68 F. 105 | 6th Cir. | 1895
after stating the facts as above, delivered the opinion of the court.
1. One of the principal questions presented by the appeal of the Richmond & Irvine Construction Company concerns the relation which it bears to the appellee the Richmond, Mcholasville, Irvine & Beattyville Railroad Company. Its contention is that it is properly to be considered as a contractor with the railroad company, and it assigns as error that the circuit court did not so hold, instead of construing it to be a subcontractor under the Ohio Valley Improvement & Contract Company. As will appear more fully by the opinion of the court heretofore filed in the case of Central Trust Co. v. Richmond, N., I. & B. R. Co., 68 Fed. 90, the Ohio Valley Improvement & Contract Company had contracted with the said railroad company to construct and equip the entire line of railroad of the said railroad company. The Ohio Valley Improvement & Contract Company, hereafter designated as the “Contract Company,” after doing the larger part of the work and furnishing the greater part of the materials for that purpose, became financially embarrassed, and unable to complete its contract without assistance. It had agreed to construct and equip the said line of railroad for the bonds and stocks of the railroad company. Thus all the assets of the railroad company had either been paid or pledged to it, and when the latter became unable to go on with the work the railroad company was in no condition, financially, to complete the construction itself. In this situation of affairs the contract company entered into an agreement with the appellant the Richmond & Irvine Construction Company, hereafter designated the “Construction Company,” that the latter should complete the work of construction between Richmond and Irvine, Ky., and furnish all necessary materials. It also agreed to purchase
“And said contract company agrees to pay tlie said construction company for said work, materials, and such claims as may he so purchased, the sum $400,000, to he paid as follows: In the new 5 per cent, first mortgage bonds of said railroad company the sum of $200,000 as soon as the bonds are printed and ready for delivery, and the sum of $200,000 in money due and payable a-t the expiration of thirty days after the track of said railroad is laid and completed as aforesaid from Richmond, Ivy., to the Kentucky river, opposite Irvine, Ivy.; but, should said sum not be paid at maturity, the same shall bear no interest until January 1, 1892.”
It was signed only by the contract company and the construction company. The contention of appellants that this contract is to be construed as a contract of the railroad company, and its relation as that of an original contractor, is based upon two propositions:
First. It contends that under the evidence in this case the contract company was, in legal effect, the railroad company, and that engagements made by it were, in legal effect, engagements made by the railroad .company. In support of this, appellant has endeavored to show that the stockholders in each corporation were the same, and that the contract company dominated and controlled the railroad company. The contract company was a legal corporation, wholly distinct and separate from the railroad company. The fact that the stockholders in each may have been the same persons does not operate to destroy the legal identity of either corporation. Neither does the’fact-that the one corporation exercised a controlling influence over the other through the ownership of its stock or through the identity of stockholders, operate to make either the agent of the other, or to merge the two corporations into one. There is no pretense of- any fraudulent concealment of the interest of the one corporation in the other, or of the fact that the persons controlling the one corporation likewise controlled the other. The officers and agents of the construction company were fully aware of the relations Avhieli existed between the two companies. They also knew that the contract company was under obligation to build and equip the railroad for the railroad company. With this knowledge of the relations of each corporation to the other, it deliberately entered into a contract with the contract company to do work for and under the contract company, as a subcontractor. The facts of this case are very much the facts which appeared in the case of Trust Co. v. Bridges, 6 C. C. A. 539, 57 Fed. 753. In that case the court dis-
Second. Appellant also rests its contention upon the legal effect of the action of the board of directors of the railroad company contained in certain resolutions found upon the minutes of the board, as follows:
"Whereas. the Richmond, Xicholasville, Irvine & BeuUyvillo Railroad Company, hereinafter designated tlio -Railroad Company,’ is informed l>y tlio Ohio Valley Improvement & Contract Company, hereinafter designated the 'Improvement Company,’ that it desires to make a subcontract with the Richmond & Irvine Construction Company, hereinafter designated the •Construction Company,’ substantially as follows, to wit: First. That said construction company will finish the work of construction necessary to be done upon the railroad of the railroad company from Versailles to Irvine, according to the construction contract of October 11, 1888, which, it is estimated, will require something less than $110,000. Second. That said construction company shall purchase and take up certain lien claims of subcontractors, now existing and unpaid, for work heretofore done and material furnished on the line of the railroad, the lien claims to he purchased, added to the cost of the work and materials, to aggregate $200,000. Third. That said improvement company will pay to said construction company. in money, the amount so paid out both in construction and in the. purchase of subcontractor's lien claims, amounting in the aggregate to $200,000. and will pay to the said construction company, as an additional consideration, in 3 per cent, bonds of this company, an amount equal, a.t par value, to the amount of money to he so paid by the improvement company to the construction company. Now, be it resolved, that the Richmond, Nicholasville, Irvine & Beattyville Railroad Company does hereby consent to the subletting by said improvement company to said construction company upon substantially the terms above mentioned, and consents, so far as this company can lawfully do so, that said construction company shall have a contractor’s lien upon the railroad for all work done and material furnished and claims purchased as above mentioned.”
