83 F. 593 | 8th Cir. | 1897
This case presents a contest for priority between a mortgage and mechanics’ liens upon a railroad. The mortgage was made on July 1,1889, and was recorded in November of that year, but no bonds were issued under it until April 10,1890. The mechanics’ liens were based on twp construction contracts, one of which was made on April 18, 1889, ¿nd work under it was completed on October 1, 1889; while the other was made on December 14, 1889, work under it was commenced at about that time, and was continued until about June 27, 1890, when it was completed. The appellee the Nebraska & Western Railway Company was the mortgagor, and the appellee the Manhattan Trust Company was the trustee to whom the railway company gave this mortgage to secure bonds to the amount of $2,583,400 which were to be issued under it. The appellants are the members of a partnership styled E. P. Reynolds & Co., which built the railroad covered by the mortgage under the two contracts which-have been mentioned. On December 18,1890, the trust company exhibited its bill for the foreclosure of the mortgage. On June 30, 1891, a decree of foreclosure was rendered. A gale was made under this decree, which was confirmed on October 30, 1891. Reynolds & Co. had not been parties to this suit, and on November 2, 1891, they filed a cross bill in it to establish mechanics’ liens for $37,400, which they claimed to be due upon their first construction contract, and for $13,-600, which they claimed to be due upon their second construction contract. They sought by this cross bill to charge the moneys in the hands of the court which were the proceeds of the foreclosure sale with a first lien in their favor. Their claim was contested by the trust company and the railway company, by answers which they filed to the cross bill; and bonds were given to secure the payment of the amounts of these liens in case they should be adjudged to be superior to that of the mortgage. The court dismissed the claim for the lien for the balance due under the first contract upon the face of the pleadings, and referred the questions of fact and law which arose under the claim for the balance under the second contract to Mr. William A. Redick, who reported the facts in detail, and found that the appellants had a lien upon the proceeds of the sale superior in equity to that of the bondholders under the mortgage. The trust company filed exceptions to this report, which were sustained by the circuit court, and a decree
The facts out of which this controversy arises are these: The mortgage, by its terms, covered the railroad, the franchises, and all the after-acquired property of the mortgagor, but the railroad was constructed by Reynolds & Go. under their contracts after the mortgage was made and recorded. On March 15, 1889, the railway company made a contract with, the Wyoming Pacific Improvement Company for the construction of its railroad. The substance of that agreement was that the improvement company would construct the railroad, and the railway company would pay for the construction $20,000 in cash and $20,000 in its first mortgage bonds for every mile of railroad that the improvement company built. On April 18, 1889, Reynolds & Co. made a contract with the improvement company, to the effect that: they would build about 80 miles of this railroad, and that the improvement company would pay them therefor in cash, on monthly estimates of the engineer. They finished the performance of this contract on October I, 1889. Their final estimate was settled by crediting them with $37,-400 upon the amount which they owed to the improvement company upon a subscription which they had made for $08,000 of its stock, and by paying them a balance of about $5,000 in cash. Thereupon, on October 8, 1889, they gave to the improvement company a receipt in full lor their claim against it under this first contract. The subscription which has been mentioned was made by Reynolds & Co. on A,pril 20, 1889. By the terms of the subscription contract, Reynolds & Co. agreed to pay to the Manhattan Trust Company, for the use of the improvement company, $08,000 in certain installments; and the improvement company agreed that, when these payments were completed, it would deliver to them first mortgage bonds of the railway company to the amount of $31,000 on or before April 20,1891, or as soon thereafter as issued, and negotiable certificates for stock of the improvement company to the amount of $37,100. They had paid several installments upon this subscription contract in cash, and, after the credit of the $37,100 which they had earned by the construction of the 80 miles of railroad under (he first contract, they still owed the improvement company on the subscription contract: $13,600 on December 11, 1889. On that day they made a second contract with, the improvement company for the construction of an additional 16 miles of the railroad, and immediately entered upon its performance. This contract contained an agreement of the improvement company to pay for the construction in cash on monthly estimates, and a promise that the $13,600 owing on the subscription contract: should not he declared in default, until the completion of, and the final settlement under, the construction contract. When this second construction contract was made, the mortgage had been made and recorded, but no bonds had been issued under it. On February 1, 1890, while Reynolds & Co. were engaged in the' performance of this contract, the Manhattan Trust Company and five other parties agreed to loan to the improvement company, and to pay over to the trust company, $1,050,000 for the purpose of purchasing the right of way and paying for the construction of the railroad which Reynolds & Co. were building. This promise was made on the ex
