Residents for Responsible Government v. GrannisResidents for Responsible Government v. Grannis
In 2000, CWM commenced communication with DEC about possible modifications to its permit, including substituting a technologically superior geosynthetic clay liner (hereinafter GCL) as a final cover for RMU-1 instead of the CCL. Over the next eight years, DEC conducted investigations regarding this change and other changes sought by CWM, the agency issued numerous notices of incomplete application with requests for additional information, and received revised applications as well as scientific research reports and technical information. CWM eventually narrowed its modification application to essentially seeking to use the GCL as a final cover and, since the final cover system with the GCL would be 2 1/2 feet whereas one using CCL would have been five feet, CWM sought to use the resulting extra 2 1/2 feet of air space available before reaching the maximum allowable height for additional waste disposal. This would extend the operational life of RMU-1 for up to one year by making an additional 106,870 cubic yards of space available, increasing the total waste of RMU-1 by about 3%.
CWM submitted an environmental assessment form with an April 2008 permit modification application and, after DEC initially found deficiencies in the application, a revised application followed in June 2008. DEC issued a negative declaration (see
We consider first petitioners’ argument that DEC violated
“Where a statute is ambiguous and its interpretation ‘involves specialized “knowledge and understanding of underlying operational practices or entails an evaluation of factual data and inferences to be drawn therefrom,” [we] defer to the administrative agency‘s interpretation unless irrational or unreasonable‘” (Matter of New York State Superfund Coalition, Inc. v New York State Dept. of Envtl. Conservation, 68 AD3d 1588, 1589 [2009], quoting Matter of KSLM-Columbus Apts., Inc. v New York State Div. of Hous. & Community Renewal, 5 NY3d 303, 312 [2005], quoting Kurcsics v Merchants Mut. Ins. Co., 49 NY2d 451, 459 [1980]). The language of
The next issue is whether DEC‘s determination of no significant impact is supported by the record. While petitioners do not dispute the superior quality of the GCL final cover system, they contend that DEC failed to take a hard look at the environmental impact of extending the operation of the RMU-1 for approximately one year. “Judicial review of an agency determination under [the State Environmental Quality Review Act] is limited to ‘whether the agency identified the relevant areas of environmental concern, took a “hard look” at them, and made a “reasoned elaboration” of the basis for its determination‘” (Matter of Riverkeeper, Inc. v Planning Bd. of Town of Southeast, 9 NY3d 219, 231-232 [2007], quoting Matter of Jackson v New York State Urban Dev. Corp., 67 NY2d 400, 417 [1986]). “It is not the province of the courts to second-guess thoughtful agency decisionmaking and, accordingly, an agency decision should be annulled only if it is arbitrary, capricious or unsupported by the evidence” (Matter of Riverkeeper, Inc. v Planning Bd. of Town of Southeast, 9 NY3d at 232; see Akpan v Koch, 75 NY2d 561, 570 [1990]).
Here, over the course of eight years, DEC required CWM to provide an array of reports and information regarding the effectiveness of GCL covers as well as ramifications resulting from the use of such a cover at RMU-1. In its negative declaration, DEC identified areas of environmental concern, including information regarding the superior nature of GCL covers, the resulting increase in capacity at RMU-1, the extension of the operational life of RMU-1 by approximately one year, and the similar nature of the operations during this extended time. DEC determined, and the record supports, that a GCL cover affords better protection, thus having a positive environmental impact. The agency also noted that allowing the GCL cover would decrease the truck traffic that otherwise would have been necessary to deliver clay for a CCL cover. Although truck traffic delivering waste would continue for the additional year, such
Spain, J.P., Stein, McCarthy and Garry, JJ., concur. Ordered that the judgment and order is affirmed, without costs.