted. light unless that 10,000 square yards at $3.50 000.00— dispose cross-ap- first of ARCO’s We will yard. square sequence of facts A narration of peal. fully ARCO quot- aware of Rissler’s background which should up build will price ed square yard, three finally into the more im- logically lead us just thick for paving. inches It was dis- question. portant by representatives Rissler’s directly cussed made spring plans of 1970 ARCO In the representatives with ARCO’s as well as refinery. open areas of Sinclair pave representatives of ARCO, when Certified time, working Certified at At the were present. all ARCO engaged performing welding plant, from others received bids as well. job, principal type of work for piping general was anxious organized. it is Certified's to know wheth which would do work because it superintendent experience there had with er it wanted job. qualified go on to another ARCO never did preparation and was dirt work proposal paving. representatives accept ARCO made Certified of roads “purchase “guar plus order” for a but issued cost for profit, item all of which $35,000.00,” maximum of which Cer were paid by anteed invoices ARCO. Further- purchase accepted. more, never The proposal tified order Certified’s included laying counter accept prime offer not an coat but became ARCO hired someone do that. proposal, ance of Certified’s var else to evidence of an oral offer. Trautwein v. ied the terms ARCO with Rissler was sub- Wyo.1970, 472 P.2d stantial. Leavey, 779. With commitments out firm ARCO told Cer paving phase by Rissler encountered with the base. proceed

tified Certified problems. can conclude the evidence bought crushed base material from Rissler. acting upon instructions from ARCO problems spots ran into soft personnel, Rissler was directed lay down usual where the crushed rock base could up inches paving to 16 at points critical used, satisfactorily so consultation than the rather uniform three inches antici- person with and instructions from The net pated. result was that equiva- nel, asphaltic spots base in those 18,519 square yards lent of paving upon. decided three inches thick was down, laid problem developed actually A the area further when was covered was probably half plain figure. discovered that the about usual rock There crushed is no evi- dence, conflict, base could not be pipes used over Rissler did not deliv- lay 3,000 er plant roads. down By using were under tons paving mate- *5 which, if tamping equipment, danger the rial laid at of creating thick, three inches equal 18,519 the apparent. Again, leaks became would square an asphal- yards in- upon; per square $1.75 tic mix base was decided voiced yard such a mix for a sub-to- $32,408.25. solidify being spread. after tal of would In its All base invoice paving, for further material —both crushed rock there was included special special the base tons at Rissler, (393.5 $7.50) mix —was ordered from it mix rate of previ- mentioned, coming ously $2,951.25, to billed to Certified. The plus crushed base was separately material, invoiced sales tax of on by $50.90 to ARCO crushed Certified for $5,398.64. grand $35,410.40, to total of paid and came that special ARCO price quantity sum to Certified. the mix was not dispute. Certified admitted at in figure trial that it should The last is the exact have that amount of forwаrded jury’s verdict in amount on to Rissler. The favor of Rissler and ARCO, against when a that amount further is not amount of equipment rental, for dispute. special asphaltic base to $158.90 materi- which Ris- entitled, by al furnished Rissler was sler was is added. on another bill and we will come to that. argues ARCO that if the jury had

Rissler, shortly July 1970, began before given “step” instruction, been or “issue” it heavily pressing management ARCO for have reached the could not result it did and go proceed ahead because it to to there therefore was error in the jury While the job. next evidence at point been must have confused. jury conflicting, light becomes in the in the instructed law of contracts, written verdict, jury’s we conclude ARCO dealt quantum meruit, oral contracts and directly with Rissler and instructed Rissler apparently not particular form figurе proceed quoted to basis of its preferred. connection, ARCO In that we do square yard, three inches thick. $1.75 not