Lead Opinion
By the Court,
In this appeal, we consider whether an indemnity clause in a construction contract between a general contractor and a subcontractor obligates the subcontractor to indemnify the general contractor for its partial negligence for constructional defects, regardless of whether the subcontractor is also negligent. In this, we must also determine whether the subcontractor’s testimony constituted a judicial admission by a party, rendering it automatically negligent and liable for indemnification. Additionally, we consider the scope of the indemnification clause’s duty to defend and appellant’s argument that attorney fees and costs in indemnity cases should be apportioned according to the percentage of negligence of the indemnitor.
This appeal arises from a constructional defect action in which a group of homeowners brought suit against the developer and general contractor, respondent Plaster Development Company, Inc. Plaster then filed a third-party complaint against its subcontractor, appellant Reyburn Lawn & Landscape Designers, Inc., based on Reyburn’s indemnification obligation and failure to defend Plaster pursuant to the indemnity clause in their contract. During trial, Plaster moved for and was granted judgment as a matter of law after the district court considered Reyburn’s owner’s testimony to be a judicial admission of liability. As a result of the order granting judgment as a matter of law, the district court precluded Rey-burn from submitting any jury instructions, limited the scope of Reyburn’s closing argument, and did not allow the jury to determine Reyburn’s liability for the constructional defects. Ultimately, the jury found Plaster 99 percent at fault.
Consistent with our holding in George L. Brown Insurance v. Star Insurance Co.,
Because the district court’s indemnification determination was based on its conclusion that Plaster was not solely negligent, since
Finally, based on our conclusion that the duty to defend extended only to claims connected with Reyburn’s potential negligence, we further conclude that any award of attorney fees to Plaster should have been limited to those fees and damages incurred defending against the causes of action concerning Rey-burn’s scope of work, not the entire amount of damages and all attorney fees and costs Plaster incurred throughout this eight-year litigation. We therefore reverse the district court’s judgment and remand this matter for a new trial.
FACTS
Historical facts
Plaster was the developer and general contractor of the Marble Canyon residential construction project in Las Vegas. The terrain of the'project required the use of retaining walls to support the residential building lots. The project also required the construction of sidewalls, which were not retaining walls, but rather served as “fence walls.”
Plaster contracted with Bill Young’s Masonry, Inc., to construct and backfill the retaining walls and to construct the sidewalls. Plaster contracted with Reyburn to perform the rough and final grading of the building lots, but Reyburn did not design or construct any of the retaining walls and sidewalls in Marble Canyon. Rough grading occurs after the concrete pad or foundation of the home has been poured and establishes the basic elevation and drainage of the lot. Finish grading occurs near the end of construction and, in this case, required Reyburn to apply four inches of sand, or topsoil, on the lot and grade it to allow water to drain away from the home, retaining walls, and sidewalls. The sidewalls were not constructed until after the final grading was completed. Once Bill Young’s Masonry finished building the sidewalls, Rey-burn completed its duties by clearing away any excess materials.
INDEMNITY: . . . Subcontractor agrees to save, indemnify and keep harmless Contractor against any and all liability, claims, judgments or demands, including demands arising from injuries or death of persons (Subcontractor’s employees included) and damage to property, arising directly or indirectly out of the obligation herein undertaken or out of the obligations conducted by Subcontractor, save and except claims or litigation arising through the sole negligence or sole willful misconduct of Contractor, and will make good to and reimburse Contractor of any expenditures, including reasonable attorney’s fees. If requested by Contractor, Subcontractor will defend any such suits at the sole cost and expense of Subcontractor.
Soon after homeowners moved into Marble Canyon in 1996, they made general complaints about both the retaining walls and the sidewalls. Eventually, they hired an independent engineer to evaluate the structural integrity of the walls, and the results, showing that the walls were engineered and installed improperly, were provided to Plaster. Plaster responded that the walls were in compliance with all applicable codes and had passed inspection.