These' resolutions do not operate t.o make the railroad company a principal contractor, within the meaning of the Kentucky lien act, being sections 2492-2495. St. Ky. 1894, by Barbour and Carroll, and which have been fully set out in the opinion of this court filed in the principal cuse. A contractor, within the meaning of that act, is one who does work or furnishes material for the owner, and upon a contract with the owner for the payment of the contract price. A subcontractor,within the meaning of that acl,isonewho con tract sunder and with the principal contractor. Kow, nothing in ihese resolutions obligated i he railroad company to pay the construction company for the work and materials which it was to do and furnish, and for (he lien claims which it was io purchase and hold. The railroad company was obligated to (lie contract company to the extent of (he contract; ¡nice mentioned in the contract between them. The labor and materials which fue construction company undertook to furnish are a pari of the same labor and material» which tlie contract company had agreed to .furnish, and for which the railroad company was bound io pay. There is nothing in ihese resolutions which indicates that the railroad company intended to personally assume liability to the construction company. The language that “si consents, so far as this company can lawfully do so, that said construction company
2. The nineteenth assignment of error filed by the construction company presents a question concerning the application of a payment of part of the contract price in railroad bonds, made by the contract company to the construction company. The rule in regard to partial payments made by the contract company to its subcontractors, and the effect of such payments upon the lien of such subcontractors, is fully stated and explained in the opinion filed upon the questions involved by the appeal of the Central Trust Company, and need not be here repeated. That rule was applied to all payments made to subcontractors, except only the construction company. The learned district judge who heard this case in the circuit court deemed the contract between the contract company and the construction company so peculiar as to justify a departure from the general rule adopted with reference to partial 'payments made to other subcontractors, by the contract company. The peculiarity of that contract consisted, not only in the great variety of things which the construction company undertook to do, but in the odd way in which the price wms to be fixed which was to be paid for all its undertakings. The construction company was a corporation organized for the express purpose of helping the contract company out of its difficulties. It obligated itself to do all that the contract company had contracted to do, and had not done, on that part of the road between Richmond and Irvine, Ky. This involved the acquirement of rights of way, grading, track laying, bridge and depot building, the furnishing of all necessary materials, including steel rails, etc. The contract company had; as more fully appears in the principal opinion, obligated itself to pay the interest upon the bonds of the railroad company during construction, and for one year thereafter. It owed a great deal of money to subcontractors for work finished and materials furnished. Its obligation to pay matured coupons, and to pay subcontractors having liens, had to be provided for, and so the construction company undertook to buy and hold matured coupons not exceeding $12,000 in par value, and to purchase and hold for its benefit subcontractors’ lien claims to be designated by the contract company. The total capital stock of the construction company was fixed at $200,000. Of this capital it undertook to use $140,000 in expenditures on the work of construction. The expendí-
“And said contract company agrees to pay the said construction company for said work, materials, and such claims as may he so purchased, the sum of 8400,000, to he paid as follows: In the new 5 per cent, first mortgage bonds of said railroad company, the sum of $200,000 as soon as the bonds are printed and ready for delivery, and tile sum of 8200,000 in money due and payable at tlie expiration of thirty days after the track of said railroad is laid and completed as aforesaid from Richmond, Ivy., to the Kentucky river, opposite Irvine, Ky., but should said sum not be paid at maturity, the same shall bear no interest until January 1, 1892.”