find attached to its brief the ideal form An oral contract was thus That formed. it nor do suggests any we find reference to directly ARCO dealt with Rissler is borne any instruction it offered and was refused fact billing out instead of by the coúrt which demonstrates the stan price ARCO for contract urges. dard it We “step understand a in square yard, Certified billed ARCO struction” to be one where jury is di base, laying the on a pay-as-they-went basis step by to step rected consider prop- various nation on the grounds objection may order. are fa- particular in a ositions miliar murder ed homicides when and step somewhat exactly support notice a claimed State, Wyo.1976, find instructions1 able wеre eration. sue” “step” should Safeway terial was offered see none requests the objects the “* stating struction * * precedent 365; instruction, also [*] instruction, part: giving jury *6 * * argues In examination instruction cases what of that * [*] Rule 756, 763. Stores, law as set made and the distinctly the matter to in what Nichols >> that not at a unless No retires to consider been an [A]ny party or the made ARCO 51, W.R.C.P., provides in ma loss, to the step instruction party error the proposition. instruct it cogent argument. Inc., as visualized he grounds of his order there should have been offered, no form of “is offenses. to the trial offers no court instruct however, “issue” only was failure to Pangarova, Wyo.1968, forth in the objects avail- unsupported by has in may assign as error Wyo.1972, 502 P.2d judge form in which to consider includ- may file other instruction; we thereto before mind. jury We nеed not 415. We are objections authority Evanson v. give its than there figure judge, his objection. which he requests. form of the used verdict, written ARCO, consid Joly While how, they jury out we in- satisfy its verdict different There step establish oral The burden been convinced. verdict same such cross-appellant the court for a that the finding upon each such a verdict request interrogatories is form rogatories, dict. The the decision the ty of the best “* * position gested language, does one or issue instruction had instruction, rather a form of verdict. We find no request information, rule, special of is no form, accompanied by written inter in favor giving for a form of used. Rule judge and in its ARCO seems to prejudicial error special result would have been submission give know whether the based rule, the court upon way to infоrm the court of which is to the form language showing may require any wanted the one; if the of a one or more issues of form of a special on a written contract, quantum verdict with instruction on the issue in writing if submission of his 49, W.R.C.P., provides should may party verdict different or made that even if a is necessary nor objection by than to the record nor did sound discretion of failure to absence, cross-appellant of fact. By the submit a do we find meruit. includes have or concerned that jury we the proprie- answers requested used, possible.” a general have not returned to a ver submit reached. counsel, general written divulge a find If the return of his issue, than fact, sug- any a Dreesen, 1975, every necessary Haley material fact in ing said in v. As jury. to a expla- Murphy a clear submitted while issue Smith 532 P.2d signed purpose, making objecting jury practice than a Apparently, other record for of Kitts, Wyo. 1975, purposes. jury appeal is contin- Runnion v. has retired after instructions County uing It is 1312. We District Court. can visualize counsel in Natrona by parties thinking objections stipulation no being of while the instructions done during being given argument. par- They objection raised. Even are will be good by very stipulation, frown on the little when so we entered after ties do W.R.C.P., Here, requiring jury ob- we find an of retires. even untime- Rule avoidance given objection argument being along jections ‍‌​​‌‌​‌​​​​‌‌‌‌‌​‌​‌​‌‌​​‌​‌​​​‌​​​‌‌‌‌‌​‌​‌​​​‌‍ly be before the to oral made to instructions Leasing objections It is with instructions. not an Jackson v. Gelco retires. practice process Wyo.1971, 1052. The of mak- case such a defeats issue purpose ing objections rule instructiоns at time when of a desirable fashioned improvement upon opportunity permit to reflect correction or least of has an the court