Rhodes v. Hinds

79 A.D. 379 | N.Y. App. Div. | 1903

Spring, J.:

The lumber all the time belonged to the lumber company, and was stored in the plaintiff’s yard for its convenience, but the possession was really that of the lumber company, and the shipments were to be at its option and forty per centum of the contract price was to be deferred until after shipment.

The question is whether the plaintiff is entitled to recover for the value of the labor actually expended in manufacturing and *381piling the lumber destroyed. It is clear that he has no lien on the lumber for the money unpaid, for it was to be turned over to the lumber company and payment was to await the sales or delivery on board the cars, which is incompatible with the existence of a lien. ( Wiles Laundering Company v. Hahlo, 105 N. Y. 234.)

The crucial test is in this class of cases : Who was in default ? The title to the logs was in the lumber company. The lumber manufactured therefrom was also owned by it. The company furnished the property which was to be enhanced in value by the labor of the plaintiff. If it failed to furnish the logs for any cause it was in default. If there was a like failure as to the lumber the plaintiff could not perform. Without the fault of the plaintiff he is prevented from completing his contract. The fact that it is entire and its completion was to precede payment are not important because the lumber company, upon whom the obligation rested, is unable, by reason of the fire, to supply him the lumber to ship. It is urged that this is a harsh rule, as each party without any claim -must lose. But the situation of the parties to the agreement is not alike. The owner may protect himself by insurance. The plaintiff has no title and no lien and hence has no insurable interest. The plaintiff cannot perform because the defendant does not possess the property essential to render performance possible.

The counsel for the respondent invokes the principle that by the terms of the agreement complete performance must be accomplished before appellant may exact the enforcement of his compensation beyond the sixty per centum already paid, and if he expected to be relieved from the stringency of his agreement he should have protected himself against loss from the destruction of the property by fire by appropriate clauses in the contract. The counsel relies upon Harmony v. Bingham (12 N. Y. 99); Tompkins v. Dudley (25 id. 272); Herter v. Mullen (159 id. 28, 43), and kindred cases. In Tompkins v. Dudley (supra) the defendant contracted with the plaintiffs as trustees to erect a schoolhouse for a specified sum, payment in part to be made as the work progressed. Before the building was completed it was burned to the ground, and the plaintiffs were allowed to recover the sums paid to the defendant upon the contract. It will be observed that the builder during the performance of his agreement had the schoolhouse in his possession and *382completely under his dominion. He was able to insure his pay by a lien upon the property and to indemnify himself from loss by fire by insurance. In Harmony v. Bingham (supra) the defendants, who were common carriers, agreed by a contract under seal to transport merchandise for the plaintiff from Hew York city to Independence, Mo., within twenty-six days, for a stipulated freight charge, and a certain deduction was to be had for each day’s overrunning of the time. The defendant did not get the goods to their destination within-the twenty-six days, but declined to deliver the goods until the full freight was paid, which the plaintiff did under protest, and brought" suit upon the covenant for the freight paid, as well as for damages for breach of the agreement, and recovered. The defends ants claimed that they were prevented from delivering the goods because a canal along a' portion of their route had become impassable by a freshet, although the proof showed the route by Hew Orleans was known to .the defendants to be accessible. The Court of Appeals held that the covenants must control, and that the defendants were not excused from performance by the fact the canal was impassable. In these cases, as well as in others cited by the counsel for the respondent, the well-settled doctrine is reasserted that where a party has assumed a. charge or burden he is bound to perform, and inevitable or unforeseen accident is no excuse. •

We think the present case is to be distinguished in principle from those cited and others of cognate application. As has been already suggested, the company in this case not only owned the property and had it under its control, but it was to produce it for shipment. To be sure, the plaintiff undertook unqualifiedly to deliver this lumber and to complete his agreement before payment in full became due, but this undertaking must be construed in the light of the fact that it was the lumber of the company, and before plaintiff could perform he miist have the lumber to deliver. This principle is reinforced by the fact that the lumber remained piled after it had been sold for about ten days, and during this period the election of the time of delivery was with the company. The condition referred to, limiting necessarily the absolute undertaking of the plaintiff to ship the lumber, must have been within the contemplation of the parties when they made their agreement. (Stewart v. Stone, 127 N. Y. 500, 507.)

*383This feature relieves the plaintiff from liability for failure to perform, and may also prevent him from recovering beyond the value of the labor which he put upon the company’s property before its destruction. The work he did was in the fulfillment of the agreement, and as he is debarred from full performance by the default of the company, he may recover the actual value of his services in manufacturing and piling the lumber.

The authorities recognize the distinction adverted to. In Niblo v. Binsse (1 Keyes, 476), which seems to be a leading case, the plaintiff’s assignor contracted to do certain plumbing in a house owned by the defendant’s testator, to be completed at a given date, and part of the compensation to be paid as the work progressed, a certain sum upon its completion and the balance when it was tested and proved adequate. During the performance of the work the building burned without the fault of either party, and the contractor was permitted to recover for the work performed. The recovery was upheld upon the ground that the owner was in default in not furnishing the building, which was necessary to enable the contractor to carry out his agreement. In the same line are Whelan v. Ansonia Clock Co. (97 N. Y. 293); Hayes v. Gross (9 App. Div. 12); Dexter v. Norton (47 N. Y. 62); Butterfield v. Byron (153 Mass. 517) ; Haynes v. Second Baptist Church (88 Mo. 285; 57 Am. Rep. 413); Jones v. Judd (4 N. Y. 412). The present case, it seems to us, is much stronger for the plaintiff than any of those enunciating the principle upon which liability attaches, for in each of them the contractor or laborer had a lien for his services or materials on the thing upon which they were wrought or attached.

The doctrine in these cases does not conflict with the rule that one who agrees to perform before receiving compensation must comply with his undertaking, and if he seeks to be protected against inevitable calamity, must so stipulate in his agreement. That provision presupposes the lumber company has at all times done on its part whatever is essential to enable the plaintiff to perform strictly and fully.

An action was commenced by the plaintiff against the Star Lumber Company to recover for the claim contained in the complaint in this action. During its pendency the company became insolvent, a receiver of its property was appointed and the plaintiff *384was enjoined from prosecuting the action. Thereupon this action was commenced against the defendant, a director of said company, charging him with personal liability for said indebtedness by reason of the failure of said company to tile its annual reports as prescribed by section 30, chapter 688, Laws of 1892, in the years 1895 and 1896 when said statute was in force. It appears that a report in each of the said years was filed in the office of the clerk of the county of Jefferson, which was the proper county, but the same was verified in 1895 by the defendant as vice-president of the said company and in the following year by its president, but the secretary or treasurer of the said company did not join in such verification as the statute required nor was it filed in the office of the Secretary of State in compliance with the statute. These omissions render the defendant individually liable for the debt of the plaintiff. (Manhattan Co. v. Kaldenberg, 165 N. Y. 1.)

Our conclusion is that the judgment should be reversed and a new trial granted, with costs to the appellant to abide the event.

Adams, P. J., Williams, Hisoock and Hash, JJ., concurred.

Judgment reversed and new trial ordered,. with costs to the appellant to abide event, on questions of law only, the facts having been examined and no error found therein.

midpage