Procedural facts
The homeowners filed a class-action complaint against Plaster in May 2000, alleging that their perimeter retaining walls and sidewalls were defective as a result of improper design, preparation, materials, and construction. In November 2001, 18 months after initiation of the litigation and 5 years after the homeowners first complained about the walls, Plaster, for the first time, notified Rey-burn of the alleged defects in the walls and tendered the defense of the defect claims to Reyburn. Stuart Reyburn, owner of Reyburn, would later testify that he received the tender of defense and attempted to contact Plaster’s counsel to inquire about the litigation, but Plaster’s counsel never responded. In any event, Reyburn did not take over the defense of the action. In March 2002, Plaster brought a third-party complaint against Reyburn and Bill Young’s Masonry for indemnity and/or contribution.
The homeowners, Plaster, and Reyburn proceeded to trial, which was held in the spring of 2004. The majority of the trial focused on the homeowners’ claims: whether the design of the re-
Near the end of the trial, Plaster orally moved for judgment as a matter of law against Reyburn on the contractual indemnity and breach of contract causes of action, claiming that Stuart’s testimony amounted to a judicial admission of liability. The district court granted the motion after minimal argument by counsel and without the benefit of briefing on the issues. The district court found that Stuart had admitted that placing sand over the drainage openings was within Reyburn’s scope of work and that it was a mistake to cover the drainage openings during final grading. The district court then explained that the evidence demonstrated that Plaster was not solely negligent in causing the damages and that the lack of sole negligence triggered the indemnity clause between the parties.
Under the ruling, the district court limited the scope of Rey-burn’s closing argument, precluded submission of jury instructions or a verdict form, and barred the jury from determining Rey-burn’s liability, if any. During deliberations, the jury sent a note to the judge asking where they could indicate their conclusions concerning Reyburn’s liability, but the judge directed them to fill out the verdict form “as is.” The jury ultimately awarded damages to the homeowners, attributing 1-percent fault to the homeowners and 99-percent fault to Plaster.
After the verdict was rendered, all parties filed post-trial motions. Reyburn sought reconsideration of the district court’s oral order granting judgment as a matter of law and moved for a new trial. Plaster moved for a determination of damages against Rey-burn on its indemnity and breach of contract causes of action, and the homeowners moved for an award of attorney fees, costs, and interest against Plaster. The district court held a hearing on the
As a result of the trial judge’s resignation, the case was assigned to Judge David B. Barker in 2007. In December 2008, Reyburn and Plaster renewed their post-trial motions. Judge Barker ultimately resolved the renewed motions in February and April 2009, five years after the conclusion of the trial, denying Reyburn’s motion for new trial and finding that Reyburn was required to indemnify Plaster for all of the homeowners’ claims. The district court then entered judgment for Plaster and awarded Plaster attorney fees and costs against Reyburn in the sum of $952,813.26, and interest in the amount of $582,264.18, based on Reyburn’s failure-to-defend contract claim.
Reyburn now appeals, arguing that the trial judge erred by granting Plaster’s motion for judgment as a matter of law on the indemnity and breach of contract claims and that it was error to order Reyburn to pay all of Plaster’s attorney fees and costs related to the suit.
DISCUSSION
In resolving this appeal, we must interpret the indemnity clause in the parties’ contract both as to damages and as to the duty to defend. In doing so, we first consider whether Reyburn’s negligence alone can trigger Reyburn’s duty to indemnify Plaster for liability on the retaining wall and sidewall claims, and then whether the covered liability extends to damages based on Plaster’s contributory negligence or merely to damages for Reyburn’s negligence. In this, we must consider whether the district court erred when it characterized Stuart’s testimony as a judicial admission of liability, triggering the indemnity clause, and, if so, whether a disputed factual issue as to Reyburn’s liability remains, such that judgment as a matter of law was precluded. Finally, we address whether Rey-burn had a duty to defend under the contract and, if so, whether Reyburn was responsible for the entirety of Plaster’s attorney fees and costs.
