249 N.W. 501 | Mich. | 1933
Plaintiff, when sued in the court of common pleas for the city of Detroit, for payments due under a land contract, entered his appearance in the suit, pleaded the general issue, then filed the bill herein to have rescission of the contract for alleged fraud, obtained an order requiring defendant to show cause why an injunction should not issue to restrain the proceeding at law, was granted an injunction upon condition of filing a bond within a specified time, failed to file the bond, let the case in the court of common pleas go to judgment, and took no appeal. The court held the judgment at law res judicata and dismissed the bill. Plaintiff reviews by appeal, claiming that his plea in the court of common pleas did not present the issue of fraud set up in his bill of complaint, and, therefore, there was no adjudication of the fraud now claimed.
The test by which plaintiff is bound is what he could and should have pleaded in the common pleas court. Plaintiff therein could not recover without a valid contract and an existing obligation upon the part of the vendee therein to pay instalments thereon. Plaintiff herein cites McHugh v. TrinityBuilding Co.,
The case at bar falls within the holding in Bassett v.Trinity Building Co.,
In the case at bar the equity court tendered restraint of the action at law if a bond was given, and plaintiff not only failed to give the bond, but also failed to defend against the action upon the contract. Plaintiff had remedy open and offered, but failed to avail himself thereof. He cannot now maintain the bill for rescission.
The decree in the circuit court is affirmed, with costs to defendant.
McDONALD, C.J., and CLARK, POTTER, SHARPE, NORTH, FEAD, and BUTZEL, JJ., concurred.