182 So. 101 | Miss. | 1938
An affidavit was filed with the plea by the business manager and financial secretary of the appellee, in which it is stated that the construction of the said nurses' home, including the plumbing and heating work in connection therewith, was entirely completed on the 27th day of January, 1938, and that the home has now been occupied and in use since the 31st day of January, 1938; that the check of the appellant in connection with *480 the bid has been returned to him by registered United States mail.
There was no denial of the facts set forth in the affidavit in support of the plea in bar, and the facts present sufficient matter to bar the appeal, as the court would not award a contract, or compel the performance thereof, the work in connection therewith being already completed; but the appellant would be remitted to a suit for damages, if he is entitled to damages in connection therewith.
The suggestion of error is therefore overruled.
Overruled.