proce- judges objection approve Trial should not is a desirable instructions. well-taken some stipulations. error. It serves well-de- can avoid such dure and Sales, Inc., son for Wyo.1976, 544 P.2d the rule Trailer and some of its ramifica- tions may helpful also be the deciding of question future cases. The usually us, appears study after It as incidental issue in 1,100 pages appeal, of record in this Here, a case. it the principal issue, so we through slashed the underbrush it believe deserves more attention. to the core of matter: right was there Some contracts specifically provide for plaintiff between Rissler and contract de interest. Those cases can be upon decided what ARCO and sort of if fendant their contract terms regarded as com- any, properly was there Certified? It pensation for the use of money or for the the existence of pushed aside written extension credit. The contract in such Certified and found a com contract with governs instance itself by interest way plete plaintiff oral contract between compensation or damages for breach. We defendant, with unit of measure within are not concerned with that type of con- compute terms could its concerned, tract. We are here, with the Rissler’s contract entitlement. amount that is silent with respect to inter- meruit was quantum unnecessary. Resort While we est. have statutory provisiоn for can no confusion in the find verdict. interest, allowance it does pre- not applied contrary, it To the extraordina cisely indicate application to recovery as ry usually sense followed common litigation. a result of adequate We hold that jury. 13-477, W.S.1957, C.1965, Section instructed, ly understood the issues and act provided as follows: upon basis of ed substantial evidence. “Interest the loan or forbearance of court has spoken frequently This money, goods things action, shall be prerequisites to recovery pre about cent, per at the rate of seven annum, per interest holds with the ma rate, greater unless exceeding ten that interest jority cent, courts recoverable annum, be contracted liquidated unliquidated but not on parties.” and that a claim is considered 9-103, By Ch. § Session Laws of Wyo- readily computable by when simple ming, that section was amended to computation. Zitterkopf mathematical read as follows: Roussalis, 436; Wyo.1976, 546 P.2d Mader v. “If agreement there provision James, 190; Wyo.1976, 546 P.2d Chandler- rate, law for a different Gorrell, Simpson, Wyo.1970, Inc. money shall at the rate of seven [sic] (see Wyoming cited); cases there per annum.” percent *7 Insurance Company United Pacific Mar same words appear 40-9-103, also as § Contractors, tin and Luther General Incor W.S.1957, 1975 Cum.Supp., part as of the 664; 455 porated, Wyo.1969, Leet v. Uniform Wyoming Consumer Credit Code. Joder, 1956, Wyo. 75 295 P.2d 733. See far ease is concerned, As as this the law has Company Construction also changed. not The interest rate is adopted Casualty Surety Western 10 only as а convenient measure of damage for den., 275 F.2d cert. 362 Cir. U.S. money loss of use of and recognizes the 1011, allowing 80 4 L.Ed.2d S.Ct. view legislative money that has value be- recovery on a of interest claim decided on yond its intrinsic worth. Wyoming law. the basis of None of the Wyoming cases which have While the rule is stated those clearly particularize been cited that cases, it undergone very has little discussion incorporated statute is as a matter of law in jurisdiction. in this think rule whether, all contracts or where allowed as a probed to be needs order for there to be recovery, of is interest added as an understanding holding allowing of our damages item for breach of recovery of interest this case. The just rea- pay failure to claim when due. In event, statutory liquidated has beеn whether a claim is or unliquidat- interest the standard for the rate ed. The real is the only used consideration ease allowed, has when deter- the amount due A interest which can be reached. Re- liquidated.2 amount due liquidated mined claim is when it is readily com- agreed upon interest is of whether gardless by simple mathematical putable calculation. applied, statutory rate is advance or Company Pacific United Insurance v. Mar- for penalty pay failure it constitutes Contractors, tin and Luther General Incor- due.3 money when over case, supra. In that