Subsequently a modification of the contract was agreed upon, as follows:
“The agreement attached hereto between the undersigned, bearing date January -, 1891, was made with the expectation and understanding that the paid-up capital stock of the Richmond & Irvine Construction Company should equal the sum of $200,000 in money which was to be expended in the prosecution of the work of constructing the R., N., I. & B. R. R. and the purchase of the lien claims mentioned in said contract. Now, this writing witnesseth, that if the said paid-up capital stock should fall short of the said $200,000, then the Richmond & Irvine Construction Company shall only be paid under* said contract an amount of bonds equal to said i>aid-up capital stock, and a like amount in money. In testimony whereof, wo have hereunto subscribed our names this, the 7th day of February, 1891.”
The capital expended did in fact fall short of that anticipated, and ih.e bond payment made by the contract company was correspondingly reduced. This agreement comes at last to this: that in place; of agreeing, in the first instance, upon a definite price to be paid for what the construction company agreed to do and expend, the parties to that contract agreed that the price to be paid should be the actual amount of the cash expenditures plus the value of an equal amount of securities, which, as shown by the master’s report, were worth 40 per cent, of their value. This arrangement settled definitely the profit allowed the construction company upon its entire outlay, provided the whole of the price should be paid or collectible. The contract may have been a hard bargain, as between the contracting corporations, and this view, in part, may account for the exceptional rule enforced in regard to the application of the partial payment so as to reduce the amount of its lienable claim, as well as the amount of its pro rata enforceable against the property of the railroad company. On the otliei hand, it is to be remembered, in mitigation, that this profit was more apparent than real. The market value of the
3. The same appellant assigns as error that the court disalloxved interest on its pro rata, except from the date of decree. ' We think this xvas error. The agreement between the contract company and the construction company provided that the actual cost of work and labor and expenditures for material, etc., made by the construction company for the contract company should be “payable at the expiration of thirty days after the track of said railroad is laid and completed as aforesaid from Richmond, Ky., to the Kentucky river, opposite Irvine, Ky.; and, should said sum not be paid at maturity, the
i. The contract between the construction company and the contract company provided for the doing of many things, and she expenditures of money on many accounts, which the circuit court: hold were not lienable 'matters. All these expenditures made by the construction company, and which were excluded from the lienable claim of that company, were made matters of exception to the report of tin special master, and the ruling of the court thereon ha.s been assigned as error. We are of opinion that the court’s ruling was correct, with respect to each and all of these matters thus excluded from the lienable claim. Money paid for purchase of rights of way is neither work nor material, within the meaning of the lien act. Neither is money expended in the payment of the salaries of the president of the construction company and its other general officers, although properly chargeable to the contract company, as between it and the construction company. Nor were the expenses of the construction company for stationery, and like office material, lienable claims. The construction company paid |2,34(5.29 to a trust-company to secure its guaranty upon a contract made by the construction company for (he purchase of steel rails. Appellant insists (hat this expenditure constitutes a part of the actual cost of the steel rails which it had contracted to- furnish for (he completion of the road. We think that (hat expenditure was one resulting alone from its own want of sufficient cash capital, or its own insufficient credit, and that no such expenditure was within the meaning or spirit of the contract between it and the contract company. If its own capital or credit had been sufficient, no such expense need hare been incurred; and (he contract makes no provision, directly or indirectly. for compensating the construction company for expenses directly due to its own insufficient capital or credit. The4 construction company paid out some .$10,000 for legal expenses incurred in purchasing or condemning rights of way. The court held such expenditures were not lienable. There was no error in this, for t.wo reasons: First, because the furnishing of rights of way is not '¡he furnishing of "materials," within the lien act: second, legal service rendered by counsel is not “labor.” within (he meaning of (he lien si atufe.
