16 App. D.C. 150 | D.C. Cir. | 1900
delivered the opinion of the Court:
There is a preliminary question of fact presented in this case respecting the time of the completion of the building mentioned in the proceedings. It is claimed on behalf of the appellant that it was substantially finished and complete at the time at which the last payment was made, September 24, 1896. On behalf of the appellees it is claimed that several things then remained undone which were required by the contract between the builder and the owner, and that the work of construction was not then complete.
Undoubtedly it is matter of common experience that, in the construction of houses which are supposed to have bpen completed, many details of minor importance have often been neglected or overlooked. Of course, strictly speaking, no work can be regarded as finished and complete when the slightest thing required by the contract has been left undone. Until the last nail has been driven, and every key has been fitted, and the minutest detail has been arranged, no work can be said to have been fully completed. And yét here, as elsewhere, by common usage, the maxim “De minimis non curat lex” must apply. It can not be that, because two or three months after a building has been delivered to the owner and accepted by him it is discovered, for example, that a cord has been omitted from a window sash, and the builder is called upon to furnish it, therefore the work of construction is to be regarded as so far incomplete as to keep open or revive the right of filing notices of mechanics’ liens by-those who have had no connection
But we are not required in the present case to be astute in the determination of the condition of this work on the 24th day of September, 1896. For it is very clear to us from the testimony that the building was not then completed according to the contract, and that work of considerable value remained to be done. There was a downspout to be placed on the front of the building at a cost of $14 or $15; there -were iron shelves to be placed in the vault for the books of record of the company, a broken plate-glass window to be replaced, the mosaic work of the floor to be cleaned and rubbed or polished, some slight alteration or improvement in the marble work on the front of the building, some gas fixtures to be hung, and possibly some other minor things to be done. The cost or value of all these things in the aggregate does not appear; but clearly it was not trifling or inconsiderable, and they were all required ■by the contract. Until they were done we can not regard the building as completed in the sense of the mechanics’ lien law só as to affect the rights of the subcontractors in this case. We are of opinion that, for the purposes of this suit, the building was not complete until after the filing of all the notices of lien.
But in the view which we take of this case it is unimportant whether the building was completed or not on September 24, 1896. Under the mechanics’ lien law -the subcontractors had three months after the completion within which to file their notices; and there is no 'pretense
In the case of Herrell v. Donovan, 7 App. D. C. 322, in accordance, as we believe, with the dictates of reason and common justice, and with the tenor of the best reasoned decisions on the subject, we held that the rights of subcontractors under the mechanics’ lien law of this District, while arising under the statute, and not by contract, yet were dependent on the contract between the owner and the builder and on the state of the accounts between them ; and that the subcontractors were bound by all the terms and conditions of that contract. And this decision we have more than once reaffirmed. Such a construction of the mechanics’ lien law we have regarded as necessary to do
It is idle to argue that the owner and the builder had the right to modify their contract, to waive its terms, and to dispense with its prerequisites for the payment of money. Under the circumstances of this case they had no such right, so far as to affect the rights of the subcontractors-The policy of the law forbids any action on their part that would nullify the provisions of the law. It must be conceded that the mechanics’ lien law is a restriction upon the freedom of contract; but it must be sustained, as other legislation of a similar character is sustained, upon the broad ground of public policy. It is true that it makes the owmer of property liable to persons with whom he has not contracted ; but in so doing it does him no wrong. Its practi-cal effect is only to substitute the subcontractor pro tanto as his creditor in the place of the contractor. If he has duly and reasonably guarded his own interests he is never called upon to pay more than he has covenanted to pay in his original contract. He enters upon his contract with the common knowledge that it is impossible for the person with whom he contracts to perform the contract bj' himself alone, and that such person must call in others to his assistance as laborers and subcontractors. It is, therefore, no undue interference with the freedom of contract to require that the rights of those so called in to aid the contractor should be protected. Consequently, when, in pursuance of the policy of the law, and in accordance with its requirements, provision is made for .the protection of the rights of subcontractors, and the subcontractors have entered upon the performance of such portion of the work as is assigned to them upon the faith of the contract, it is no longer competent for the original parties, the owner and the builder, by an arrangement between themselves, even in good faith,
This conclusion appears to us to be self evident; and it appears to us that any other conclusion would nullify and overthrow the law.
Of the good faith of the Insurance Company by its president and secretary there would seem to be no ground whatever for question. According to the testimony — and herein we prefer to believe the secretary of the company rather than the surety on the contractor’s bond who received the money and appropriated it to his own use — the money was paid by the company upon the distinct understanding • that this surety would settle with the subcontractors. This he wholly failed to do; and it would appear that he had no intention to do so when he received the check for the money from the company. His violation of trust is chargeable to the Insurance Company which reposed confidence in him and not to the subcontractors who had no part in that confidence. While it was entirely free from actual fraud upon the subcontractors, and even solicitous that these should be fully paid and satisfied, the Insurance Company can not divest itself of its liability to the subcontractors under the contract and under the law by its having intrusted the money to an agent who did not apply it where it should have been applied, and retained it for claims of his own. The company, however, suffers nothing by its improvident payment, beyond the costs of the litigation which it has caused, since it has its remedy on the bond against the surety to whom it paid the money.
From what we have said it follows, in our opinion, that the decree appealed from was right and just, and that it should be affirmed, with costs. And it is so ordered.