When Reynolds & Co. completed their second contract, in June, 1890, their final estimate was $66,173.97. They consented that the $13,600 which they still owed to the improvement compan;)', by the terms of their subscription contract, should be charged against this estimate, accepted the balance of the estimate in cash, and gave to the improvement company a receipt in full for all claims arising under their second construction contract. When this fact came to the attention of the trust company, on July 7,1890, that company credited the $13,600 on the subscription certificate of Reynolds & Co., and issued to them two certificates,- — one to the effect that they were entitled to receive on May 1, 1891, or as soon thereafter as they should be issued, mortgage bonds of the railway company to the amount of $34,000; and another that they were entitled to stock of the improvement company to the amount of $37,400. These certificates were subsequently assigned by J. H. Reynolds, one of the members of the firm of Reynolds & Co., for the firm, and were thereafter subdivided into several certificates of like character; but none of the bonds of the railway company and none of the stock of the improvement company has ever been tendered or delivered to Reynolds & Co., or to any member of the firm, on account of their subscription and its payment. On August 29, 1891, Reynolds & Co. filed, in the proper offices in the counties through which the railroad extended, accounts and affidavits of the materials they had furnished and the labor they had performed under these two con
The following facts were questioned, but, in our opinion, they are established by the evidence in this record: At the time that: Reynolds & Co. permitted the $13,600 which was due to them upon their seond construction contract t.o be applied in payment of their subscription, they did not know that all the bonds which the improvement company had received or was to receive from the railway company had been pledged by it as collateral security for its notes, and they assented to this application of the $13,600 in the expectation that they would receive the bonds aud a proper certificate for the stock called for by their subscription upon making their final payment upon it. They would not have consented to this application if they had known that: the improvement company had disabled itself from delivering the bonds. Tin; Manhattan Trust Company acted in these transactions foi- itself and as trustee and agent: for the railway company, the improvement company, and the lenders for whose benefit the bonds were pledged as collateral security. The trust company knew of the two construction contracts of Reynolds & Co., of their subscription to the stock of the improvement company, of the terms of their subscription contract, of the manner in which the two credits of $37,400 and $13,600 were made upon that contract, and it knew that those; sums represented the respective balances due them in money upon their construction contracts. It also knew at the time when the credit of $13,600 was made that all the bonds of the railway company which had been or could be lawfully issued had been pledged as collateral security for the debts of the improvement company, so that the latter could not deliver the bonds called for by the subscription contract of Reynolds & Co. E. P. Reynolds, Jr., was the managing partner of Reynolds & Co., and he was the only member of the firm who had authority to sign j he contracts or checks, or to handle the securities of the firm. He refused to accept for the firm the certificate for the bonds issued by the trust company on July 7, 1890. The indorsement of that certificate by J. H. Reynolds for the firm was without authority, and the trust company liad notice of this fact. The record discloses many other facts, but none that are material to the questions that must: be determined by this court.
The first question which demands consideration in this case challenges the action of the court in dismissing the appellants’ claim for a lien for $37,400 under their first construction contract. The labor and material bestowed upon a building' or a railroad by a contractor enhance the value of the property of the owner, and become lost to the builder. If he receives no compensation for them, he never can take them back, but the owner and those who take under Mm receive all their benefits. It is therefore just and equitable that the laborer and material man should have a lien for their wages, and for the value of their materials, upon the improvements which they construct; and statutes which authorize such liens should be liberally construed, to advance this reasonable and salutary remedy. Nevertheless, the me
“Suca verified statement or account must be filed by a principal contractor within ninety days, and by a sub-contractor within sixty days, from the date on which the last of the material shall have been furnished, or the last of the labor is performed; but a failure or omission to file the same within the periods last aforesaid shall not defeat the lien, except against purchasers or incumbrances in good faith without notice, whose rights accrued after the thirty or ninety days, as the case may be, and before any claim for the lien was filed: provided, that when a lien is claimed upon a railway, the sub-contractor shall have sixty days from the last day of the month in which said labor was done or material furnished within which to file his claim therefor: * * • provided further, that such lien shall continue for the period of two years, and that any person holding such lien may proceed to obtain a judgment for the amount of his account thereon by civil action; and when any suit or suits shall be commenced on such accounts within the time of such lien, the lien shall continue until such suit or suits be finally determined or satisfied.” Consol. St. Neb. 1891, §§ 2170, 2171.
