32 N.Y.S. 976 | N.Y. Sup. Ct. | 1895
The complaint alleged two separate causes of action, growing out of two different contracts. As to one there is
“Fifth. It is mutually agreed between the parties hereto that, if the second party shall execute any part of such work defectively, then such defective work shall be rebuilt at the expense of the party of the second part, upon receiving the order from the engineer or engineers in charge to that effect.”
The referee found that the engineer in charge did not furnish to the defendant a certificate that the work had been performed in a substantial and workmanlike manner, nor make and deliver to the plaintiffs an estimate of the quantity of work done by the plaintiffs, all of which was, by the terms of the contract, a condition precedent to a right of recovery by the plaintiffs; and he further found that there was no proof of'a waiver of such certificate by defendant. In accordance therewith he held that the plaintiffs were not entitled to recover any sum whatever, and directed judgment accordingly. His report also directed that judgment should be entered dismissing the counterclaim set forth in the answer, but not upon the merits. With the reasons for the decision respecting the counterclaim as stated in the referee’s opinion, the appellant is dissatisfied. We shall refrain from a discussion of them, however, on this review, because we think the decision must be upheld upon other grounds, and it matters not whether proper reasons are given for rendering a correct judgment.
“He alleges that the plaintiff has broken the contract, or failed to perform it, and cannot, therefore, compel him to pay, and yet insists that he can compel the plaintiff to pay for defects in the work, for which» the latter gets no ■compensation. This, I apprehend, he can scarcely be allowed to do. He ■cannot both repudiate the contract, and enforce it, in the same action. Had (the defendant brought his action to recover damages for the nonperformance of the contract on the part of the plaintiff, it would have been necessary for
*979 him to allege performance or an offer to perform, on his part, or he would not have stated a cause of action. Certainly he is in no better situation in regard to his own counterclaim, as defendant. Having interposed the plaintiff’s breach, in avoidance of his own obligation to pay, and procured a ruling to that effect in his favor, he is in no situation to enforce the contract against the other party, in any particular, especially in the same action.” .
This case was cited and followed in Woodward v. Fuller, 80 N. Y. 312. The same question came before the court in Lennon v. Smith, 124 N. Y. 578, 27 N. E. 243. In that case the plaintiff contracted to build a cellar within a certain time, and it was agreed that a penalty of $20 a day should be enforced for each day the work should remain unfinished beyond the term. In an action brought to recover the contract price the referee decided that there was a substantial breach of contract upon the part of plaintiff available to defeat recovery by him; and, having decided that the defendant was entitled to be relieved from the obligations of the contract by reason of the breach by plaintiff, he proceeded to award damages in favor of defendant and against the plaintiff in the sum of $540 for nonperformance of the contract. In reviewing that judgment the court said:
“She could not repudiate the contract for the purpose of barring the plaintiff’s claim for his work, and at the same time make it effectual for the recovery of damages against him for its breach, although she might, if the facts permitted, recover damages, if any there were, in excess of the price or value of the plaintiff’s work. And the reason is that, in such case, the contract is permitted to remain operative for the purpose of the remedy and relief of both parties to it, and it is no less essential to support the defendant’s claim for damages than it is to sustain that of the plaintiff founded upon it for his work. It is apparent that a rule having the effect to give one of the parties to a contract the benefit of it to the exclusion of the other in the same action would or might work very unjustly to the latter, and quite unreasonably to the profit of the former.”
If it should be assumed in this case that the cause of action which defendant set up by way of counterclaim was a completed cause of action, nevertheless he was not entitled to recover on it,, because he interposed the plaintiffs’ breach of the contract to prevent any recovery by them, and obtained a decision in his favor, whereupon he deprived himself of the right to recover in that action damages against the plaintiffs because of such breach. Had he permitted a recovery by the plaintiffs for the amount due them under the contract, he would have been entitled, under the authority of Lennon v. Smith, and upon principle, to counterclaim his damages against them, although they might have largely exceeded the amount due to the plaintiffs under the contract; and for such excess he would have been entitled to an affirmative judgment against them.
If the views expressed are correct, it is unnecessary to consider the exceptions taken to the admission of evidence, and to the refusals of the referee to find certain facts which were requested by the defendant, for, if the rulings had been otherwise, the result could not have been affected. Presumptively both parties were entitled to costs, under section 3234 of the Code of Civil Procedure, but it does not appear that the defendant presented a bill of costs