Interpretation of the indemnity clause
Typically, “[contractual indemnity is where, pursuant to a contractual provision, two parties agree that one party will reimburse the other party for liability resulting from the former’s work.” Medallion Dev. v. Converse Consultants,
In our recent decision in George L. Brown Insurance v. Star Insurance Co.,
Here, Plaster argues that the agreement’s scope was intended to indemnify Plaster for its own negligence so long as Plaster was contributively, not solely, negligent. Plaster explains that because the agreement expressly excludes indemnification for its sole negligence, the parties intended that Plaster would be indemnified for its contributory negligence. Therefore, according to Plaster, once it demonstrated that it was not solely negligent in causing the defects, the indemnification agreement was triggered. The district court agreed and determined that Plaster only needed to demonstrate that it was not solely negligent in order to invoke the indemnity clause and thus granted Plaster’s motion for judgment as a matter of law. We disagree and conclude that because the indemnity clause is not explicit about whether Reyburn is required to indemnify Plaster even if Reyburn is not negligent, and as to whether the scope of the agreement includes indemnity for Plaster’s contributory negligence, the clause necessarily covers only Reyburn’s negligence.
According to the indemnity clause at issue here, Plaster must be indemnified for “any and all” liabilities that “aris[e] directly or indirectly out of” Reyburn’s obligations under the subcontract.
Having determined that not only must Reyburn be partially negligent to trigger the indemnity provision, but also that the indemnity provision covers only Reyburn’s negligent acts, we now turn our attention to the district court’s conclusion that Reyburn was at least partially negligent when it granted judgment as a matter of law against Reyburn based on its findings that Stuart Reyburn made a judicial admission of liability.
Judgment as a matter of law — contractual indemnity
This court reviews a district court’s order granting judgment as a matter of law de novo. Winchell v. Schiff,
Toward the end of the trial, Plaster orally moved for judgment as a matter of law against Reyburn on Plaster’s contractual indemnity cause of action. After determining that the indemnity clause required Reyburn to indemnify Plaster once Plaster proved that the damages were not the result of Plaster’s sole negligence, the district court granted the directed verdict. In reaching its conclusion, the district court considered the testimony elicited from Stuart on cross-examination and determined that it constituted a judicial admission and proved that Reyburn was, at least, partially negligent for the damages and defects alleged by the homeowners. However,
Judicial admission
As Reyburn’s owner, Stuart testified at trial about the work performed by Reyburn under the subcontract. He described the process of final grading and was asked whether he was aware of the drainage system for the retaining walls. Stuart responded that
there’s no specific verbiage in the contract talking about drainage of walls . . . and based on what I’ve seen now, you know, there was some head joints [(drainage openings) in] some places and none other places.
He was also unsure whether there was some other type of mechanical drainage system in place, therefore, he was uncertain as to the drainage system applied to the retaining walls. Plaster’s counsel next asked Stuart about his standard practices when grading:
Q: Okay. So is it your normal practice on any job to make sure, for instance, if you’re going to do grading where you’re actually putting dirt against a wall, that you’re not covering up whatever drainage scheme is in place?
A: That would be a normal practice.
But what you need to understand is we’re not block wall experts. We don’t — that’s not our — that’s not our scope of work. I mean, we are there per contract, and per contract states we want four inches of topsoil over the entire lot.
So the lots are inspected by the city. They’re inspected by the supervisor]. That’s [another contractor’s] job. So if there was an issue at hand, you know, with us potentially [blocking] head joints, that would have been an easy fix.
But I think the thing that I need to stress is, is if there was dirt covering a head joint, dirt is not waterproof. I mean, it would still allow for the water to drain because we’re just putting in sand. We’re not compacting, nothing. We’re just laying sand. So if I had any sand over a head joint or partially blocking a head joint, the head joint would still be able to drain.
Stuart also testified that, as a general rule, a subcontractor should not cover drainage openings.
Plaster’s counsel then asked Stuart:
Q.: [I]f you and [Plaster] covered up — you know, raised the dirt in the upper lot above the waterproofing, that would be a mistake, right?
*343 A.: Yes.
Q.: And if you and Plaster raised the dirt up on the lower lot above the weep holes or the open head joints, that would be a mistake, correct?
A.: That’s correct.
