116 Wis. 287 | Wis. | 1903
The principal question to be determined on this appeal is whether the plaintiff is entitled to a mechanic’s-lien under the circumstances set out in the statement. Plaintiff was a subcontractor, and agreed with the principal contractor to furnish certain shelving and counters or tables-, which were placed in the appellants’ building. His accepted! proposition was to furnish the materials he did furnish for ai
“First, actual physical annexation to the realty; second, application or adaptation to the use or purpose to which the realty is devoted; third, an intention on the part of the person making the annexation to make a permanent accession to the freehold.”
To this may be added the proposition stated in Homestead L. Co. v. Becker, 96 Wis. 206, 71 N. W. 117, that “the matter of intention of the parties is held to be the principal consideration.” This question of intention is chiefly important in contests between the grantee of the freehold and mortgage or lien claimants. In the case at bar the facts are but little in dispute. The appellants, who were owners of the building, and fitting it up for use as a clothing store, contracted for the
• It is suggested that, inasmuch as $500 has been paid on the contract, the court can still support the lien, on the view suggested in North v. La Flesh, 78 Wis. 520, 41 N. W. 633,—that where lienable and nonlienable articles are charged in one account, and the value of the lienable articles can be readily ascertained from the account without a restatement thereof, the right to a lien is not impaired. The trouble here is that there is no evidence presented in the bill of exceptions which enables us to fix the price of the tables or the
But in this connection the further question is raised that the contract between plaintiff and the Markle Company being' entire, and for a lump sum for lienable and nonlienable articles, the plaintiff has waived his lien, and cannot enforce any claim against appellants. This question has never been definitely determined in this state, although some features of it were discussed in North v. La Flesh, supra. The following language from McMaster v. Merrick, 41 Mich. 505, 2 N. W. 895, was quoted:
“It is also settled that one of the plainest cases of waiver is where privileged and unprivileged claims are mingled together in the same dealings, so that the lien is not kept ascertainable without restating and charging the accounts.”
The court said, in substance, that they had no quarrel with this proposition, and that in a similar case would rule the same way. But the North Case was distinguished from the Michigan case on the ground that in the former case the lienable items in the account could be ascertained without restating the account. In a case very similar to the North Case the supreme court of Oregon used this language:
“Had the claim contained a lumping charge of the amount demanded, and there were no means of ascertaining from the notice itself the quantity and value of the lumber used in building the sidewalk, the lien would be defeated, . . . for a court cannot, from oral evidence, separate items for which a lien is given from those for which no lien can be acquired.” Harrisburg L. Co. v. Washburn, 29 Org. 150, 44 Pac. 390.
In a later case the same court said:
*292 “The rule seems to be that when lienable and nonlienable items are included in one contract for a specific sum, or are made the basis of a lumping charge, so that it cannot be perceived from the contract or account what proportion is charge-
“When a demand is filed by a person seeking to avail himself of tbe act giving a meebanic’s lien, services for which be might have bad a lien are combined with other charges for which no lien is given, and tbe whole summed up in one item, so that it is impossible to ascertain from the account filed bow much of tbe gross charge is a lien, tbe party will lose tbe whole benefit of tbe act.”
This case was followed in O’Connor v. C. R. R. Co. 111 Mo. 185, 20 S. W. 16. See Sweem v. A., T. & S. F. R. Co. 85 Mo. App. 95; Schulenburg v. Robison, 5 Mo. App. 561; Johnson v. Barnes & M. B. Co. 23 Mo. App. 546. Another case uses this language:
“It is tbe inseparable blending of items for which tbe law gives no lien, because they are not lienable in their nature, with lienable items, which defeats the entire lien claim, and not the blending of lienable items, some of which remain unproved, or improved to their full extent.” Schulenburg & B. L. Co. v. Strimple, 33 Mo. App. 154.
The supreme court of Maine say that, where a laborer claiming a mechanic’s lien has so intermingled his lien claim with non-lien items that the exact amount for which he is entitled to a lien cannot he ascertained, the whole lien must fail. Baker v. Fessenden, 71 Me. 292. See Kelley v. Kelley, 77 Me. 135. In a case in Illinois the contract with the lien claimants required the other party to pay a given sum for the entire labor agreed to be performed, only part of which was lienable. The court held the contract entire, and that a lien could not be enforced, for the reason that the statute only gave a lien for a part of the work, and the contract, being entire,
“Tbe debt due them was for an entire sum, on tbe completion of tbeir contract. That contract included materials for which there never was any lien, and it was an entire contract.”
For these reasons the court held tbe plaintiffs could not maintain their suit. This case was followed in Graves v. Bemis, 8 Allen, 573, and in Peatman v. Centerville L. H. & P. Co. 105 Iowa, 1, 74 N. W. 689. Other cases along the same line might be cited, but enough have been referred to to show that a lien claimant circumstanced as the plaintiff has shown himself to be is not entitled to a lien. His contract is an entire one, for a feed sum, and cannot be separated or apportioned so as to sustain a lien, even if a new trial were had.
By the Court. — Judgment as against the appellants is reversed, and the cause is remanded, with directions to enter judgment in their favor, dismissing the action.