Rhinеlander Paper Company (Rhinelan-der) seeks review of orders’ of the Federal Energy Regulatory Commission (FERC or Commission) which renewed Rhinelan-der’s license to operate a hydroelectric project pursuant to the Federal Power Act (FPA), 16 U.S.C. §§ 791a et seq. Rhine-lander challenges two provisions of the license: one that retains the project’s historical property boundary (rejecting, pending preparation of a land management plan, Rhinelander’s proposal to remove a large portion of the property from the project boundary) and a second provision that requires Rhinelander to develop and implement a plan to monitor invasive plant species at the project. For the following reasons, we deny Rhinelander’s petition for review.
I.
On June 26, 1998 Rhinelander filed an application for a license to continue operating its 2.12 megawatt hydroelectric project on the Wisconsin River in Oneida County, Wisconsin, which has been licensed to operate since 1938. 1 In its application Rhi-nelander sought to modify the project’s boundary by removing from it some 2,478.5 acres, most of which is privately owned, out of a total area of 2,771 acres (excluding the rеservoir), leaving approximately 292.5 acres within the project.
In November 1999 FERC opened the proceeding to comments, motions to intervene, recommendations and terms and conditions. The Department of the Interi- or, United States Fish and Wildlife Service (FWS), intervened and submitted a letter dated January 3, 2000, which did not oppose approval of Rhinelander’s application but offered two reсommendations relevant here.
First, the FWS opposed Rhinelander’s request that FERC modify the project boundaries within the license terms. Expressing concern that some of the land that Rhinelander owned and proposed to remove might “have high wildlife and recreational values,” 1/3/2000 Letter from FWS to
Second, the FWS proposed requiring Rhinelander to work with the FWS and the DNR to monitor and control the spread at the project of exotic invasive plant species such as purple loosestrife (Lythrum salicaria) and Eurasian water-milfoil (Myriophyllum spicatum). The FWS acknowledged there was no evidence of the plants at the project at that time but noted infestation might become a problem over the term of the license.
In March 2003 FERC staff issued a Final Environmental Assessment (Final EA) of the license which addressed each of the two issues raised by the FWS. First, the Final EA recommended that FERC modify the project boundary as Rhinelan-der requested because the “2,478.5 acres of land that would be excluded from the current boundary is primarily a highly developed, privately-held residential area” which “would not be necessary to maintain project operations” and “their removal would neither diminish public access to the reservoir, nor have an adverse impact on sensitive environmental features.” Final EA at 90 (JA 235). Second, with regard to exotic and invasive plants, FERC’s Final EA acknowledged there was no apparent infestation at that time but “agreе[d] with the FWS recommendation to control the spread of purple loosestrife and Eurasian watermilfoil.” Id. at 78 (JA 229). Accordingly, the EA recommended that “Rhine-lander, in consultation with FWS and DNR, develop a plan .for Commission approval, to monitor purple loosestrife and Eurasian milfoil in project waters and implement measure[s] to control/eradicate these species, as appropriate,” id. (JA 229), agreeing with Rhinelander that “any control measures implemented by Rhine-lander should be limited to its own property.” Id. at 79 (JA 230). 3
On August 20, 2003, FERC’s Director of the Office of Energy Projects (Director) issued an order granting the license with the two provisions based on the FSW recommendations.
Rhinelander Paper Co.,
Rhinelander requested rehearing on the two contested issues, which FERC denied in a February 18, 2004 order.
5
Rhinelander filed a timely petition for review on April 16, 2004.
II.
“We review a Commission licensing decision under the FPA to determine whether it was ‘arbitrary and cаpricious.’”
Alabama Rivers Alliance v. FERC,
A.
We first consider FERC’s decision to retain the existing project boundary in *5 the new license. Under FERC’s regulations, a project boundary “must enclose only those lands necessary for operation and maintenance of the project and for other project purposes, such as recreation, shoreline control, or protection of environmental resources.” 18 C.F.R. § 4.41(h)(2). Rhinelander contends that the lands proposed to be removed are not “necessary” for operation of the hydroelectric project and that FERC was therefore required under its own regulation to remove the lands from the project boundary. We disagree.
FERC grounded its decision on section 10(a)(1) of the FPA, which directs:
That the project adopted, including the maps, plans, and specifications, shall be such as in the judgment of the Commission will be best adapted to a comprehensive plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, for the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat), and for other beneficial public uses, including irrigation, flood control, water supply, and recreational and other purposes [authorized under 16 U.S.C.] section 797(e) of this title[;] if necessary in order to secure such plan the Commission shall have authority to require the modification of any project and of the plans and specifications of the project works before approval.
16 U.S.C. § 803(a)(1). FERC has construed this section to impose on both the Commission and the licensee “statutory obligations to protect project shoreline and aquatic resources” which require that the project boundary encompass a “buffer zone area” adequate to protect the- surrounding environment.