5. Each of the appellants has filed numerous assignments of error touching the improper exclusion of items of expenditure which it. is now insisted should have been included in ascertaining the total original contract price entitled to the statutory lien, and to be prorated among all who contributed to the proper work of construction. It is sufficient to say that we have given careful attention io the various assignments and the evidence relating to them upon which this class of objections to the decree have been presented to (his court, and we find that none of the assigu-
6. The decree allowed none of the subcontractors interest except from the date of the final decree. This has been assigned as error. We have already passed upon this matter, so far as the construction company is interested. The disallowance of interest seems to have been based upon the assumption'that there was no contract between the contract company and the subcontractors for the payment of interest, and that the allowance pi interest upon such claims, in the absence of a local statute, was within the sound discretion of the court. The court seemed also to attach importance to the fact that the litigation which has resulted in delay was not vexatious, but necessary for the proper marshaling of-liens. The question divides itself: First, is interest properly allowable as between the contract company and its subcontractors? Second, is there any reason which should move the conscience of a chancellor to disallow interest because of its indirect effect upon the rights of another class of creditors? In general terms, it may be stated that the contracts between the contract company and its subcontractors provided for payments of a proportionate part of the contract price on monthly estimates as the work progressed, and for payment of all balances due on the completion of the work. There seems never to have been any serious controversy as to these balances due to subcontractors, except in regard to a claim for so-called extra work and materials asserted by appellant Walker. Their claims were not paid because the contract company was unable to pay them, and not because it disputed its liability. As between the contract company and the subcontractors, there can be no serious contention but that interest
“If the deht ought to he paid at a particular time, and is not, owing to the delimit of the debtor, the creditor is entitled to interest from that time, by way of compensation for the delay in payment. And if the account be stated, as the evidence went to show was the case here, interest begins to run at once.-’
This rule announced by the supreme court of the United Slates seems to be in entire accord with the latest utterances of the supreme court of the stale of Kentucky. In the case of Henderson Ootton Manuf’g Oo. v. Lowell Machine Shops, 86 Ky. 668, 7 S. W. 142, the court said, concerning the allowance of interest upon an account for machinery sold and payable at; a definite time by agreement of the parties:
“The true ground upon which to put the allowance of interest is the fault ot the party who is to pay the debt. If he has made default of payment, then, ex aequo et bono, he should reimburse the «'editor for keeping him out of the use of his money. He should render an equivalent for the use of wliat. is not his own. If there be a specified time for payment, and a failure to then pay, or a demand of payment of a liquidated claim, and default, then the debt should, as a matter of law, bear interest from the time of such failure. This is the current of authority, and it is supported by both right and reason.”
Neither is there anything in the case of Redfield v. Iron Co., 110 U. S. 174, 3 Sup. Ct. 570, or Thomas v. Car Co., 149 U. S. 116, 13 Sup. Ct. 824, which conflicts with the doctrine as stated in Young v. Godbe and Henderson Cotton Manuf'g Co. v. Lowell Machine Shops, cited above. In Redfield v. Iron Co., Justice Matthews, in discussing ihis question, said, for the court:
“Interest is given on money demands as damages for delay in payment, being just compensation to the plaintiff for a default on the part of his debtor. Where it is reserved expressly in the contract, or is implied by the nature of the promise, it becomes part of the debt, and is recoverable as of right; but, when it is given as damages, it is often matter of discretion, in cases like the present, of recoveries for excessive duties paid under protest, it was held in Erskine v. Van Arsdale, 15 Wall. 75, that the jury might add interest, the plaintiff ordinarily being entitled to it from the time of the illegal exaction. But where interest is recoverable, not as part of the contract, but by way of damages, if the plaintiff has been guilty of laches in unreasonably delaying the prosecution of his claim, it may be properly withheld. Bann v. Dalzell, 3 Car. & P. 376; Newell v. Keith, 11 Vt. 214; Express Co. v. Milton, 11 Bush, 49.”
In Thomas v. Car Co., heretofore cited, there seems to have been no definite time agreed upon as to payment, and interest was disallowed because, as the court said, the delay in payment “was occasioned by resisting demands made by the car company, which the result of the litigation shows were excessive, if not extortionate.” The contract company was in default, and interest is properly allowable from the time it failed to pay according to its promise, by way of compensation for the delay in payment. Neither is there anything in the fact that the railroad company is insolvent, nor in the fact that the allowance of interest will diminish the fund to which
“They were liens superior to the bonds. They should hear interest, or, wliat is the same thing, the fund from which they are payable should hear interest until paid. The security and priority of the lien attach as well to interest as to principal. The aggregate of the subcontractors’ claims exceeds by at least fifty per cent, the fund due Eager, even with interest, so that in the distribution no interest need be calculated on the claims after December 15, for the share applicable to each will not be varied by adding interest to all claims for tlie same period from December 15, 1800. to tlie date of the decree. But the limit in the aggregate of the liens fixed on tlie property must be increased by interest until satisfaction. This is not a case where the distribution is to be made pro rata between the' lienholders and tlie bondholders, in which case, of course, interest is not to be calculated upon tlie claims after tne time of tlie sequestration of tlie property for sale and distribution, so long as the, claim cannot be paid in full. Bank v. Armstrong, 16 U. S. App. 465, 8 C. C. A. 155, 59 Fed. 372. In the distribution of the proceeds of a common security between liens of different priorities, we know of no principle by which interest can be stopped on the amount of the superior lien until its satisfaction. As between the bondholders and the lienholders, the lienholders are entitled to interest to the day of payment, and the decree should therefore include interest on tlie amount herein found due Eager from December 15, 1890, until it shall be entered.”
