114 N.Y.S. 154 | N.Y. App. Div. | 1908
This is an appeal from a judgment of the Special Term in favor of the plaintiff in a suit to foreclose a mechanic’s lien. The prop
First, it is said that no sum of money was shown to be due in the hands of the Yreeland Company applicable to the plaintiff’s claim, or that at most it appears that such sum did not exceed $1,086.73. The lien was filed for $1,535, and the judgment is for $1,657.80, being that amount with interest. But it is admitted in the appellant’s pleadings that this sum of $1,535 was due from the library corporation to the Yreeland Company, and it was conceded at the trial that nothing had been paid by the Yreeland Company to Commeau on account of the contract between it and him. Moreover, the plaintiff gave proof that his contract was practically identical with that made by the Yreeland Company with Commeau, less some work for hardware and glass supplies, and also that three-quarters of Commean’s contract had been performed when his lien was filed. That which remained of Commeau’s contract was work of erection which Cominean valued at $400 and the hardware work amounting to $114.58. Even allowing these items to Commeau, and conceding that they were outside of the contract between Commeau and the plaintiff, there would still be due to Commeau $1,645.42, which exceeded the lien filed. The value of Commeau’s contract was $2,160, so that if 75 per cent of it had been performed the amount due him was in excess of the lien. The appellant’s contention that a sum not greater than $1,086.73 was due in any event, rests upon its contention that there was evidence that the Yreeland Company had been compelled to complete the work of
Second, it is said that the Vreeland Company should not pay interest or costs. But the lien on the property did not include the costs, which are charged against the defendant personally. As the expenses of the litigation were due mainly to the resistance of the appellant, the court of equity had the right to impose them upon the appellant. (Kenney v. Apgar, 93 N. Y. 549.) And I think that the allowance of interest was proper. In Excelsior Terra Cotta Co. v. Harde (181 N. Y. 11), the court, per Cray, J., say: “ While the old common-law rule has been modified, which required that a demand should be liquidated, or its amount ascertained, before interest' could be allowed, the extent of its modification is that if the amount due is capable of being ascertained by mere computation, the allowance of interest is proper. (See Gray v. Cental R. R. Co. of N. J., 157 N. Y. 483.)”
Third. It is contended that the materials furnished were not for the improvement of the realty, but were chattels not affixed. The contract between the plaintiff and Commeau called for double cases with shelves, exhibition cases, partition base, cupboards, a platform, lockers, dressers, bulletin boards and supply cases. It was required that the materials used in the construction of the various cases, lockers, railing, bulletin boards, etc., shall be of the same wood as the finish of the rooms in which they are installed. There is evidence that the shelves were measured with reference to the rooms and constructed to fit into the spaces, with the exception of one platform expressly made portable; these various articles were fastened to the realty by holdfasts, nails, screws, angle irons and the like. Kellogg, the defendant’s architect, testified that to remove the cases would do material injury to them and the wall; that the wall was not finished behind the cases. The question is whether in fact and intention the work and materials have become part and
Sixth. It is said that the architect’s certificate was not shown to have been given to the Vreeland Company, and hence the plaintiff failed in his proof. In Seeman v. Biemann (108 Wis. 379) the court say: “ A further claim is made that the liens were not enforceable since nothing was due the principal contractor except upon architect’s certificates of satisfactory performance of the conditions of the contract, and the evidence does not show that such certificates were given or were produced upon the trial. We are unable to see how that is material. A subcontractor’s lien is not dependent under our statutes upon whether there is anything due the principal contractor. If in any event a claim would be lien able under the principal contract in favor of the contractor, it is lienable in favor of his subcontractor, and the right in that regard cannot be impaired by any default of the principal contractor. It would be a strange doctrine under our lien statutes to hold that the neglect of the principal contractor to acquire the right to recover for constructing a building where it has actually been constructed and is in existence as an improvement upon the proprietor’s land, will defeat the right of a subcontractor to look to the property for the payment of his claim.”
The judgment must be affirmed, with costs.
Hooker, Gaynor, Rich and Miller, JJ., concurred.
Judgment affirmed, with costs.