33 Pa. Super. 321 | Pa. Super. Ct. | 1907
Opinion by
The plaintiff entered into a contract to perform the work and to furnish part of the material used in the construction of an improvement to the water system of the defendant. The plan involved the excavation of a tunnel about 1,000 feet in length, a ditch in connection therewith and the placing in the ditch and tunnel of pipes to be used by the company. The specifications furnished to the plaintiff set forth in detail the extent and character of the work to be done, the manner of its execution and the time within which it was to be completed. The contract provided that a delay in the completion of the work beyond the time limited would subject the plaintiff to the forfeiture of |5.00 a day during such delay as liquidated damages. The plaintiff alleged performance according to the contract except as to the time of the completion of the work, and for that delay a flood, strikes of laborers and the permission of the defendant were presented as excuses. Two payments of $800 and $500, respectively, were acknowledged and this action was brought to recover the remainder. The defense set up was that the plaintiff had failed in material particulars to perform the work according to the plans; that the tunnel was not as wide or as high as required and was not timbered in accordance with the specifications; that the work was abandoned by the plaintiff before it was completed; that at one point the terra cotta pipe laid in the tunnel was broken; that the earth
The provision in the contract for the completion of the work at the time stipulated provides a redress to the defendant in case of the plaintiff’s failure and does not relieve the defendant
We do not find sufficient warrant in the record to sustain the assignments of error. They are, therefore, overruled and the judgment affirmed.