porated, this court the district denying affirmed court in inter- money to the use was entitled that est the basis the claim on there in contract with earned on its it had which controversy required weeks to try and due; it became the date from ARCO myriad, perplexing problems aris- time. Ris- accrued that cause of action ing arrangement of the loosest kind of out money to the use of entitled also sler was the contractor and the subcontrac- Certified from the between it is entitled money has due. use tor that there not claim which date it became of which Rissler has readily computable by simple value economic mathe- real Money ability has the deprived. calculations. matical earning interest. in terms reproduce us, the case now before there only In inappropriate when Withholding interest application rudimentary needed capi- of use of contractor’s loss causes the predetermined arithmetic knowns. life. fact commercial tal. Interest aware fully of Rissler’sprice ARCO sense, nec- In that square paving: per yard, $1.75 three inches plaintiff, only not compensate the essary to Rissler’s explained, estimator thick. both it has suffered by which the amount testimony, letter because of sense for breach of damages in the usual thickness, variation wide not be could use the loss of also for contract but computed an area-covered basis ARCO it is entitled. money to which explained He that a obvious. cubic foot the use of gained money weighs pounds. material paving At lost and to extent which Rissler rate, yard, thick, a square three inches enriched. We note a unjustly have been = (3 ton X 3 weighs per sq. 0.162 ft. ft. ft. case, in this inequity when the particular = -*(cid:127) per 2.25 cu. ft. yd.; sq. yd.; allowed interest ARCO's trial court n + n = per sq. yd.; X 144 324 lbs. 2.25 petroleum prod- clаim = 2,000 3,000 0.162tons sq. yd.); tons of ucts, so, failed to allow inter- properly applied to material used that factor of 0.162 est Rissler. 18,519 yards equals equivalent; 18,519 and Certified contend that Ris- ARCO = $32,408.25. sq. Xyds. was not because of sler’s claim questioned never that computa- long trial and the contested nature of Those tion. it tinkered at demands. factors While cross-examina- Rissler’s estimator, affect the determination of necessarily strengthened tion statutory damages. (Jae- use 2. Some courts do not rate Williston on Contracts 3rd Ed. example, E. I. For see Du Pont 1413; measure. through ger) 5 Corbin on Con- §§ *8 Lyles Company Lang & De Nemours & Con tracts, 1046; through 1044 McCormick on §§ 328, 1955, Company, 4 Cir. 219 F.2d struction 52; through Damages, 61 Law §§ 50 Harvard 956, 884, den., 75 99 cert. 349 U.S. S.Ct. L.Ed. 113, 136, Developments in the Law— Review 1280, fixed the interest on the where 107, Damages; Review Pre- 15 Stanford Law pay what the contractor would to basis of upon Damages; judgment Interest as 5 U.C.L.A. Law principal amount of his a loan 262, Damages Interest as in California. Review recovery, considering money state Annotation, 487, 2, 492, 60 A.L.R.3d § also See charged banks. market and rates The court Prejudgment Interest on Builder’s Allowance statutory apply there refused rate. Recovery in for Breach of Action Construction Contract. generally and scholars The text writers ob- of interest serve that the allowance constitutes

33 position of Rissler that its unit costs question determinative of the whether an the same. ARCO offered no evi- money remained amount of sued for is a ‘liquidated ” place figures its own to Rissler’s dence of sum.’ dispute. Rissler’s claim never varied from subject, Prejudg “Award of to verdict. If there initial invoice Recovery mеnt Interest Builder’s in Ac complexity, dispute it went Contract,” tion for Breach of Construction liable, who was whether there was a over has received extensive treatment Anno validity counter- guarantee, ARCO’s tation, 60 A.L.R.3d 487. generally agrees It matters have nothing and those in its conclusions with the prevailing rule liquidated whether claim is or not. liquidated par claims. Of the amount of Proof of claim and how juncture ticular interest at this analy is its computed took but a matter of few min- beginning page sis 512 that virtually utes. every jurisdiction following the rule that only was computation

