38 N.Y.S. 345 | N.Y. App. Div. | 1896
The facts upon which this appeal is to be determined are practically without dispute. The action is to foreclose a mechanic’s lien.
. Plaintiff is an architect', and was employed by the defendant company in 1892 to prepare plans for and superintend the construction of a power house at New Brighton, Staten Island. His compensation, provided by agreement, was five per cent on the cost of the structure and expenses. After the preparation of the plans the company requested him to modify them by limiting the construction to one-half of the building. This plaintiff complied with by providing an eighteen-inch Avail running through the center of the proposed structure. The construction of this building Avas then entered upon, and when about half completed the company became
Plaintiff’s compensation as agreed upon ivas five per cent of the cost of the structure. But. by custom among architects, established upon the- trial, when the building is not erected, or if the erection is begun and not completed, the compensation is reduced by one and one-half per cent of the cost -of the part not erected, the compensation of five per cent being made up by a. charge of three and' one-half per cent for preparing plans and one and one-half per cent for supervision. The plaintiff’s expenses were $440.80.
- Plaintiff’s present claim is that lie. was entitled to a lien of $10,288.35, and, if not entitled to the whole gum, for more than the ■court has allowed. His claim is made tip by charging five, per cent on the. amount expended, three and one-lialf per cent on $216,000^ the estimated cost of completion, and expenses. The admitted payment is $3,427.45.
The court below found and stated plaintiff’s account as follows:
For preparing plans for the whole structure........... $11, 550 00
Expenses ..................................440 00
$11, 990 00
Payments........:......,. ........................ . 3, 427 45
$8, 562 55
:One-half .............: ....................'......■. $4, 281 22
One and a half for supervising $115,000 expended.... 1, 725 00 ■
$6,-006 22
which sum he determined Was a lien, and directed a personal judg-naent for the remainder of the claim.
■ The only substantial point in controversy relates- to tlie .extent of the lien. There is no decision in this State, that we are able to find, Where it has been held that an architect who simply prepares, plans and' specifications is embraced within the lien law of the- State: Wherever the question lias arisen the preparation of plans has. been accompanied by superintendence of the construction.
We think the court below was right in holding that it is the part the architect takes during the construction that draws his services within the lien law. This rule, as applied here, limited the lien to the actual superintendence of the part constructed. Before the construction was entered upon plaintiff was informed of the modification proposed, and changed his plans accordingly. When the construction was begun he then knew, and assented thereto, that the building which was to be erected was only one-half of the one originally proposed; that the other half might or might not be erected, as contingencies dictated. And when the work was begun, as well' as when work stopped, it was the common understanding that only the half would then be erected. It cannot, therefore, be
All concurred, except Cullen, J., not sitting.
. Judgment modified as stated in the opinion, with costs to the appellant.