The facts in this controversy are not materially in dispute. In June, 1953, plaintiffs became the owners of a tract of land in defendant city, comprising approximately 89 acres. It is claimed that the consideration for the purchase was $440,000 and that the property was acquired with the purpose in mind of platting it. It was divided into 2 subdivisions and plats thereof were prepared by engineers employed by the owners for that purpose. The proposed plats were submitted to the common council of the city of East Detroit for approval, and referred to the city engineer. Some question was raised with reference to plans for disposal of surface waters, but eventually these problems were solved and defendants raised no further objections.
It is the claim of plaintiffs in this proceeding that they were advised by the city engineer and, likewise, by the city manager that the plats would not be approved unless 1 lot in each subdivision was conveyed to the city, the claim being that such lots were desired for playgrounds for young children. Some discussion occurred from time to time concerning the matter, plaintiff Bankle claiming that he objected to executing the conveyances on the ground that the city was without authority to require them as a condition prerequisite to approval of *390 the plats. He did not take the matter up directly with the common council, but relied on the statements made to him by the city’s representatives, the manager and the engineer. Conveyances as requested were finally executed and delivered, and the plats were approved. Plaintiffs asked that each deed contain a reverter clause providing in substance that if the lots were not used for playground purposes the grantors would be entitled to reconveyances. This was refused. The record indicates that the conveyances were absolute in form.
By agreement between the parties, plaintiffs deposited in escrow with the defendant city a sum of money estimated as necessary to cover the cost of improvements in the property, such improvements to be made pursuant to contracts let by defendant city. Among such contracts was one for the paving of a certain street referred to in the record as Boulder avenue. The contract as made by the city provided for a 6-inch pavement which, during the process of construction, was increased over a certain section of said street to 8 inches. Plaintiffs claimed that the alteration in the construction was unauthorized under pertinent provisions of the municipal charter, and that they were improperly charged with the additional cost of the paving because of the alteration made at the insistence of the city engineer, and without their knowledge or acquiescence. Settlement was made with the contractor on the basis of the work actually done and materials furnished, the cost thereof being charged against the deposit made by plaintiffs to cover improvements. The total added cost charged against them because of the alteration in question is claimed to have been the sum of $6,680.80.
Plaintiffs instituted the present suit by bill of complaint filed March 4, 1955. In their pleading they alleged that defendants were without authority *391 to insist on the conveyances of the lots in question as a condition prerequisite to approval of the plats, that plaintiffs were faced with the necessity of obtaining such approval in order to proceed with their plans and protect their investment, and that, in fact, the deeds were delivered as the result of economic duress. It was further claimed that plaintiffs were entitled to an accounting with the city, that the increased cost of the pavement on Boulder avenue, due to the alteration in construction plans, should not have been charged against them, and that they are entitled to the allowance of such overcharge. Defendants by their pleadings denied the right to the relief sought, claiming in substance that the city was within its rights in demanding deeds to the lots, that the increase in the thickness of the pavement on Boulder avenue was necessary and properly authorized, and that plaintiffs may not question the dealings between the contractor and the city. The trial court determined the issues in favor of defendants and denied relief except as' to the claimed right to an accounting. Plaintiffs have appealed from the decree entered.
In the preparation and approval of the plats of the property the parties were subject to the provisions of PA 1929, No 172 * , as amended prior to the dealings in question here. Section 19 of the act (CL 1948, § 560.19 [Stat Ann 1953 Rev § 26.449]) gave to the council of defendant city the right to examine for accuracy the plats submitted and to reject a plat found materially in error. The succeeding section likewise invested the governing body of the city with the power to determine whether the land covered by the plats was suitable for platting purposes. It was expressly authorized to require that streets and private roads be improved *392 and properly drained, and that all highways, streets and alleys conform to the general plan, if any, that may have been adopted for the city.
It does not appear from the record before ns that the city of East Detroit prior to the occurrence of the matters in issue here had adopted an ordinance, or ordinances, with reference to the submission and approval of plats. Neither does it appear that the plaintiffs were required to dedicate the lots for use by the public for park or playground purposes. The pleadings and the proofs indicate that the deeds were in the form of ordinary conveyances to the city. It further appears that said lots have not, in fact, been used for playgrounds or that it is intended to so use them in the future. It is a fair inference that the city has seriously considered disposing of such lots for the reason that small playgrounds are not deemed feasible. As noted, the requirement imposed on plaintiffs with reference to deeding the lots to the city did not involve indicating on the plats that they were dedicated to any public use.