Not un when a claim under a construction contract but it used a liquidated, involved contract unit stan is or where thereof, the amount agreed between ARCO and dard Ris- although unliquidated, capable is of as square yard, sler: three inches calculation computation, certainment is Where there a standard fixed thick. recognized it is also held or that a contrac contract, from which the amount right to tor’s recover interest on his claim is may computed, liqui earned there is a by the act of not barred the party against figure, which should bear interest dated it asserted putting whom forward an date due. Paduano v. J. Boesp from the C. unliquidated counterclaim or set-off. The 1965, Company, flug 66 Construction counterclaim or set-off does not convert a 527, 841, 845, citing P.2d Wash.2d Mall demand into one liquidated is unliqui- Equipment Co., 1954, Co. v. Far West Tool & dated. Herbert Brooner Construction Co. 158, Elte, 45 Wash.2d 273 P.2d 652. In Inc. Golden, Mo.App.1973, 541; 499 S.W.2d Inc., Mullen, 1972, v. S. S. Cir. 469 F.2d Lasher, 1945, 594, Knutson 219 Minn. 1127, 1133, the rule was Paduano laid out 696; 688, Covell, N.W.2d ‍‌​​‌‌​‌​​​​‌‌‌‌‌​‌​‌​‌‌​​‌​‌​​​‌​​​‌‌‌‌‌​‌​‌​​​‌‍Hansen v. 1933, neatly say that prejudgment more inter 772, 670; 218 Cal. 89 A.L.R. (1) is allowable when an est amount claimed v. Ryan, Pearson 42 R.I. 105 A. (2) or when the amount 513, 3 A.L.R. 805. unliquidated and this amount claimed Even though the existence by computation with refer determinable unliquidated counterclaim or set-off neces standard contained ence to fixed amount sarily puts the payable doubt, opinion without reliance on or dis is well settled does not render the cretion. deprive uncertain or claim itself the claim rule, discussion of In his McCormick right ant of interest. Damages, 215-216, pp. 54 at § states: Corporation Fluor v. United States ex rel. “ * * * claim for Is the such a sum Steel Mosher Cir. demand, ‘liquidated’ still where the de- 823, 830, den., cert. F.2d 394 U.S. liability fendant denies all under the con- 1632, 23 L.Ed.2d 40. S.Ct. See also Jim tract, disputes liability for certain E, Inc., Arnott, L Inc. v. & Colo.App.1975, and admits It items others? would seem C — Star Concrete of a dispute the existence over Corporation v. Hawaiian Insurance whole claim should not Guaranty Company, 8 Wash.App. the character of the change claim from 509 P.2d 758. Mere differences of opinion a liquidated, unliqui- one for to one for an due preclude the amount do not pre sum, and this conclusion sup- dated finds disputes interest nor do as to ** port in the cases. liability. Co., Homes & Son Construction “ * ** *9 short, Corporation, 1974, it is the In character of Inc. v. 22 Ariz.App. Bolo of the 303, the claim and not defense that 1258. P.2d when Contracts, part damages interest is a pp. 286- on § Corbin impossible it is to ascertain whether allowing when applied approved 287, is included interest in the award jury had Flandro, v. in Mitchell interest unliquidated contract or claim. This on an 455, appeal after re- Idahо come does not within either inhibition case 236, 526 P.2d 841: 96 Idaho mand decision. The not Leet of or a a service contract the case of “In on the matter of interest instructed agreed price, contract at an construction party requested such an neither instruction. completed has been the work when the exact The verdict amount there is a accordance under contract. claimed due There is debt, even money nothing suggest that to interest was includ may honestly believe that the defendant * * of Indeed, the amount the verdict. ed in properly work not done. to entirely the contrary. the record This interest is collectible on In all such cases on contract and does action not the date the sum due from of breach. portion of the Wyoming involve the statute accounting may The fact that skilled be case, Leet in the considered which allowed involving necessary, determination of * * money due, “on interest sales, received, prices of amount withheld unreasonable of delay pay expenses prevent not does overhead right The interest ment.” followed as a of interest.” allowance law matter of and did not involve ques remand, appeal, ap- after the court On tion fact. Construction Com proved computation the lower court’s v. pany Casualty Surety Western Com interest. pany, supra. See also Engeiberg v. Sebas A word of caution is added. The