One error assigned by appellant Walker and otlmiw needs to be especially noticed. J. W. Walker liad a contract with tlie contract company for .tlie erection of four bridges, for which lie was to receive the sum of $140,200. One of these bridges was known as the
“Tlie balance ol' tlie contract price for each structure, including' tlie ten per cent, reserved on the monthly estimates, is to become due aud payable as each structure is completed and inspected and approved, according to both specifications attached hereto. As payments are made upon the material, the title to the same is to become vested pro rata in the party of the second part"
The proof fails 1m allow that the material was in fact paid for as delivered, to any considerable extent. But we are of opinion. even if the material had been in part paid for, so that the íitle luid voided in proportion to the payments in tlie contract company, that under the circumstances of this case the appellant ought not to bo allowed to recover (he value of this material, necessitated hy an accident for which his own employes were manifestly responsible. The most he could claim, under any consideration, would be that each of the contracting parlies should share the loss in the pioportion that they held title to 1ho material destroyed. The burden vuis certainly put upon appellant to establish the ex lorn of his claim. This lit1 has not done. But upon (he ground first indicated, to wit. that the accident was tlie result of the negligence of the bridge contractor, and was not contributed to or brought about by any fault or neglect of (he contract company whatever. She loss ought, therefore, to fall upon the party responsible for She accident.
The appeals of G. W. Gourley, W. B. Smith, C. F. & A. R. Burnan, J. W. Caperton, and John Bennett are from decrees disallowing
J. E. Dougherty appeals because a claim for $454.10. for services as a civil engineer in the construction of the railroad was disallowed. The ground upon which it was disallowed was that his services were rendered within the counties of Jessamine and Woodford, and the claim filed in Jessamine county alone. The Kentucky act giving a lien for labor required that the verified statement claiming a lien should be filed in the county clerk’s office of “each county in which the labor was performed.” The only evidence concerning the locality in which Dougherty did his work is that during September, October, and November, 1890, “Dougherty’s work was principally in Jessamine county, and his headquarters were in that county,” and that “he did a small amount of work during that time in Woodford.” The itemized statement of his account filed in Jessamine county was as follows:
Ohio Valley Improvement & Contract Oo. to J. E. Dougherty, Dr.
1890. Address.
Por services and expenses as resident engineer, as follows:
Salary for month of September . $100 00
“ “ “ October . 100 00
“ “ “ November . 100 00
“ “ “ December . 125 00
“ “ “ August . 13 20
“ “ September . 11 90
“ “ “ October .■. 40
“ “ “ November . 2 10
“ “ “ December . 1 50
$454 10
It is clear that the greater part of his work during three months was done in Jessamine county, where his lien was filed. It will not be unjust if it be assumed that his salary of $300 during those months was two-thirds earned by his work in Jessamine, and that a proportionate part of his expenses for the same time attached to his work in Jessamine. The decree, as to his claim, will be so modified as to allow him $208.60, as the amount of his lien claim, upon which he will receive his pro rata as other lienors, with interest.
The claim of Dickason & Crawford was uncontested, except to the extent that it embraced railroad ties cut under a contract with the contract company, but never delivered to the railroad company, or on its premises. The contract company notified them that they would not accept the ties, and that they need not deliver them. The ties had been cut under and in accordance with a contract prior to such notice. There being no other market for them, they were
A considerable number of other errors have been assigned by one or other of the appellants. To'notice each would extend this opinion to an undue length. They have all been examined, and none of them are regarded as -pointing out any substantial error. The decrees appealed from will therefore be affirmed, except as herein expressly modified. Costs of appeal will be paid out of the fund arising from sale of tiie railroad.