Stuart then testified that he understood that Reyburn would be responsible to repair any work that was improper, but that he was uncertain about the legal implications of the indemnity clause. He ultimately testified that he understood that Reyburn would defend Plaster so long as Reyburn had proper notice of the defects and was given an opportunity to repair the problems. On cross-examination, Stuart testified that neither he nor Reyburn was ever notified that Reyburn had covered any drainage openings and that they had not received any complaints from Plaster or anyone else concerning Reyburn’s work.
“Judicial admissions are defined as deliberate, clear, unequivocal statements by a party about a concrete fact within that party’s knowledge.” Smith v. Pavlovich,
Stuart’s oral testimony was not a clear, unequivocal statement of liability nor did it admit a fact adverse to Reybum’s claims. Rather, Stuart’s testimony was responsive to hypothetical conditions or practices. He did not deliberately, clearly, and unequivocally testify that Reyburn covered any drainage openings or that any damages arose from Reyburn’s work. Thus, we conclude that the district
Conflicting evidence
In addition, a review of the record indicates that there was conflicting evidence regarding Reyburn’s negligence. Judgment as a matter of law should not be granted when there is conflicting evidence on material issues. Banks,
Reyburn’s duty to defend
The indemnity clause also imposes a duty to defend — “[i]f requested by [Plaster], [Reyburn] will defend any such suits at the sole cost and expense of [Reyburn].” This court has previously addressed an insurer’s duty to defend under an insurance policy, but has only generally discussed the duty to defend arising from an indemnity clause. See Allstate Insurance Co. v. Miller,
An indemnity clause imposing a duty to defend is construed under the same rules that govern other contracts. Crawford v. Weather Shield Mfg. Inc.,
Plaster argues that Reyburn breached its duty to defend by refusing to defend the allegations that involved Reyburn’s scope of work. Plaster relies upon Crawford for its contention that Rey-burn’s duty to defend was triggered by the filing of the homeowners’ complaint, regardless of Reyburn’s ultimate liability. In Crawford, the jury determined that the indemnitor was not negligent and, thus, the trial court determined that the indemnitor was not required to indemnify the indemnitee.
Similar to Crawford, the Indiana Court of Appeals also limited the defense costs under a duty to defend to those costs incurred from defending against the indemnitor’s scope of work. Henthorne v. Legacy Healthcare, Inc.,
Following the standards enunciated in Crawford and Henthorne, we now hold that unless specifically otherwise stated in the indemnity clause, an indemnitor’s duty to defend an indemnitee is limited to those claims directly attributed to the indemnitor’s scope of work and does not include defending against claims arising from the negligence of other subcontractors or the indemnitee’s own negligence. Accordingly, here we must first determine whether the district court properly granted Plaster’s motion for judgment as a matter of law on its breach of contract cause of action before we consider the extent of Reyburn’s obligation, if any, to pay for any of Plaster’s defense costs.
The district court, without much explanation, granted Plaster’s motion for judgment as a matter of law against Reyburn on its breach of contract cause of action, concluding that Reyburn had breached its duty to defend Plaster. In so doing, the district court relied upon evidence that indicated that Reyburn had received the tender of defense letter from Plaster and did not defend.
To invoke the duty to defend, the plaintiffs’ complaint must have sufficiently alleged negligence on the part of Reyburn, or their claims must have concerned Reyburn’s scope of work for the project. See Hughes Properties Inc.,
Defense costs
After the conclusion of trial, Plaster moved for a determination of damages against Reyburn. Approximately five years elapsed between the filing of post-trial motions and the district court’s award of attorney fees and costs to Plaster. During that time, the
Because we hold that an indemnitor’s duty to defend an indem-nitee is generally limited to those claims directly attributed to the indemnitor’s scope of work and does not include defending against the negligence of other subcontractors or the indemnitee’s own negligence, see Crawford,
CONCLUSION
We conclude that the indemnity clause in this case does not unequivocally or explicitly state that Reyburn would be required to indemnify Plaster, even if Reyburn was not negligent, and does not clearly require indemnification for Plaster’s contributory negligence. Therefore, the indemnity clause must be interpreted against Plaster, meaning that Plaster must prove negligence on the part of Reyburn before the clause is triggered and that Plaster may be in
Because Reyburn’s duty to defend Plaster is limited to those claims directly attributed to Reyburn’s scope of work and does not include defending against the negligence of other subcontractors or Plaster’s own negligence, we conclude that whether the homeowners’ complaint sufficiently alleged negligence on the part of Reyburn, triggering its duty to defend, was also a material issue of fact for the jury to decide. Thus, we conclude that the district court erred in granting judgment as a matter of law on Plaster’s breach of contract cause of action as well.