tiani, 1929, 207 Cal. 279 P. stating receive notice of must the amount debtor no question there is for a jury fact interest starts to run. A due before de decide, no function the jury cannot be default if he is fendant not usurped, interest incident an award of pay. of what to There must be a informed price plaintiff and the the contract should and determined amount fixed which could rightful his not be mulcted thereby been tendered and interest judgment. Miller, 1944, Binning Wyo. stopped. We hold that Rissler was as a entitled If 146 P.2d 527. the amount from of law to interest ARCO at the matter owing the amount can be indebtedness centum annum from rate seven calculated and determined from statements the date Rissler’s bill August correct, rendered and found is a $35,410.40, paving, sum of of mere calculation. Chandler- matter $158.90, rental, equipment was delivered Gorrell, supra. Simpson, Inc. We hold that Rissler was enti- to ARCO.5 to interest as matter of law tled from question posed has been $5,398.64 Sep- sum of allowing matter of interest whether the 17, 1970, the date Certified was tember jury. have been In should invoice of that date indicates billed. Joder, supra, denial of interest Leet previously that Certified been invoiced upheld after basis invoice cannot be the first found in the in that case. The of circumstances court record. power of a that the court to add inter said a verdict is based on the assumed est to We affirm the district court in all re- grant plaintiff except its failure to provide prejudg- failure spects he is to which entitled as a matter of interest. remand to the ment may compute judge law and that add with directions interest at 21, 1975, 13-479, W.S.1957, deposited May Repealed 5. On with the Section C.1965. 9-103, Laws, Chap. Wyo- Session district court clerk the amount of § ming, it. entered

35 annum, percent per nеgotiations con- rate of seven arrangements and between ARCO, opinion, with this to the date of the Rissler, sistent Certified and this court is appealed from and enter modi- judgment entitled weigh that evidence and con- judgment accordingly. fied clude that “ARCO dealt directly with Ris- sler and instructed proceed Rissler to on the McCLINTOCK, Justice, dissenting in figure quoted basis $1.75 THOMAS, joins. with whom Justice part, square yard, ‍‌​​‌‌​‌​​​​‌‌‌‌‌​‌​‌​‌‌​​‌​‌​​​‌​​​‌‌‌‌‌​‌​‌​​​‌‍three inches thick. An oral thus formed.” Using majority I with the this con- sustaining concur agreed upon tract standard by Rissler and judgment fixing court district ARCO of per square yard, three sum due from and Certified to thick, inches it then becomes a matter of but must dissent Rissler1 rudimentary arithmetic to compute opinion requiring the inclusion inter- amount due. This results in a well majority present structured est. figure “which should bear interest

argument, which from the long the basis оf is the date due.” well established of this court that rule which are calculable readily sim- My own examination of the evidence computation2 mathematical from the ple leaves me in doubt that an actual oral con- upon of the contract3 are claims which face tract existed between ARCO and Rissler for be prejudgment included in performance of the paving upon work They as matter of law.4 agreed compensation and were it materi- parameters computation on the find al the position I which take I might well an oral contract which they find was face disagree. However, throughout the plead- into between Rissler and ARCO. entered ing, pretrial stages and trial of the proceed- process interpretation done This upоn ings appeal to this court Rissler the jury’s verdict, the evidence and present has continued to alternative claims: to me. unacceptable (1) that either express there was an con- opinion, As I read the al- furnishing holds that tract for the of service and ma- conflicting the evidence was terials at agreed as price permitting appli- majority previous decisions, Joder, as in Parties are referred to 225, 1. Wyo. v. Leet 75 opinion. 244, 733, (1956), 295 P.2d 740 In re John- Guardianship, Wyo. 173, son’s Estate and 78 Roussalis, Zitterkopf v. 546 P.2d 2. 