16 N.Y.S. 313 | N.Y. Sup. Ct. | 1891
Lead Opinion
Although various causes of action were set out in the complaint, upon this appeal only the questions involved in the trial of the issues upon the first cause of action and the defendant’s counter-claim are brought up for review. The complaint alleges that the plaintiffs were co-partners in the firm of Reilly & O’Connor, and that in June, 1889, they entered into a contract with the defendant, whereby they agreed to execute, construct, and finish all the masonry work required to be done by the said defendant for the bridge to be constructed by the "Pennsylvania, Poughkeepsie & Boston Railroad Company across the Lehigh river at or near Slating-ton, Pa., for which the defendant agreed to make certain payments to them; that they entered upon the performance of this work, and carried out said contract in the manner and form in all respects as therein provided. The complaint further alleges that it was provided by the contract that when the work required to be done thereunder should have been completed, and the engineer in charge of the work have so certified, and made his estimate of the amount of work performed thereunder, the defendant should pay to the plaintiffs, within 20 days, the sum due to these plaintiffs under said contract. It was then alleged that the work had been fully performed and finished, and the engineer in charge of the work under said contract, more than 20 days before the commencement of the action, had certified that said work was completed, and had estimated the amount of the work done and money earned and due thereunder; that, according to the prices named in said contract, there was a certain sum due for the work done, of which a balance remains unpaid, which is sought to be recovered in said first cause of action. The defendant, by his answer, admitted the contract, denied its performance, and
One of the plaintiffs then testified that 20 or 30 days after the work was finished he asked the defendant if he had his certificate, and that the defendant replied that he had received the final certificate and estimate for the Slatington bridge, and that that was the only one he had received. He said he had been doing a good deal of grading, and that he could not pay the plaintiffs finally on this work, but would give $2,000 on account, and would pay the balance very soon,—within a week or two, in that neighborhood, or as soon as he got his affairs in shape. He further testified that about the same time he received from the defendant a statement of account, which he produced, in the hand
Upon the termination of the evidence the defendant’s counsel renewed his motion to dismiss the complaint as to the first cause of action upon substantially the same grounds hereinbefore mentioned, which motion was denied, and an exception taken. The plaintiffs’ counsel asked the court to direct a verdict, which the court granted, to which direction the defendant’s counsel duly excepted. It is a well-established rule that where both parties ask for a direction, although the evidence does not entitle the court to make a direction, the effect of the request is to submit thequestion of factfor determination by the court, and amounts to a waiver of trial by jury. O'Neill v. James, 43 N. Y. 84; Dillon v. Cockcroft, 90 N. Y. 649; Stratford v. Jones, 97 N. Y. 589; Provost v. McEncroe, 102 N. Y. 650, 5 N. E. Rep. 795; Kirtz v. Peck,
This error, as far as the final result of this appeal is concerned, renders it unnecessary to consider the question as to whether the certificate by Schafer is the certificate called for by the contract. But, as passing over this question upon this appeal might lead the trial court upon a new trial to an erroneous conclusion as to the views of the court upon this point, it is proper that we should present one or two considerations which lead us to the conclusion that Schafer’s certificate, even if the original had been produced, would not have been a compliance with the requirements of the contract. We think that the recital by which the contract is commenced indicates clearly who is meant by the engineer or engineers in charge# as the phrase is used in the •sixth clause of the contract, which clause relates, among other things, to the final certificate. The contract commences as follows: “These articles of agreement, * * * witnesseth that the second party,” (the plaintiffs) “for and in consideration of the covenants, stipulations, and agreements hereinafter mentioned, promises and agrees to execute, construct, and finish in every respect, in the most substantial and workman-like manner, and to the satisfaction and acceptance of the engineer or engineers in charge of the Pennsylvania, Poughkeepsie & Boston Railroad Company, all the masonry work required to be done by the first party,” (the defendant,) etc., clearly showing that it was the intention of the parties that the work should be done to the satisfaction, and acceptance of the engineer in charge of the railroad •company; and the object of making the contract in this form is apparent, because the work was being done for the railroad company, the plaintiffs being
Concurrence Opinion
I concur with the presiding justice that Primrose, who was the engineer in the charge of the road, and who was to determine when the plaintiffs had performed their contract, was the engineer who was to give the certificate which was a condition precedent to the right of the plaintiff to recover; but I think there was no evidence to justify the court in finding that the certificate required by the contract had ever in fact been given. The contract plainly contemplated a certificate that the work that plaintiffs agreed to perform had been “completely finished in every respect and performed agreeably to the various stipulations and specifications in the agreement,” and that to entitle plaintiffs to recover they must show that such a certificate had been given by the engineer in charge of the railroad to defendant. That certificate was distinct from either the provisional estimate, or the final estimate as to the amount of work done. The estimate simply stated the amount of work done. The certificate that was required was that the work had been performed according to the contract. Ho such certificate was offered in evidence, and the only evidence that can be said to relate to it is the statement of the plaintiff “that at the time I saw Mr. Lee he stated that he had this certificate. The work had been finished more than twenty days.” What this certificate was to which the witness alluded does not appear. Lee denies having made any such statement, and the testimony of witnesses called by defendant make it clear that no certificate of Primrose had ever been given, and that, as matter of fact, the work had not been completed according to the contract. The finding of the jury that a certificate as required by the contract had been given would, I think, have been clearly against the weight of evidence. I think that upon all the evidence it appears that plaintiffs never complied-with their contract, either in doing the work that they had agreed to do, or obtaining the certificate of the engineer of the road that the work had been completely finished and performed agreeably to the stipulations and specifications in the agreement; and the obtaining of such a certificate was a condition precedent to the plaintiff’s right to recover. I also concur with the presiding justice that it was error to admit the paper, Exhibit H, in evidence, and that the judgment should be reversed.
Daniels, J., concurs.