OPINION BY
Thomas F. Ribarchak d/b/a Fisher Associates (Fisher) appeals from the June 17, 2011, order of the Court of Common Pleas of Washington County (trial court), which denied Fisher’s motion for partial summary judgment and granted the motion for summary judgment of the Municipal Authority of the City of Monongahela (Authority), Galway Bay Corporation (Gal-way) and Chester Engineers, Inc. (Chester) (collectively, Appellees). 1 We affirm.
The Authority, by and through Chester, solicited bids from various contractors for a renovation project for its sewage treatment plant. Galway submitted a bid for the project and included Fisher as a subcontractor. The Authority awarded Gal-way the contract on November 16, 2000, pending review of the solicitor, engineer and general manager. On April 16, 2001, more than thirty days after Galway’s bid was accepted, Galway requested that the Authority consent to the substitution of Kiski Valley Systems (Kiski) as a subcontractor in place of Fisher. According to the contract drawn up in October 2000, between the Authority and Galway, “[n]o substitutions will be accepted after 30 days from the Contract award date.” (Contract, 10/00, ¶ D.5, at D-3; R.R. at 19a.) 2 However, the Authority agreed to Gal-way’s substitution of Kiski for Fisher.
On October 15, 2001, Fisher filed an action against Appellees claiming breach of contract and negligence. Fisher claimed that it had a valid contract with Galway and the Authority because Galway included Fisher in its general contractor’s bid to the Authority and the Authority accepted Galway’s bid, which listed Fisher as a subcontractor. Subsequently, Fisher and Ap-
Fisher first contends that the trial court erred in failing to grant it partial summary judgment as to liability because Appellees breached the contract they had with Fisher. We disagree.
In order to form a contract, there must be an offer, acceptance, and consideration or a mutual meeting of the minds.
Yarnall v. Almy,
Here, Fisher made Galway an “offer” by submitting its bid proposal to Galway to do the instrumentation work for the Authority’s sewage treatment plant project. The terms of the offer were set forth in Fisher’s bid proposal.
The question now before us is whether Galway accepted Fisher’s offer. Initially, Fisher contends that Galway accepted Fisher’s bid proposal by using it in Galway’s general contractor’s bid to the Authority and that this acceptance was further confirmed by the Authority’s acceptance of Galway’s bid, in which Fisher was named as a subcontractor. We disagree.
There are no Pennsylvania cases precisely on point. However, many jurisdictions have rejected the notion that the use of a subcontractor’s bid by a general contractor constitutes legal acceptance of the bid.
See, e.g., Finney Co. v. Monarch Construction Co.,
“A subcontractor bidder merely makes an offer that is converted into a contract by a regularly communicated acceptance conveyed to him by the general contractor. No contractual relationship is created between the subcontractor and the general contractor even though the bid is used as a part of the general over-all bid by the general contractor and accepted by the awarding authority.”
Finney,
Our Supreme Court’s decision in
Hedden v. Lupinsky,
Here, Fisher made an offer to Gal-way, but Galway did not expressly accept Fisher’s offer. The use of Fisher’s bid proposal by Galway in its general contractor’s bid and the subsequent acceptance by the Authority of Galway’s bid did not amount to Galway’s or the Authority’s acceptance of Fisher’s bid. A contract is only formed when an offer is accepted, and this record is void of any evidence that Galway or the Authority conveyed to Fisher an acceptance of its offer. We conclude that the trial court did not err in determining that there was no contract between Fisher and either Galway or the Authority and, therefore, there was no contract between them for either to breach.
Next, Fisher contends that its proposal was accepted by Galway because Galway did not substitute Kiski until after the thirty-day time period within which Galway had to substitute any subcontractors pursuant to the contract between the Authority and Galway. (See Contract, 10/00, ¶ D.5, at D-3; R.R. at 19a.) Fisher claims that it is entitled to challenge the untimely substitution because it is a third-party beneficiary of the contract between the Authority and Galway. We disagree.
Our Supreme Court in
Scarpitti v. Weborg,
[A] party becomes a third party beneficiary [to a contract] only where both parties to the contract express an intention to benefit the third party in the contract itself, unless, the circumstances are so compelling that recognition of the beneficiary’s right is appropriate to effectuate the intention of the parties, and the performance satisfies an obligation of the promisee to pay money to the beneficiary or the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance.
Id.
at 372-73,
Here, the contract, which set forth the general conditions, supplemental general conditions, technical specifications, bonds and standard drawings for the Authority’s sewage treatment plant improvements project, was made for the benefit of the Authority and Galway. There was no express intent to benefit Fisher. Fisher was not a party to this contract, nor was he
Accordingly, we affirm.
ORDER
AND NOW, this 21st day of May, 2012, the June 17, 2011, order of the Court of Common Pleas of Washington County in the above-captioned matter is affirmed.
Notes
. We note that this is a pure contract case brought before the trial court. Although one of the parties is a municipal authority, this court does not have appellate jurisdiction because none of the criteria of 42 Pa.C.S. § 762 is satisfied, i.e., immunity, statute governing the affairs, etc. However, because this case was transferred here from the Superior Court and no party has objected to this court’s jurisdiction, pursuant to 42 Pa.C.S. § 704, jurisdiction has been perfected in this court. While we could still transfer the matter, in the interest of judicial economy and because no objections were raised, we will hear the appeal.
. We note that the contract does not contain the general contractor's bid proposal, but sets forth the requirements of the Authority for the sewage treatment plant improvements project.
. Our review of a trial court’s ruling on a motion for summary judgment is limited to a determination of whether the trial court committed an error of law or abused its discretion.
Fogarty
v.
Hemlock Farms Community Association, Inc.,
. Fisher was only mentioned in Galway’s bid proposal to the Authority, which was not part of the contract.