439 429, 433, 72 (1957), 320 P.2d A.L.R.2d745 James, (Wyo. 1976); (Wyo.1976), Mader 195 has this court ventured discussion of the principle appears reh. denied. damages subject of interest as and both are first to have been enunciated the denial for My point. perusal inconclusive on the own McKay, rehearing Wyo. in Kuhn v. the tеxts and majority opinion, cited in (1897), authorities note 3 of applied P. has been majority particularly Prejudgment opin numerous cases as cited In- Damages: Application ion. terest as New of an Old Theory, (1962-63) L.Rev. 107 Stanford has Gorrell, Chandler-Simpson, Inc. reap- convinced me that needs to (Wyo. 1970) only appears to be the praise carefully unreasonably what me the referring decision face of the inequitable rule of narrow and sions, our earlier deci- Kuhn, supra contract. computation n. found the basis for seriously consider whether this court price; market an established kept step developing jurispru- recognized that this others have basis but found that there was market was a valid dence of our sister states allowance of established legislaturе’s interest. Our amendment of the price, g., e. Johnson Hanover Fire statute, majority opinion, 120, 137, Wyo. as shown in the rais- Insurance P.2d (1943). interesting questions. appear I 619-620 es If in this my convictions, talking against note it is Only accept purposes dissent do I of this questions for the reason that those should be agreement complete this majority I rule. am in with the only they are considered in briefs matter of that the whole arguments of For this counsel. reason I interest deserves extensive consideration this court and am my limit dissent to the narrow issue of allow- sympathetic with their indi- ance as matter of law of interest leaning allowance cated toward the of interest readily computable claim. damages. I note that in two of our *11 36 specific quantum it. A instruction on to work prices contract the of the

cation only by objected the to ARCO and done; it did the work with (2) or that meruit in that the acquiescence of ARCO this court knowledge party and contends no full to represent was entitled recover as such did not cor- reason for that instruction and of the service and ma- the value law. While continu- rect statement the reasonable furnished, by indepen- jury properly as established the to claim that could ing terials evidence, usually is recovery which an oral contract and its found based dent thereon, pleadings arguments to the and in way in aban- referred only If it is rea- previous recovery meruit. the claims to its quantum doned of the service and materials work. majori- value value sonable reasonable recoverable, jury if the even the found is that that ty’s cоnclusion value to be fixing price such reasonable the finds was an oral there deep, work, it nevertheless follows yard, 3" than square rather liqui- thereof, the claim was not amount of reasonable value is that the to the entitled the and could not be so unjustified. to suit prior my opinion dated trier the the fact until reported Supreme In first case the the reasonable value. such determined Wyoming Territory, Western Un- Court recog qualification clearly think this I Monseau, Company v. 1 Telegraph Wyo. ion majority, cited by authorities nized was said: (1870) it 19 “ Washington * those from * * particularly proper there is evidence to [I]f Company Mall Tool v. Far Circuit. Ninth a jury to on the issue before be submitted Company, 45 Wash.2d Equipment West it; them, province weigh it is their C. (1954); 654 Paduano v. J. P.2d 273 very case, appealing be a clear it must 66 Boespflug Construction strongly conscience of the very (1965), and Wash.2d permit us court, to interfere to induce Mullen, Inc., Elte, 469 F.2d Inc. v. S. S. It is not sufficient with their decision. denied, 1972), 1127, 1133 (9 apply reh. Cir. jury might probably another arrive liquidated claim as stated in of a definition conclusion, nor at a different Damages one p. 213 as § McCormick entirely satisfied with the court should which, evidence furnishes data “the where verdict; if proper there evidence for believed, possible compute makes it if tending prove to consider and them exactness, without reliance amount we must be presented, satisfied with issue opinion (Emphasis or discretion.” upon unless it is judgment, made to ap- their clearly added) qualification applied judgment has pear that their been unfair- Ulvestad, Hopkins v. Wаsh.2d ly exercised.” (1955): P.2d “ * * * weigh This reluctance to evidence has involving