Reynolds v. Hart

42 Colo. 150 | Colo. | 1908

Mr. Justice Gabbert

delivered the opinion of tbe court:

Appellant, plaintiff below, brought suit before a justice of the peace to recover from appellee, as defendant, damages which he claimed to have sustained in not being permitted to complete a contract which he claims to'have entered into with the defendant. The case was appealed to the county court, and there tried before a jury. A verdict was rendered for the defendant, from which the plaintiff appeals. There being no written pleadings, the issues between the parties must be determined from the testimony.

Plaintiff testified that he was employed by the defendant to do thirty feet of assessment work on mining claims, for which he was to receive two dollars and a half per shift. He worked seventeen shifts, and was then, as he claims, discharged without cause. He was paid for the work performed.

Defendant testified that the contract with plaintiff was for no definite amount of work, but by the day or shift only; that the mines upon which the work was to be performed were situated at, or above, timber-line, and that it was necessary to perform the work on these- claims before snow-fall; that the contract between the parties was entered into some time in the month of September; that plaintiff quit the job and stayed away for nine or ten days; and that plain*153tiff voluntarily relieved him from the contract by writing him a letter to the effect that he might con•sider himself at liberty to hire someone else to do the work which he had engaged to perform.

It further appears from the testimony, .which is undisputed, that plaintiff did cease work for about nine days; that he notified defendant that his cessation of work was caused by the illness of his .wife; that he would resume work by a certain date if he was not notified to the contrary; that he did go to the property where the work was to be performed on that date, and on his way up, met the defendant and notified him that he was going1 to work; that the defendant made no objection to his resuming work; that he did work two days, and was then discharged.

It is evident that there were two issues which the parties sought to litigate: (1) Whether the contract was for a definite amount of work at so much per shift, or whether it was by the shift only; and (2) an abandonment of the contract, by plaintiff, either by ceasing work for such a length of time that defendant was justified in discharging him, or that plaintiff voluntarily released him from the contract.

The case having been submitted to a jury and a verdict rendered in favor of the defendant, his counsel here invoke the rule that a verdict based on conflicting testimony will not be disturbed on review. There are two reasons why this rule is not applicable to the present case: (1) It does not apply if the case is not submitted under proper instructions; and (2) when an issue has been submitted to the jury which is not in the case.

Instructions given submitted the case to the jury upon the theory that a verdict should be returned for-the defendant if it appeared from the testimony that plaintiff ceased work under his contract for an unreasonable length of time; or, if plaintiff, while *154absent from work, informed tbe defendant that he might not return, and defendant was at liberty to employ another to take his place.

From the testimony it is clear there was no issue of abandonment of the contract by plaintiff, either by ceasing work for an unreasonable length of time or notifying defendant that he was at liberty to- employ someone to take his place. An instruction which submits to the jury a question not in the case, is erroneous. — Walsh v. Jackson, 33 Colo. 454; Big Hatchet Con. M. Co. v. Colvin, 19 Colo. App. 405.

Assuming that in yiew of the .season of the year, the character of the work to be performed, and the location of the properties upon which the work was to be done, the defendant would be authorized to treat the contract as abandoned on the part of the plaintiff in the event he ceased work for an unreasonable length of time, and that plaintiff’s ceasing to work for nine or ten days was an unreasonable length of time, it appears that defendant failed to take advantage of his rights in this respect. He admits that he was notified by plaintiff that he would go up to work on a certain day, unless he was notified to the contrary ; that plaintiff did go that day, and on his way up met him; that he knew plaintiff was going to resume work, but, he did not notify him that he had elected to consider the contract terminated. It further appears that plaintiff did actually resume work for two days. A party who has the right to rescind a contract because of the default of another to such contract, must at least act with a reasonable degree of promptness after knowledge of such default; otherwise, he waives his right to rescind because of such default. — Auld v. Travis, 5 Colo. App. 535; Tilley v. Montelius Piano Co., 15 Colo. App. 204; 7 Current Law, 821; Dunn v. Steubing, 120 N. Y. 232.

So that the failure of the defendant to inform *155plaintiff that he had elected to terminate the contract because of his default, and permitting him to resume work without objection thereafter, was clearly a waiver of his right to take any advantage of plaintiff’s default, if he had that right.

The same rule applies to the instruction on the subject of plaintiff having offered to release defendant from his contract. He did not accept the offer, allowed plaintiff to resume work without objection, an'd, neither by act nor deed, indicated that he intended to avail himself of the privilege extended by plaintiff.

Outside of the question of damages we think there was but one issue between the parties — i. e., the terms of the contract. If, however, it could be successfully contended that there was such a conflict in the testimony on the question of abandonment or the release of defendant by plaintiff as to justify the submission of these -questions to the jury, then the instructions were erroneous; because they omitted, as to the first proposition, the question of whether or not the defendant had waived his right to insist on an abandonment, and, as to the second, whether he had accepted the offer of plaintiff to release him from his contract. When a court instructs a jury upon what state of facts a verdict must be returned against a party, the instruction must include all the facts material to the right of such party. — Gallegher v. Williamson, 23 Cal. 332; Deasey v. Thurman, 1 Idaho 775; Holmes v. State, 23 Ala. 17.

Plaintiff requested an instruction, which was refused, to the effect that if he went to work with the consent of defendant, and worked two days after the alleged abandonment of his contract, before he was discharged, that the defendant waived his right of pleading plaintiff’s abandonment, and a verdict should be returned in favor of the plaintiff. This *156instruction was rightly refused, because if there was any issue of abandonment in the case to be submitted to the jury, the instruction requested did not state all facts necessary for the jury to consider in connection with that question, in that both parties’ rights further depended upon whether the contract was by the shift only, or for a definite amount of work.

There is another question in the case — not mentioned, however, by counsel for defendant — and that is, whether there is any testimony to establish that plaintiff really suffered any damages; but as it is not discussed, we express no opinion upon it. We mention it, however, so' that it will not be assumed, in case of a re-trial, that this court held that the testimony in the present record established damages in favor of plaintiff, in case he established the contract as contended by him.

The judgment of the county court is reversed and the cause remanded for a new trial.

Reversed and remanded.

Chief Justice Steele and Mr. Justice Campbell concur.

midpage