Finally, if the jury determines that the homeowners sufficiently alleged claims involving Reyburn’s scope of work, we conclude that the district court must apportion an award of fees and costs between those actually incurred by Plaster in defending against those claims directly attributable to Reyburn’s scope of work and those incurred in defending its own negligence.
Accordingly, we reverse the judgment of the district court and remand this matter for a new trial on Plaster’s indemnity and breach-of-contract-for-failing-to-defend claims against Reyburn.
Douglas, C.J., concurs.
Notes
One percent of the fault was apportioned to the homeowners.
Because we reverse on other grounds and remand for a new trial, we do not address Reyburn’s argument that the new district judge who was assigned to the case post-trial was not sufficiently familiar with the issues and evidence to determine the then-pending post-trial motions.
Prior to trial, Bill Young’s Masonry settled with the homeowners and was removed from the action.
This wall was replaced by Plaster prior to trial.
A majority of states have adopted some form of anti-indemnity statutes, “which, in one form or another, restrict, modify, or invalidate indemnification agreements contained in construction contracts.” 3 Philip L. Bmner & Patrick J. O’Conner, Jr., Bruner & O’Conner on Construction Law § 10:77 (2002). For example, California has adopted legislation that renders an indemnity clause void as against public policy if the agreement provides indemnity for the indemnitee’s “sole negligence or willful misconduct.” C.I. Eng. & Const. v. Johnson & Turner Paint,
Pursuant to the subcontract, Reyburn’s only obligation was to complete the rough and finish grading on the lots.
Plaster’s negligence is only mentioned in the context of Reyburn not having to indemnify Plaster if Plaster is found to be solely negligent.
Because we remand this case for a new trial, we do not address the extent of Reybum’s indemnification obligation to Plaster for damages, if any, resulting from defective sidewalls or retaining walls. This issue must be resolved by the district court based on the scope of Reyburn’s work or the allocation of negligence between the parties. See generally 3 Bruner, supra note 6, §§ 10:66-10:67 (discussing apportionment of liability between multiple at-fault parties, albeit in the context of indemnification agreements with different triggering language than the one at issue here).
Plaster did not send the letter tendering its defense to Reyburn until November 2001, 18 months after the initiation of litigation. Although the 18-month delay in receiving notice of its duty to defend was likely prejudicial, Reyburn again failed to raise this issue in the district court, so we do not consider it on appeal. See Albios v. Horizon Communities, Inc.,
Reybum also argues that Plaster should be precluded from seeking attorney fees through a post-trial motion because attorney fees arising from a breach of contract must be proved as special damages at trial. In Sandy Valley Associates v. Sky Ranch Estates, we distinguished between attorney fees as a cost of litigation and as special damages.
Because the indemnity clause in this case expressly authorizes attorney fees, regardless of whether the attorney fees could have been awarded as damages for breach of the contractual duty to defend, they were also directly authorized by the contract as a cost of litigation and can be considered in a post-trial motion. However, as discussed above, any award of attorney fees to Plaster and against Reyburn must be limited to Plaster’s fees incurred defending against the causes of action specifically concerning Reyburn’s scope of work or involvement in the project.
Concurrence Opinion
concurring:
I submit that the express negligence rule has less utility than the rule suggested in the Restatement (Third) of Torts: Apportionment of Liability § 22 cmt. f (2000), which holds that “An indemnitee can recover contractual indemnity for his or her own legally culpable conduct only if the contract is clear on that point,” but recognizes that, “[i]f the contract is otherwise clear, it need not contain specific words, such as ‘negligence’ or ‘fault.’” See George L. Brown Ins. v. Star Ins. Co.,