; The conclusion may not be avoided that the plat act of 1929, above cited, did not empower the defendant city to require, as a condition prerequisite to the approval of plaintiffs’ plats, that the lots in question be deeded to the city. The fact that the plats were approved must be taken to indicate that no statutory ground was discovered for rejecting them. Such being the case, plaintiffs were entitled to favorable action in accordance with their application. In
Campau
v.
Board of Wayne County Auditors,
Counsel for defendants call attention to
Ridgefield Land Co.
v.
City of Detroit,
Are plaintiffs entitled to a reconveyance of the lots in dispute? As before noted, the prayer for relief in this respect is based on the theory that plaintiffs were subjected to economic duress, that in order to carry out the plans that they had made with reference to their property the approval of the plats submitted to the common council was necessary, and that resort to legal means to enforce ap
*394
proval meant delay and serious loss. It is claimed that, because of such pressure, the lots were deeded to the city, and that equity, in view of the facts established by the proofs, may properly grant relief. Similar questions have arisen in prior decisions of this Court. In
Vyne
v.
Glenn,
“The defendant informed the plaintiff that he had stopped the payment of certain moneys due the latter from third parties, well knowing plaintiff’s circumstances at the time, and that his failure to get the moneys so due him would result in his financial ruin, and thus compel the plaintiff to settle with the defendant in order that the stoppage might be removed. It is idle to say that such a settlement was free and voluntary, and that it should be sustained. To say that the plaintiff had a legal remedy if a wrong had been done him, or that the commencement of garnishee proceedings would not vitiate a settlement thereafter made between the debtor and creditor, may be true generally; but where the wrong done, as in this case, was for the evident purpose of forcing a settlement not in accordance with the legal rights of the parties, and where the delays incident to litigation would - but -work • the • ru-in -which the- *395 plaintiff dreaded, — to hold that because he had a legal remedy for the wrong, and did not avail himself thereof, would not meet the difficulties in a case like the present. The choice offered him was financial ruin or immediate settlement. If this was not obtaining a settlement under duress, it would be difficult to conceive what would be.”
Analogous principles were involved in
City of Saginaw
v.
Consumers Power Co.,
In
Detroit Club
v.
State of Michigan,
In the instant ease the defendant demanded and received from plaintiffs property to which the municipality was not entitled. Under the applicable statute there was no authority to impose as a condition prerequisite to the approval of the plats that the lots in question be deeded to the city. The purpose for which it was then intended to use said lots does not alter the situation. Unquestionably the city had the power to establish public playgrounds but it could not demand that plaintiffs donate the land therefor. In complying with such demand plaintiffs acted under compulsion and are entitled to a reconveyance of the lots in question.
Plaintiffs are also entitled to an accounting with reference to the money deposited in escrow to cover the cost of improvements within the subdivisions. This brings us to a consideration of the claim of the plaintiffs with reference to the alteration of the contract for the paving of a certain portion of Boulder avenue within the platted property. That the contract as first made between the city and the paving contractor contemplated a pavement 6 inches in thickness is not disputed. Neither is it questioned that the thickness of the pavement over a section of the street was increased to 8 inches on the recommendation of the city engineer. It was the claim of the defendant city on the trial of the case that such change was deemed expedient because of unsatisfactory condition of the foundation with reference to drainage, and also because the prospects of heavy traffic over such street.
It is not questioned that the contract in the first instance might have been let for an 8-inch pavement, nor is it questioned that with the affirmative consent and approval of the common council the contract might subsequently have been modified to provide for the change from 6 to 8 inches in thick *397 ness of pavement. Settlement with the contractor was made on the basis of the work actually done, such settlement involving the payment of $6,680.80 over and above the probable cost had the original plan been followed. In agreeing to the settlement with the contractor it seems apparent that the common council of the city in effect ratified the modification in the contract as recommended by the city engineer. It is not claimed that the action was taken in bad faith, plaintiffs’ contention being based on the theory that the approval of the council to the change in the construction should have been obtained before the work was actually done. The situation presented seems to be the not unusual one of an action that might have been, and perhaps should have been, authorized in advance, being subsequently ratified by the council.
In
Alsmeier
v.
Adams,
62 Ind App 219 (
A decree will enter in this Court requiring that defendant municipality execute and deliver to plaintiffs proper conveyances of the lots in question within 30 days from and after the entering of said decree, and otherwise affirming the decree of the circuit court. Neither party having fully prevailed, no costs are allowed.
Notes
CL 1948, § 560.1 et seq., as amended (Stat Ann 1953 Bey § 26.431. et seq., as amended). . . ...