It is insisted that the cross bill to enforce the lien under the first contract was not exhibited within the time of the lien. The work under that contract was commenced in the spring or summer of 1889, and was completed on October 1st of that year. The statute provides that the lien shall continue for the period of two years. The cross bill was not filed until November- 2, 1S91. The only question presented by these facts is, when did the two- years of the continuance of the lien commence to run? The lien undoubtedly attaches at the time when the contractor commences to perform his agreement, and it continues and grows pari passu with the work as it progresses, so that in one sense it commences and continues from the time when the performance begins. But it does not become fixed in amount or capable of enforcement until the. last act has been done to complete the performance of the contract, and it is only iron) that time that a vested lien for a determined amount can be said to exist and continue. It may be argued with considerable force that a lien exists and continues unimpaired, under the first part of section 2171, for 60'days after the last day of the month in which the performance of the contract is completed without the filing of any statement or claim to it, and that the subsequent proviso, which declares that it shall continue 2 years, extends the term of its existence for 2 years from the expiration of the 60 days. But that construction would continue it for 2 years and
The lien under the second contract stands in a different position. It attached to the property in December, 1889, when the appellants commenced the performance of that contract. At that time the mortgage to the trust company secured no bonds, — no debt, — -because no bonds had been issued and no mortgage debt had been created. Until bonds were issued and sold or hypothecated, the trust company held the trust deed as the mere agent of the railroad company, and was bound to release or dispose of it as that company directed. It had no superior right to or better claim noon the mortgaged property than the mortgagor itself. Iron Co. v. Eells, 32 U. S. App. 348, 363, 15 C. C. A. 189, 199, and 68 Fed. 24, 34. There is no doubt that the lien of a recorded mortgage securing bonds which have been issued or sold and pledged is superior to any claim or equity of a subsequently created debt of the mortgagor for the construction of the railroad mortgaged, which is not secured by a mechanic’s lien. Railroad Co. v. Hamilton, 134 U. S. 296, 299, 10 Sup. Ct. 546. But the debt of these subcontra dors was secured by a mechanic’s lien, which had attached, and was superior to the interests of both the mortgagor and the trustee under the mortgage, before any of the bonds it was to secure had been pledged or issued. It is true that the statute under which this lien was created required these subcontractors to file the statement of their lien within 60 days from the last day of the month in which their labor was done or their material was furnished, and that they did not file it until nearly a year after that timo had expired; but the statute also provided that “a failure or omission to file the same [the statement] within the periods last aforesaid shall not defeat the lien, except against purchasers or incumbrances in good faith without notice, whose rights accrued after the thirty or ninety days, as the case may be, and before any claim for the lien was filed.” The effect of this statute was to give to the subcontractors a lien upon the railroad which they constructed as against the owner, and as against all purchasers and incumbrancers under it whose rights accrued after they commenced the performance of their contract, and before the expiration of the 60 days after the last day of the month in which they completed it, without the filing of any statement or notice of their lien whatever. The theory and reason of the statute are that during the construction of the railroad, and for 60 days after the last day of the month in which the performance of the contract is completed, the new railroad itself shall be notice to all purchasers and incumbrancers of the lien of the subcontractors upon' it, and that all who take any title to or incumbrance upon the improvement or the right of way on which
It is contended, however, that the acts of the appellants in June and July, 1890, permitting the balance due on this construction contract to be credited on their contract of subscription for the stock of the improvement company, receipting for the amount due under the construction contract, and taking, indorsing, and' permitting a subdi
Finally, it is strenuously argued that this cross bill seeks relief through the rescission of the contract of settlement, which cannot be granted, because the appellants accepted the certificates for the bonds and stock issued under this settlement by the trust company, indorsed those certificates, and permitted them to be subdivided and reissued. It is true that it is a condition precedent to the rescission of a contract that he who has received or deprived the other contracting party of anything of value under it must return it, and restore the latter to his original situation. But this rule has no application to the case in hand, (1) because the certificates of the trust company which were issued under the settlement were never accepted or indorsed, but were rejected by the only member of the firm of Reynolds & Co. who had authority to act for them in the premises; and (2) because, if we concede that these certificates were indorsed by Reynolds & Co., they did not confer upon them or deprive the trust company or the improvement company of anything of benefit, advantage, or value. The improvement company had made a worthless promise, which it had disabled itself from performing. The certificates of the trust company were nothing more than its statements that the appellants were entitled to the fulfillment of this worthless promise. The trust company did not guaranty its performance, or obligate itself in any way to the appellants. Its certificates vested no rights and imposed no obligations. Their return to the trust company would neither have released an obligation nor conferred a benefit. Their return was therefore not a prerequisite to a rescission of the contract of settlement, because the law never requires the performance of an idle ceremony. Moreover, the joint acts of the improvement company and the trust company by which they pledged all the bonds to secure loans from strangers, and thus disabled the former company from delivering the bonds, were in themselves a distinct repudiation of the contract of settlement, and gave to the appellants the option to accept those acts as a rescission of the contract, and to recover the consideration they gave for it, or to bring an action against the improvement company for damages for breach of the contract. Smiley v. Barker, 83 Fed. 684; Nash v. Towne, 5 Wall. 689, 701; Ankeny v. Clark, 148 U. S. 345, 353, 13 Sup.