383 Mass. 885 | Mass. | 1981
The plaintiff appealed to the Superior Court the decision of the Plymouth zoning board of appeals (board) affirming the decision of the town building inspector refusing to extend or renew the plaintiffs building permits. G. L. c. 40A, § 17. The judge granted summary judgment for the defendants, and denied summary judgment for the plaintiff.
The building inspector denied Rinaudo’s request for an extension or renewal of the building permits on the ground that Rinaudo had not commenced the work authorized by the permits within six months of their issuance. Pursuant to G. L. c. 40A, § 15, Rinaudo appealed and requested the board to order that the permits be reissued because the work on the project had begun seasonably. See G. L. c. 40A, § 6. The board denied Rinaudo’s appeal. Its decision, upholding the building inspector’s action, was issued 123 days after Rinaudo’s appeal was filed.
Under G. L. c. 40A, § 15, as appearing in St. 1975, c. 808, § 3, “[t]he decision of the board shall be made within seventy-five days after the date of the filing of an appeal .... Failure by the board to act within said seventy-five days shall be deemed to be the grant of the relief . . . sought . . . .” The language of c. 40A, § 15, obligates a board of appeals to act on an appeal within the statutory time period, otherwise the appellant prevails by default. The defendants admit that the seventy-five day time limitation is mandatory. See Casasanta v. Zoning Bd. of Appeals of Milford, 377 Mass. 67, 69-70 (1979). Cf. Cullen v. Building Inspector of N. Attleborough, 353 Mass. 671, 679-680 (1968) (interpreting the time limitation of the prior zoning act as “directory”).
The town claims that the board of appeals lacked jurisdiction to hear Rinaudo’s appeal, because the building inspector’s denial of Rinaudo’s request for an extension of the permits was made pursuant to the State building code, not the zoning act. We disagree. The dispute over the date of the start of construction arose in the context of a determination of whether Rinaudo’s project conformed to the applicable provisions of the
The case is remanded to the Superior Court for reversal of the summary judgment for the defendants, and for entry of judgment for the plaintiff.
So ordered.