See Georgia Power Co.,
The map Rhinelander filed with its 1998 license application, pursuant to 18 C.F.R. § 4.41(h), simply identifies (by number) the parcels making up the project property and, in the case of property owned by Rhinelander, identifies the particular public record(s) recording the conveyance of each to Rhinelander. It provides no other specific information about any of the parcels. Nor does the supplement, filed September 8, 2001, do much to fill in the gaps. It reveals little about the types or uses of the land to be removed — only that the “majority” is “in private ownership,” 8/7/2001 Letter from Douglas Spaulding to Rhinelander at 2 (JA 95) (filed 9/6/2001). Further, it provides only estimates of the amount of land in residential use and identifies the “undeveloped” land as “scattered in small areas throughout the area enсompassed by the current project boundary.” 6 Id. Given the generality of the information provided, FERC did not act arbitrarily or capriciously in requiring additional data about the specific location of the types of land to be removed — and, in particular, the relationship of the land to the shoreline— *6 to enable the Commission to make an informed determination of which land to remove from the project boundary. 7 Accordingly, we uphold FERC’s decision to require Rhinelander to submit a land management plan sufficient to resolve FERC’s concerns before modifying the project boundary.
B.
Next, Rhinelander challenges FERC’s requirement in Article 406 of the license that Rhinelander develop and implement an exotic species control plan. Rhinelander contends that the requirement is beyond the Commission’s authority under section 10(j)(l) of the FPA, which the Commission invoked to impose it. Section 10(j)(l) of the FPA directs in relevant part:
That in order to adequately and equitably protect, mitigate damages to, and enhance, fish and wildlife (including related spawning grounds and habitat) affected by the development, operation, and management of the project, each license issued under this subchapter shall include conditions for such protection, mitigation, and enhancement.
16 U.S.C. § 803(j)(l). Rhinelander contends that the spread of the two plant species is not caused by any activity related to operating a hydroelectric dam and that “the noxious weeds are therefore not an affect of the generation of hydroelectric energy,” Rhinelander Br. at 18 (emphasis original), so as to bring them within the ambit of the quoted statutory languаge. As a consequence, Rhinelander maintains, FERC has authority to impose the monitoring condition not under section 10(j)(l) but only as part of a “comprehensive plan” under section 10(a)(1). We believe that FERC reasonably construed section 10(j)(l) to authorize the requirement in Article 406.
We review an agency’s interpretation of a statute it is authorized to administer under the familiar two-step Chevron framework:
“We first ask ‘whether Congress has directly spoken to the precise question at issue,’ in which case we ‘must give effect to the unambiguously expressed intent of Congress.’ If the ‘statute is silent or ambiguous with respect to the specific issue,’ however, we move to the second step and defer to the agency’s interpretation as long as it is ‘based on a permissible construction of the statute.’ ”
Noramco of Del., Inc. v. DEA,
The verb “affect” means, very broadly, “to produce an effect on; to influence in some way.” Black’s Law Dictionary 92 (8th ed.2004);
see also
Webster’s Third New Int’l Dictionary 35 (1993) (“affect” means “to produce an effect (as of disease) upon”);
United States v. Wiant,
Rhinelander nonetheless contends FERC is foreclosed from imposing the requirements of Article 406 by its decisions in two other cases, in which the Commission “found that the agency-proposed monitoring and eradication recommendations were not proper.” Rhinelan-der Br. at 18. We believe Rhinelander reads too much into the decisions it cites.
In
Weyerhauser Co.,
For the foregoing reasons, the petition for review is denied.
So ordered.
Notes
. Since June 30, 2000, when its previous license expired, Rhinelandеr has been operating the project under an annual license pending disposition of its application.
. The FWS did not object to removing privately held residential property.
. According to FERC's rehearing order, the Final EA estimated an annual monitoring cost of $9,270. 106 F.E.R.C. at 61,557.
.Article 410 directs that within one year of license issuance Rhinelander submit a land management plan which
shall include, but not be limited to, the following: (1) establishment of • appropriate *4 buffer zones; (2) a detailed map that clearly identifies the Rhinelander Project boundary, Federal lands, lands designated residential use, undesignated lands, areas of special concern, such as an identified forested wetland; (3) describe the environmental and recreational effects from removing the 28.5 acres of Federal land from the project boundary; (4) describe the existing or future use of all the proposed land to be removed from the project boundary; (5) describe the timber management practices to benefit wildlife and protect other important resources; (6) identify designated public access for recreational use of project lands, except in areas where restricted access is necessary; and (7) аn implementation schedule.
104 F.E.R.C. at 64,346.
. Rhinelander also sought rehearing of the Director’s decision to grant a 30-year rather than a 40-year license. FERC granted rehearing on this issue and amended Rhinelan-der's license accordingly.
. With the supplement, Rhinelander submitted a topographical map, prepared by the United States Department of the Interior, Geographical Survey, on which the responses in the supplement were based. The map is no more informative than the supplement itself.
. Rhinelander claims it has been treated differently from other licensees that were permitted to remove land from their projects, citing
So. Calif. Edison Co.,
. FERC nonetheless imposed the control requirement under section 10(a)(1) because of its "beneficial effects."