This not a case throughout history continued court’s labor pay and material promise Sekulich, 80 Wyo. 437, and in Culver agreed capable being rate thus (1959), Parker, Mr. Justice ‘liquidated’ to as claim. It is referred court, for the said: speaking involving implied prom- a case rather “ * * * appel- It is function of an at a reasonable rate labor pay ise to ascertain whether or not furnished, late is an and material hence ” * * * evidence upon substantial there ‘unliquidated’ claim. of fact could base its the trier questions one that Rissler was enti- No testimony. if it believed It is opinion payment tled some amount evaluate evidence that us to not for performed it, work but someone presented.”, tending did it introduce evidence Wailes, recovery shortly intro- thereafter Neal also justify 132, 134 (Wyo.1959) Jus Mr. Chief expert testimony designed to estab- duced expressed way: done it this the reasonable value the work tice Blume lish “ * * proper It is not for this court upon based negligent maintenance of before a in a case tried to exercise certain property violation of an authority beyond periphery of its applicable city ordinance. In the one in- leave to ordinary power the indemnifying liable; stance insuror was finding the facts function of as hereto- in the second it was not. The court said: fore exercised under rules of common plaintiff “The having invoked two law, reconciling the conflict evi- grounds negligence, general ver- *12 dence, drawing inference, own if dict in his may favor not be construed to permissible. more than one inference is upon have been based ground one only— }fc $ jfc the manner of piling the beams.” If, conflicting evidence, on it is not for us Summary judgment in favor injured of the what view of the say evidence party against the insuring company was accepted, how logically can we should have reversed and the cause remanded for a fac- two hold that where alternative theories trial. tual pursued actively to and are available we Since are not ordinarily the trier of may party, weigh we the evi- prevailing facts, I do not think that we can assume conclude as matter of law that dence that burden for sole purpose of permit- jury has found facts under one ting recovery of interest. We have express- theory? general The rule that “a verdict in ly rejected objections ARCO’s relative to party a finding every includes favor the failure of the trial court to make the material, necessary, and issuable fact which jury indicate the basis of its verdict. I do jury,” has been submitted O'Brien v. not think that it then lies prov- within our Acceptance Motors Corporation, General say upon ince which of two alternative (Wyo.1961), helpful theories, both favorable to the prevailing only necessary it is facts because that are to party supported by substantial evi- so considered found and in the case at dence, has found in favor of that finding rendition bar a of valuable serv- party, any more than permitted we are ices and reasonable value thereof is all weigh confliсting evidence and reach a de- necessary sustain the verdict. termination thereon contrary to jury’s. directly point I find cases I would affirm the in all re- subject, but in Schultheiss Angeles Los spects. Ry. Corporation, Cal.App.2d (1936) it was said: might

“It also be here observed that

reading transcript of the evidence clearly case shows that the verdict herein could as well have been upon lack negligence

based a total McMULLEN,Appellant Marie Bell respondent part contribu- (Defendant below), tory negligence upon of the ap- pellant through a violation of the ordi- question.

nance in In such a situation McMULLEN, John T. Appellee appellate courts will not look behind the (Plaintiff below). attempt to ascertain the No. 4757. adopted by the theory jury.” Supreme Court of Wyoming. ‍‌​​‌‌​‌​​​​‌‌‌‌‌​‌​‌​‌‌​​‌​‌​​​‌​​​‌‌‌‌‌​‌​‌​​​‌‍In Lo Galbo Columbia Casualty Com- pany, App.Div. 255 N.Y.S. Jan. (1932)judgment had been obtained person insured the defendant insur- company, and it was ance not clear from judgment whether recovery

Case Details

Case Name: Rissler & McMurry Co. v. Atlantic Richfield Co.
Court Name: Wyoming Supreme Court
Date Published: Jan 12, 1977
Citation: 559 P.2d 25
Docket Number: 4586, 4587
Court Abbreviation: Wyo.
AI-generated responses must be verified and are not legal advice.